GENERAL This method statement describes the methodology for Emulsion Painting on surface of concrete and plaster in Factory 01 - SMC project... The concrete work, plaster work were cover
Trang 2Revision History
Submitted by ACSC
Prepared by Lê Long H uậu Deputy Site Manger
Reviewed by Nguy n Hoàng Trinhễn Hoàng Trinh Site Manager
Approved by Nguy n Văn Trungễn Hoàng Trinh Project Manager
Trang 31 INTRODUCTION 5
1.1 GENERAL 5
1.2 DEFINITIONS: 5
1.3 SCOPE OF WORK 5
1.4 BUILDING DESCRIPTION: 6
2 ORGANIZATION 8
2.1 ORGANIZATION CHART (Factory No.1) 8
2.2 ASSIGNMENT 8
3 SCHEDULE 9
4 SPECIFIC STANDARD 9
5 SCOPE OF EMULSION PAINTING WORKS: 10
6 FLOW CHART AND DIRECTION OF WORK 12
7 CONSTRUCTION METHOD 13
7.1 PREPARATION WORKS 13
a Scaffolding & platform: 13
b Mock-up: 13
c Tools: 13
d Preparation works: 13
e Surface preparation 14
7.2 SEQUENCE 14
7.3 APPLICATION: 15
a Putty application: 15
b Sealer Application 15
c Paint Application 16
d Spraying compound for Texture coats of Exterior Walls 16
8 RESOURCES 18
8.1 TOOL & EQUIPMENT 18
Trang 49.1 TOLERANCE: 20
a Preparation: 20
b Application: 20
9.2 INSPECTION: 20
a Inspection of Preparation 20
b Inspection of Painting 20
9.3 PROTECTION 21
9.4 DEALING WITH DEFECT 21
10 RISK ASSESSMENT 23
11 SAFETY PLAN 23
12 APPENDIX 24
11 QUALITY CONTROL
Appendix-1: Inspection test plan
Appendix-2: Construction schedule
Appendix-3: Risk Assessment
1 INTRODUCTION
1.1 GENERAL
This method statement describes the methodology for Emulsion Painting on surface of concrete and plaster in Factory 01 - SMC project
Trang 5Painting will be carried out after all constructions of relevant concrete structures such as slab, columns andplastering work completed The concrete work, plaster work were covered by another submittals, thereforethey will no longer discussed in this method statement.
Emulsion painting includes internal and external wall and
will be applied on the ground floor and the 1st/mezzanine
Floors of building Some ceiling and partition inside the
building are also the subject to be painted
In general, the paint coating will consist of putty, primer (or
sealer), undercoat and finish coat
Putty: This coat will fill into the rough surface of plaster and
cover it to form even, smooth surfaces before applying the
paint system
Sealers: This helps to prevent underlying as well as
subsequent coats from reacting with each other, while ensuring adhesion to the surface
Primer: Primers function to bind subsequent coats to the surface, while inhibiting deterioration of the paint
system as a result of rust, weathering or other forms of corrosion
Under coats: This intermediate coat prepares the surface for the finishing coat while giving opacity and film
build to the paint system
Finish coats: This finish coat to color the surface according to the design request.
Materials of painting are divided into two systems: interior and exterior Besides the differences of materialsuch as putty, primer, finish coat, the method to apply these two kinds are exactly the same
Depend on the architect design, there will be different colors to apply for the wall, ceiling, molding…
1.2 DEFINITIONS:
PROJECT PARTICULARS:
Project name : SMC MANUFACTURING (VIET NAM) FACTORY-PHASE 1 PROJECT
Address : Long Duc Industrial Park, Long Duc Ward, Long Thanh District, Dong Nai Province, Viet Nam
PARTY:
Client/ Owner : SMC MANUFACTURING VIETNAM CO., LTD
Contractor : KAJIMA OVERSEAS ASEA PTE LTD
Responsible for the supervision of Contractors who will construct the podium and all relatedactivities as outlined in this procedure
1.3 SCOPE OF WORK
The works to be carried out by Sub-Contractor (ACSC) and shall apply for works at Factory No.1 of SMC
Trang 62 Finishing works included:
- Building purpose :Factory
- Foundation : Spun piles (D300, 350, 400 mm)
- Structure : RC structures + steel rafter; Slab on grade
Trang 7o Factory Ground floor slab : 300 mm thk
o Storage/Utilities Ground Floor slab : 150 mm thk
Trang 82 ORGANIZATION
2.1 ORGANIZATION CHART (Factory No.1)
2.2 ASSIGNMENT
Position Factory No.1 Factory No.9
Deputy Site manager NGUYỄN TRÍ KHOA TRẦN AN TOÀN
Site Engineer NGUYỄN MINH TUẤN
NGUYỄN VĂN HÀO
LÊ VĂN TUẤTBÙI CÔNG HUYNHQA&QC Engineer PHAN QUỐC TRƯỜNG NGUYỄN ANH ĐỨC
Safety Supervision ĐỖ VŨ QUYỀN ANH PHẠM VĂN MẠNH
Deputy Site Manager 2
LÊ LONG HẬU (MP: 093 734 3055)
Nguyễn Minh Tuấn (MP: 098 314 5069)
Nguyễn Văn Hào (MP: 0938.722.730)
Trang 93 SCHEDULE
Construction Schedule of painting work is attached in Appendix-2
4 SPECIFIC STANDARD
Painting works should be carried out in accordance with the requirements of:
- SMC MANUFACTURING (VIET NAM) FACTORY-PHASE 1 PROJECT Specification finishing works
- Current Vietnamese Construction Standards
TCVN 6934-2001: Wall paints- Emulsion paints- Specification and test methods
TCVN 8652-2012: Wall emulsion paints- Specifications
TCVN 5674-1992: Finished works in construction- Execution, check and acceptance (group H)
TCVN 9405-2012: Wall paints- Emulsion paint- Methods for determination of resistance to damp heat
Trang 105 SCOPE OF EMULSION PAINTING WORKS:
Emulsion painting includes internal and external wall and will be applied from the ground floor to the 1st floor
of building Some ceiling and partition inside the building are also the subject to be painted
The painting types applied for Factory No.1 are defined as below:
No Painting application Area (m2)
All paints are Kansai with the detailed materials as below :
1/ Interior paint for walls:
Putty ECO Skimcoat for InteriorPrimer Primer for Interior 1 layerFinish coat ECO-V 2 layersColor code N90
2/ Kitchen ceiling:
Putty ECO Skimcoat for InteriorPrimer Primer for Interior 1 layerFinish coat Spring Clean 2 layersColor code N90
3/ Exterior Flat walls:
Putty ECO Skimcoat for allPrimer Primer Sealer 1035 1 layerFinish coat Weather Coat 2 layersColor code N85
4/ Exterior texture Paint:
Primer Primer Sealer 1035 1 layerTexture coat Kansai Texcoat 1 layerElastomeric coat Kansai Elastomeric coat 2 layersFinish coat Kansai Weather coat 2 layersColor code N85
Trang 12
6 FLOW CHART AND DIRECTION OF WORK
The work sequences of Painting on Concrete & Plaster are shown in the following flowchart
1 RC Structures, Plastered wall
Covered by previous submittal
2 Installing scaffolding & platform Start of Painting
3 Preparation of surface
4 Applying putty mastic layer
5 Applying primer coat
6 Applying under coat
7 Applying finish coat
8 Touch up & cleaning
End
Trang 137 CONSTRUCTION METHOD
7.1 PREPARATION WORKS
a Scaffolding & platform:
Safe and adequate scaffolding, platform, ladder will be provided to site before starting painting work
They will be installed ready before starting to conform with all applicable requirement of workers’ operation
Some of essential items are:
Sandpaper: for smoothing out uneven surfaces prior to painting
Sanding block: to keep the sandpaper
Scraper: to remove peeling paint from the surface
Turpentine: to wipe off oil-based paints easily
Clean rags: to wipe up splattered paint
Masking tape: to block off objects like light switches, sockets from being painted
Covers: old newspapers or canvasses can be used to cover the floor and furniture
Brushes and rollers: choose the right type according to purpose and surface As a rule, it is good to have
a large brush or roller, and at least one or two small brushes for tight corners
With some advanced paint techniques, make sure the correct tools to pull off the job, for e.g pencil liners,dragging brushes, shaped-stamp
Paint tray: to mix paints and contain the roller
Sticks: to mix and stir paints with
Appropriate filler: to fill cracks or holes in the walls
Filling knife: to fill the cracks
Sponge and squeegee mop: to wash down walls and ceilings respectively
Container: to soak brushes, rollers, etc and to hold other odds and ends
Extension pole: to reach higher areas
Ladder: if painting high up is necessary
Protective gear: like face masks, caps, gloves, etc
Trang 14- Make sure the surface is clean, grease-free and dry
- Wash surface with water & liquid detergent
- For heavy and stubborn stains: Use turpentine and wash thoroughly
- Fungus: Remove as above, followed by fungicidal wash or bleach
e Surface preparation
Protect all equipment, light switches, electrical sockets, window/door frames before applying the putty
All defects of substrate have been repaired and accepted Substrate surface shall be sound, clean, dryand free from void, dust, grease, oil, dust or laitance Surface cleaning with stiff bristle brushing isrequired Plaster nibs and splashes shall be scraped off, care being taken to avoid damaging thesurface
Mould growth can occur on plaster surfaces if drying out has been prolonged, especially in poorcondition of ventilation The affected areas shall be treated with a surface biocide and kept underobservation for a week or so, a further wash shall be applied if growth is renewed When growthhas ceased and the surface is dry, paint coats shall be applied
All defective or loose plaster, hollow plaster, unsquared wall corners, crack lines shall be repairedwith cutting and chipping out method then made good with the same type of cement mortar aspreviously used Use cutting machine to cut along marked lines at the depth of plaster thickness thenuse hand chisel to chip off plaster at cut areas
Slight cracks shall be made good with hard stopping, using gypsum paste with fine sand Largecracks to be cut out with the edges undercut, and filled with approved special cement, the edgesbeing closely knit and the filling being levelled with the surrounding surface
Uneven areas on substrate surface that is less than 2.0 mm or unsquared wall corners thatdiscrepancy of angle shall not exceed 2 degrees, the grinding method may be used to make surfaceflat but the grinding shall be well controlled and over grinding shall not be accepted
All groove lines of external and internal wall have been made correct in size and shape, location
- Paint the difficult areas like corners and edges first so that it will be easier to cover large areas later
- Paint should be applied in overlapping, continuous strokes Overlap strokes when moving from area to area
- Paint down or left-to-right, depending on which is more convenient Gently and lightly finish off in an down stroke if possible
up Always paint more than one coat of paint, allowing for appropriate drying time between coats
- Surface preparation : The new masonry surface must be smoothed with emery-paper or grindstone and cleaned
up Daub a putty mastic then smooth and fine before painting
- Mixing : Carefully read instruction of manufacturer on label of paint container For normal use thinning is notusually necessary, but if required up to 1 part of clean water to 10 parts of paint All ready-mixed paints must
be stirred thoroughly before use Stir until the colour of the paint is homogenous
- Practice: When the perfect putty mastic become dry and strong The primer sealer should be painted from 1 to
2 coats These coats help to resist alkalization, algae, fungi which is necessary to solidify the finish paint coats.When the primer sealer coats are dry perfectly, the finish practice should be painted with 2 coats that
Trang 15separated about 2 hours from each other
- Drying time : Depend on the kind of paint the drying time varies as follows: Touch dry : 15 ÷ 25 minutes; Dryingtime: 2÷4 hours
Practice:
Daub the putty on the surface at least two layers The putty mastic thickness of each layer should be less than 3 mm
The fisrt layer will be applied horizontally then vertically for second layer or vice versa
Using steel trowel to press the slurry to the wall/ceiling surface for first layer
Between the plastering of the first and second layer, using sanding block and sand paper to smooth out uneven surface
After the first layer has dried and been sanded, a second application will be made in a similar way
Repeat the sanding and touch up putty until get a smooth, fine, even surface
The total thickness of applied putty must not be more than 5.0mm thick
Wall surfaces around door openings and window openings shall be kept without putty
application for sealant application until completion of door and window installation
Putty application onto groove lines in walls shall be in required coats and sanded to make smooth surface, straight edges and aligned for paint application Pin holes, blow holes in wall plaster surface or concrete surface shall be filled up properly
Curing time for each applied layer shall follow strictly manufacturer’s instructions but shall not
be less than 24 hours before sanding
At areas where ceiling is to be installed, putty shall be applied along ceiling lines at least 10.0cmwidth above and below each side from the ceiling level then at least one finish coat to be applied for ceiling installation
Sanding work shall be carried out right after curing time finished
Trang 16- Substrate temperature shall not be below 10oC and above 35oC and at least 3oC above the dew point of the air.
- Subcontractor shall ensure the dilution, the consumption and the number of coats shall strictly conform to manufacturer’s instructions Thinning of sealer at site shall not be recommended
- Curing time for each applied coat to be re-coated shall not be longer than 4 hours The surface shall be dry and free from any contaminants prior to application of the subsequent coat
f Paint Application
Acrylic emulsion paint application shall conform strictly to manufacturer’s instruction
Substrate surface shall be checked for cleaning and temperature, moisture and recorded bySubcontractor before paint application Substrate surface condition records shall be submitted toKajima Vietnam as evidence during the final inspection of painting work
Use of scaffolding for interior wall painting shall not be allowed Ladder or chair ladder is required to
be used
Colour of paint to be applied shall be confirmed by Kajima Vietnam with approved colour samplepanel prior to application
Application of each coat shall be inspected by Kajima Vietnam prior to recoating and drying time
of each applied coat to re-coat shall not be less than 1 hours;
Paint consumption for each coat must be as required by manufacturer and wet film thickness
shall be measured with comb gauge at the time of application
Dilution of paint on site shall not be recommended In case a site dilution is required, conformance tomanufacturer’s instructions shall be taken and measuring tools and mixing equipment must be available
at site Without measuring tools and equipment, the dilution work shall not be started
No part mixing of 2 components products is allowed under any circumstances
Paint application method shall be in the same to all areas, except areas where using method ofapplication has not been suitable or cannot be used but the approval of Kajima Vietnam shall bereceived by Subcontractor before applying
Brush application may be allowed to areas where roller application cannot reach such as wall corners,groove lines, openings and positions adjacent to ceiling lines, etc…
Brush application shall follow the principle of perpendicular application of coats to avoid stripephenomenon of applied paint
For gypsum board ceiling painting, roller application is required Protection to floor and wall and otheradjacent items including MEP installed items during ceiling painting is required at the cost ofSubcontractor
For wall skirting painting, unless specified otherwise on the drawings or contract, paint for wallskirting shall be easy to clean, odourless and exterior paint system Line marking for skirting shall becarried out before wall paint application
For exterior wall painting, unless indicated otherwise on contract, Subcontractor shall providescaffolding system with dust mesh as protection to paint has just been applied from dust and strongwind In case it is raining during exterior painting, painting shall be stopped and only re-started whensubstrate surface has checked and met requirements for moisture and temperature Failure of exteriorpaint application caused by raining shall be re-applied after removal of failed paint coats at the cost ofSubcontractor
g Spraying compound for Texture coats of Exterior Walls
Mask all adjacent areas (with sufficient area and adhesive properties)
Spray.