CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2 Architects & Construction Service Corporation Reviewed by Nguy n Hoàng Trinhễn Hoàng Trinh Site Manager Approved by Nguy n Văn Trungễn Hoàng Trinh Pr
Trang 1METHOD STATEMENT
SMC Manufacturing (Vietnam) Factory-phase 1 Project
BRICK WORK & PLASTER WORK FACTORY No.1
Ref No:
SMC-ACS-MS-01-BRW-001 Rev 02
ACSC- CONG TY CO PHAN XAY LAP THUONG MAI 2
Trang 2CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation
Reviewed by Nguy n Hoàng Trinhễn Hoàng Trinh Site Manager
Approved by Nguy n Văn Trungễn Hoàng Trinh Project Manager
Trang 31 INTRODUCTION 4
1.1 PURPOSE 4
1.2 DEFINITIONS: 4
2 BUILDING DESCRIPTION: 5
3 ORGANIZATION CHART 8
3.1 Organization Chart (Factory No.1) 8
3.2 Assignment 9
4 SCHEDULE 9
5 SPECIFIC STANDARD 9
6 SCOPE OF WORKS: 10
7 FLOW CHART AND DIRECTION OF WORK 13
8 PREPARATION WORKS 14
9 CONSTRUCTION METHOD 14
9.1 Brick work: 14
1 Mortar & mixing mortar 14
2 Wall ties (Dowel bars): 15
3 Brick wall construction method: 16
4 RC lintel & siffener 18
5 Work sequence: 19
9.2 Plastering work: 21
1 Mortar & mixing mortar 21
2 Construction method: 21
3 Work sequence: 25
10 RESOURCES 27
10.1 TOOL & EQUIPMENT 27
10.2 MATERIALS 27
1 Type of material: 27
2 Materials handling, storage and delivery 27
11 QUALITY CONTROL 29
12 RISK ASSESSMENT 30
13 SAFETY PLAN 30
14 APPENDIX 31
Trang 4CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation
Most of brickwork are for walls of Utilities Building and will be applied from the ground to 1st floor ofbuilding All walls will close the spaces between concrete structures of column to column and slab toslab, therefore they are classified in non-load-bearing walls
There will be some openings on the brick wall at location of doors and windows Around theseopenings, reinforcement concrete stiffener and lintel beams will be cast before to carry out the brickwalls
After brick walls have been completed, the plastering will be applied on both sides of them, if any
1.2 DEFINITIONS:
PROJECT PARTICULARS:
Project name : SMC MANUFACTURING (VIET NAM) FACTORY-PHASE 1 PROJECT
Address : Long Duc Industrial Park, Long Duc Ward, Long Thanh District, Dong Nai Province,
Viet Nam
PARTY:
Client/ Owner : SMC MANUFACTURING VIETNAM CO., LTD
Contractor : KAJIMA OVERSEAS ASEA PTE LTD
Responsible for the supervision of Contractors who will construct the podium and all related activities as outlined in this procedure
SCOPE OF WORK
The works to be carried out by Sub-Contractor (ACSC) and shall apply for works at Factory No.1 of SMC
MANUFACTURING (VIET NAM) FACTORY- PHASE 1 PROJECT
1 Construction Reinforcement Concrete Structure works included:
a Pile head treatment
b Earth work
c Formwork
d Reinforcement Steel Rebar work
e Concrete work
Trang 52 Finishing works included:
- Building purpose : Factory
- Foundation : Spun piles (D300, 350, 400 mm)
- Structure : RC structures + steel rafter; Slab on grade
Trang 6CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation
o Factory Ground floor slab : 300 mm thk
o Storage/Utilities Ground Floor slab : 150 mm thk
Trang 7GFL+11.900T.O.BEAMGFL+13.650T.R.BEAM
CANOPY; STEEL BEAM
CORRIDOR ZINC ROOF SHEET
Trang 8CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation
TYPICAL CROSS SECTION
Trang 9Deputy Site Manager 2
LÊ LONG HẬU (MP: 093 734 3055)
Nguyễn Minh Tuấn (MP: 098 314 5069)
Nguyễn Văn Hào (MP: 0938.722.730)
Trang 10CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation
3.2 Assignment
NGUYỄN VĂN HÀO
LÊ VĂN TUẤTBÙI CÔNG HUYNH
4 SCHEDULE
Construction Schedule of Brick work and Plaster work is attached in Appendix-1
5 SPECIFIC STANDARD
Brick work and plastering works shall be carried out in accordance with the requirements of:
- SMC MANUFACTURING (VIET NAM) FACTORY-PHASE 1 PROJECT Specification for Concrete works
- Current Vietnamese Construction Standards
1 TCVN 7572 & 7570 Test method & Acceptance for Coarse & Fine Aggregates
2 TCXD 127: 1985 Fine sand for concrete and mortar, use of fine sand
3 TCVN 2682:2009 Specification for Portland Cement
4 TCVN 5438: Cements – Terminology and Definitions
5 TCVN 9202: 2012 Cement for brick work and plastering work- Masonry Cement
6 TCVN 6260: 2009 Portland Cement Mixtures – Technical Requirements
7 TCVN 4506:2013 Water used for mixing concrete & cement mortar
8 TCVN 5992: 1995 Sampling water for testing
9 TCVN 6492: 1999 Determination of pH of water
10 TCVN 2671: 1978 Determination of organic contaminants in water
11 TCVN 4560: 1988 Determination of total dissolved salt content in water
12 TCVN 3118: 993 Method for determination of concrete strength
13 TCVN 9115: 2012 Assembled concrete and reinforced concrete structures
-Practice for erection -and acceptance
14 TCVN 1450: 2009 Hollow burnt clay bricks
15 TCVN 1451: 1998 Solid burnt clay solid bricks
16 TCVN 6477: 2011 Concrete blocks
17 TCVN 5593 : 1991 Building engineering work - Permissible tolerances in geometry
18 TCVN 9377-2:2012 Finishing work- Construction and acceptance- Part 2: Plastering work
19 TCVN 3121-1:2003 Mortar for masonry - Test methods Part 1: Determination of
maximum particle size of aggregate
20 TCVN 3121-2:2003 Mortar for masonry - Test methods Part 2: Sampling and
preparation of sample
21 TCVN 4314: 2003 Mortar for masonry – Specifications
22 TCVN 6355-2:2009 Bricks – Test Methods Part 2: Determination of
Trang 1126 TCVN 4459:1987 Cement mortar mixing and use of cement mortar
F
1st FLOOR WALL LAYOUT
Trang 12CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation
Based on the characteristics of walls, they are divided into the types as below:
- Type MW + B80a & MW+DW 75i : 80mm thk ,1.10m high
Mostly this type is applied for the perimeter wallscombined with metal siding or insulation walls:
o On Ground floor: mostly placed on grid A1,E1, 15, 15A
o On 1st Floor: mostly placed on grid A1, E1,
80 mm thk, full height from floor to the ceiling
These wall types are mostly applied for the inside and dividing walls of the rooms in Office, Utilities area on ground and 1st floor
Depending on the finishing, these walls will be applied with plastering, painting or tiling
INSIDE
MW+B80b INSIDE
STEEL PARTITION
METAL SIDING LGS 75
BRICK WALL PLASTER w/PAINT
METAL SIDING BIRDNET
BRICK WALL PLASTER w/PAINT
METAL SIDING FLASHING
BRICK WALL PLASTER W/PAINT
METAL SIDING FLASHING
BRICK WALL PLASTER W/PAINT
R.C LINTEL 80x200 PLASTER w/ PAINT
R.C LINTEL 80x200 PLASTER w/ PAINT
(12.5 kg/ m³)t 50 w/ PAINT
FLASHING
FLASHING
BRICK WALL+ TILE
GYPSUMBOARD 12.5THKLGS 75
8015 105
PLASTER w/ CERAMIC TILE
BRICK WALL
WALL TYPE LEGEND
8015 120
PLASTER w/ CERAMIC TILE
BRICK WALL PLASTER w/PAINT
8015 130
PLASTER w/ CERAMIC TILE
BRICK WALL PLASTER w/TILE
8015
PLASTER w/ CERAMIC TILE
(FIRE RATED WALL)
STEEL PARTITION
METAL SIDING LGS 75
BRICK WALL PLASTER w/PAINT
METAL SIDING BIRDNET
BRICK WALL PLASTER w/PAINT
METAL SIDING FLASHING
BRICK WALL PLASTER W/PAINT
METAL SIDING FLASHING
BRICK WALL PLASTER W/PAINT
INSIDE INSIDE GLASS WOOLINSULATION
(12.5 kg/ m³)t 50 w/ PAINT
FLASHING
FLASHING
BRICK WALL+ TILE
B80T0 B80T1 BRICK WALL+ TILE B80T2 BRICK WALL+ TILE B80P0 BRICK WALL+ PLASTER B80P1 BRICK WALL+ PLASTER B180P1 BRICK WALL+ PLASTER DW75i LGS 75+GYPSUM BOARD
GYPSUMBOARD 12.5THKLGS 75
8015 105
PLASTER w/ CERAMIC TILE
BRICK WALL
WALL TYPE LEGEND
8015 120
PLASTER w/ CERAMIC TILE
BRICK WALL PLASTER w/PAINT
BRICK WALL PLASTER w/TILE
PLASTER w/ CERAMIC TILE
(FIRE RATED WALL)
Trang 13METAL SIDING LGS 75
BRICK WALL PLASTER w/PAINT
METAL SIDING BIRDNET
BRICK WALL PLASTER w/PAINT
METAL SIDING FLASHING
BRICK WALL PLASTER W/PAINT
METAL SIDING FLASHING
BRICK WALL PLASTER W/PAINT
R.C LINTEL 80x200 PLASTER w/ PAINT
R.C LINTEL 80x200 PLASTER w/ PAINT
(12.5 kg/ m³)t 50 w/ PAINT
FLASHING
FLASHING
BRICK WALL+ TILE
8015 10
PLASTER w/ CERAMIC TILE
BRICK WALL
WALL TYPE LEGEND
8015 12
PLASTER w/ CERAMIC TILE
BRICK WALL PLASTER w/PAINT
BRICK WALL PLASTER w/TILE
PLASTER w/ CERAMIC TILE
(FIRE RATED WALL)
180 mm thk, full height from floor to the ceiling
This wall type is applied for the inside wall of Electricroom on Ground floor and the wall at connection corridor
STEEL PARTITION
METALSIDINGLGS 75
BRICK WALLPLASTER w/PAINT
METALSIDINGBIRDNET
BRICK WALLPLASTER w/PAINT
METALSIDINGFLASHING
BRICK WALLPLASTERW/PAINT
METALSIDINGFLASHING
BRICK WALLPLASTERW/PAINT
PLASTERw/ PAINT
GLASS WOOL(12.5 kg/ m³)t 50w/ PAINT
FLASHING
FLASHING
BRICK WALL+ TILE
GYPSUMBOARD 12.5THK
LGS 75
PLASTERw/ CERAMIC TILE
BRICK WALL
WALL TYPE LEGEND
PLASTERw/ CERAMIC TILE
BRICK WALLPLASTER w/PAINT
PLASTERw/ CERAMIC TILE
BRICK WALLPLASTER w/TILE
8015
PLASTERw/ CERAMIC TILE
(FIRE RATED WALL)
Trang 14CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation
7 FLOW CHART AND DIRECTION OF WORK
The work sequence of Brick work and Plastering works are shown at the following flow chart
1 RC Structures (Columns, slab, wall)
construction Covered by previous submittal
2 Installing wall ties from columns Start of Brickwall
3 Positioning wall by marking on slab, column
4 Preparing working scaffolding & platform
5 Preparing brick & mortar
Trang 15All brick units shall be moistened by water 1- 2 hours before executing the construction.
D Scaffolding preparation:
+ Scaffolding will be installed aside the wall and be propped/braced securely
+ Install platform and handrail on each story of scaffolding
+ Provide the ladder on scaffolding from the ground to the working level
9 CONSTRUCTION METHOD
9.1 Brick work:
1 Mortar & mixing mortar
Sand for mixed mortar shall be natural sand free from any deleterious materials such as clay, flaky or elongated particles, mica, shale or other laminated materials, organic impurities,iron pyrites Sand shall be clean, hard, durable, crushed It shall be thoroughly washed and all dirt, shells etc removed before use
Water for brick work shall be clean and uncontaminated potable water from the city main supply or any other approved source free from harmful matter
Mortar type to be used shall be sand-cement mortar, class mark #100 (28days compressive
strength 10 Mpa) with its proportion: 1 part of cement: 3 part of sand in volume
Trang 16CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation
The mortar proportion will be verified with the result of trial mix on site and testing prior to beuse
Mortar will be mixed by mixer which has capacity of 100 liters on site Material of mortar will
be measured in containers with defined volume to maintain control and accuracy of proportion.Mix by placing one-half the water and sand in operating mixer Then add cement and remainder of sand and water Mix batch for not less than 3 minutes after all ingredients are in the mixer
Workability or consistency of mortar on the board shall be sufficiently wet to be worked underthe trowel Water for tempering shall be available on the scaffolding at all time Mortar which has
begun “set” two (2) hours after initial mixing will be discarded
2 Wall ties (Dowel bars):
Dowel bars shall be installed at the spacing of 400mm for each skin of wall (one layer for single wall and 2 layers for Double wall)
Wall ties are made of steel bars of D6, 400mm long (100mm embedded in concrete, 300 mm exposed) The diameter of drilled holes in RC items for installation shall be 8.0mm
Wall ties will be inserted in the columns by drilling and applying of bonding agent (Sikadur 731) The diameter, depth of drilling as well as application of bonding agent will strictly follow theinstruction of manufacturer
With the stiffeners, what will be cast after laying brick wall, the wall ties will be placed in the brick wall during construction Then these wall ties will be embedded in the concrete of
stiffeners
RC Column
Trang 173 Brick wall construction method:
as damp-proof course on the slab
b) Brick wall forming:
Laying brick course by course to build the wall On every course of straight wall as well as at intersection of them, their brick units will be staggered with the previous course to avoid coincidence of vertical joint in brick block
The first course and top course of brick walls shall be of solid bricks
Mortar will be laid to form joints between courses of brick The width of horizontal and vertical joints shall be 10.0 mm wide and joint shall be fully filled with cement mortar and compressed by steel trowel
Horizontal joints shall be level and neatly pointed around as the work proceeds within
tolerance of ±10 mm / 5m Vertical joints shall be plumb and in alignment from top to bottom
of wall within a tolerance of ±5 mm / 3m.
Single S k in Bri c k Wa l l s The bricks for single skin walls shall be hollow bricks and the wall thickness shall be of 80.0mm thick
Double Skin Bri c k Wa l l s Bricklaying shall be 1 course of headers to 5 courses of stretchers in order
The gap between skins shall be filled up with mortar before laying the headers.The bricks for double skin brick walls shall be hollow bricks for stretchers and solidbricks for headers, the wall thickness shall be 180.0mm thick with a 20mm gapbetween two skins
Trang 18CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation
Prior to resuming masonry work, remove loose units and loose mortar, clean exposed surfaces
of set masonry and wet units lightly
c) Application:
Brick will be generally laid in running bond
- Form bed joints of thick layer of mortar slightly furrowed or battered
- Bevel or pyramid the bed mortar
- Form head joints by applying a full coat of mortar on the brick to be laid
- First layer will be solid brick
- Lay closure brick with mortar on each bedding surface of unit to be laid and units in place
- Place brick carefully without colliding to brick previous laid
- Strike flush joints Tool vertical joints first then brush joints to remove all loose and excess mortar
- Repeat this sequence for next course
d) Cleaning, curing and protection:
- Remove immediately concrete scum, mortar and grout stain on the wall during construction
- After the wall is constructed it should not be saturated with water for curing or any other purposes
Trang 19- When or where the atmosphere is dry, the masonry wall shall have its surface dampened with
water during a curing period for the mortar of 3 (Three) days.
- Protect completed work:
(a) Keep completed walls clean and protect from staining
(b) Cover top of walls with waterproof covering or membrane to prevent rain or mortar stain
(c) Do not apply uniform loads for at least 12 hours or concentrated loads for at least
72 hours after masonry is constructed
4 RC lintel & siffener
On the wall, there will be some openings to fix the door or window later Dimensions of these openings will be set by adding the dimensions of door (or window) a tolerance of about 2,5
cm for installation
Openings on brick wall will be formed and supported by Reinforced concrete stiffener and lintel around its boundary
Stiffener beams and columns shall also be provided to wall for each 15 m2:
Where the length of wall is longer than 5.0m (Stiffener columns)
Where the height of wall is higher than 3.0m (Stiffener beams) Typical section of stiffener (columns and beams) in Factory No.1 building will be:
For single skin: Dimensions: 8 x 20 (cm), reinforced with main bar of 2D12 and stirrup
TYPICAL STIFFENER SECTION