1. Trang chủ
  2. » Kỹ Thuật - Công Nghệ

Method statement of Tiling work

19 678 5

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 19
Dung lượng 0,92 MB

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Nội dung

PURPOSE This method statement describes the methodology for tiling of wall and floor at SMC project Tiling work will be carried out after all constructions of relevant structures such as

Trang 1

SMC Manufacturing (Vietnam) Factory-phase 1 Project

TILING WALL & FLOOR FACTORY No.1

ACSC- CONG TY CO PHAN XAY LAP THUONG MAI 2 Ref No:

SMC-ACS-MS-01-TLW-001

Trang 2

Revision History

Revision Date of issue Purpose of issue (approved/ revision)

Submitted by ACSC

Prepared by Lê Long H uậu Deputy Site Manger

Reviewed by Nguy n Hoàng Trinhễn Hoàng Trinh Site Manager

Approved by Nguy n Văn Trungễn Hoàng Trinh Project Manager

Approved by KOA

QA-QC

QA-QC

HSE

KDA

Reviewed by

Approved by

Approved by Client

Prepared by

Reviewed by

Trang 3

1 INTRODUCTION 4

1.1 PURPOSE 4

1.2 DEFINITIONS: 4

2 BUILDING DESCRIPTION: 5

3 ORGANIZATION CHART 7

3.1 Organization Chart (Factory No.1) 7

3.2 Assignment 7

4 SCHEDULE 8

5 SPECIFICSTANDARD 8

6 SCOPE OF WORKS: 9

7 FLOW CHART AND DIRECTION OF WORK 10

8 PREPARATION WORKS 11

8.1 Cleaning and check 11

8.2 Mock up 11

8.3 Forming the bed of tiling 11

8.4 Set up tiles layout 12

9 CONSTRUCTION METHOD 12

9.1 Mortar & mixing mortar 12

9.2 Tiling sequence: 12

9.3 Finishing: 16

10 RESOURCES 16

10.1 TOOL & EQUIPMENT 16

10.2 MATERIALS 16

11 QUALITY CONTROL 17

12 APPENDIX 18

Trang 4

1 INTRODUCTION

1.1 PURPOSE

This method statement describes the methodology for tiling of wall and floor at SMC project Tiling work will be carried out after all constructions of relevant structures such as slab, columns, wall completed, but before painting and installing of sanitary wares The concrete work, brick work constructions were covered by another submittals, therefore they will no longer discussed in this method statement

Before tiling work can start, all electrical and plumbing works inside the wall, if any, have been also completed, fully tested and approved All door, window frames have been installed as well Tiling work will start only the working drawing has been prepared Working drawing will be separate submitted with this document

Tiling work will be divided into two stages: firstly tiling the wall then tiling the floor

1.2 DEFINITIONS:

PROJECT PARTICULARS:

Project name : SMC MANUFACTURING (VIET NAM) FACTORY-PHASE 1 PROJECT

Address : Long Duc Industrial Park, Long Duc Ward, Long Thanh District, Dong Nai Province,

Viet Nam

PARTY:

Client/ Owner : SMC MANUFACTURING VIETNAM CO., LTD

Contractor : KAJIMA OVERSEAS ASEA PTE LTD

Responsible for the supervision of Contractors who will construct the podium and all related activities as outlined in this procedure

SCOPE OF WORK

The works to be carried out by Sub-Contractor (ACSC) and shall apply for works at Factory No.1of SMC

MANUFACTURING (VIET NAM) FACTORY-PHASE 1 PROJECT

1 Construction Reinforcement Concrete Structure works included:

a Pile head treatment

b Earth work

c Formwork

d Reinforcement Steel Rebar work

e Concrete work

Trang 5

2 Finishing works included:

a Brick work

b Plaster work

c Painting work

d Tiling work (Wall & Floor)

2 BUILDING DESCRIPTION:

Location:

Factory No.1 are located at the corner of Road No.D5 &N2-5 in Long Duc Industrial park as below

Description:

- Building purpose :Factory

- Foundation : Spun piles (D300, 350, 400 mm)

- Structure :RC structures + steel rafter; Slab on grade

- Dimensions:

o Factory

 140m long (14x10m); 60 (4x15m) - 69m wide

 Ground Floor (FL 0.00m); 1st Floor (FL +7.25m)

 Height : 11.40m

o Utilities area: 2 x (120m long, 4.5m wide)

Factory No 1

Trang 6

- Floor load:

o Factory Ground Floor : 40 KN/m2

o WC Ground Floor : 2 KN/m2

o Stair case : 3 KN/m2

o Storage/Utilities : 10 KN/m2

- Slab thickness:

o Factory Ground floor slab : 300 mm thk

o Storage/Utilities Ground Floor slab : 150 mm thk

o 1st Floor slab : 140 mm thk

- Area:

o Ground floor : 9561 m2

+ Factory area : 8400 m2

+ Storage/Utilities area : 1161 m2

o 1st Floor : 9561 m2

GROUND FLOOR PLAN

Trang 7

3 ORGANIZATION CHART

3.1 Organization Chart (Factory No.1)

3.2 Assignment

Position Factory No.1 Factory No.9 Deputy Site manager NGUYỄN TRÍ KHOA TRẦN AN TOÀN

Site Engineer NGUYỄN MINH TUẤN

NGUYỄN VĂN HÀO

LÊ VĂN TUẤT PHẠM TRỌNG HÙNG QA&QC Engineer PHAN QUỐC TRƯỜNG NGUYỄN ANH ĐỨC

Safety Supervision ĐỖ VŨ QUYỀN ANH PHẠM VĂN MẠNH

Project Manager

NGUYỄN VĂN TRUNG (MP: 090 330 7742)

nguyenvantrung@acsc.com.vn

Site Manager

NGUYỄN HOÀNG TRINH (MP: 090 291 1235)

nghoangtrinh@acsc.com.vn

Deputy Site Manager

LÊ LONG HẬU (MP: 093 232 5944)

haull@acsc.com.vn

Deputy Site Manager

NGUYỄN TRÍ KHOA (MP: 093 722 9680)

ngtrikhoa@acsc.com.vn

Site Engineer

NGUYỄN MINH TUẤN (MP: 098 314 5069)

NGUYỄN VĂN HÀO (MP: 093 872 2730)

QC engineer

PHAN QUỐC TRƯỜNG (MP: 098 314 5069)

quoctruong@acsc.com.vn

Shop Drawing

NGUYỄN VĂN THIỆN (MP: 090 657 5516)

vanthien@acsc.com.vn

Safety Supervisor

ĐỖ VŨ QUYỀN ANH (MP: 090 853 1908)

Construction Teams

Trang 8

4 SCHEDULE

Construction Schedule of tiling work on Ground Floor Toilets as below:

Work Start Duration Finish Wall tiling 01/3/2016 6 days 06/3/2016 Floor tiling 07/3/2016 5 days 11/3/2016

Construction Schedule of tiling work on 1st Floor Toilets as below:

Work Start Duration Finish Wall tiling 01/3/2016 6 days 06/3/2016 Floor tiling 11/3/2016 5 days 15/3/2016

5 SPECIFICSTANDARD

Tiling floor and wall should be carried out in accordance with the requirements of:

- SMC MANUFACTURING (VIET NAM) FACTORY-PHASE 1 PROJECT Specification finishing works

- Current Vietnamese Construction Standards

TCVN 7132-2002: Ceramic floor and wall tiles- Definition, classification, characteristics and

marking TCVN 6415-2005: Ceramic floor and tile- Test method

TCVN 6414-1998: Ceramic floor and tile- Specifications

TCVN 8264-2009: Wall and floor tiles- Codes of practice and acceptance

TCVN 9377-2012: Finish works in construction – Execution and acceptance Part 1: paving and

smoothing works TCVN 9377-2012: Finish works in construction – Execution and acceptance Part 3: wall tiling

works TCVN 7899-1-2008 Ceramic tiles - Grouts and adhesives – Part 1: Terms, definitions and

specifications for adhesives

TCVN 7899-2-2008 Ceramic tiles – Grouts and adhesives – Part 2: Test methods for adhesives TCXDVN 336- 2005 Adhesives for Tiles – Specifications and Testing Methods

Trang 9

6 SCOPE OF WORKS:

All tiling work of Factory No.1 designated for the Toilets (8 rooms) on Ground floor and 1st floor The tiling in Office area will be carried out by other Sub-Contractors This work includes screeding and tiling of wall and floor

TYPICAL FLOOR TILING

TYPICAL WALL TILING

The toilets where tiling are applied

Trang 10

7 FLOW CHART AND DIRECTION OF WORK

The work sequence of tiling floor and wall are shown at the following flowchart

Covered by previous submittal

1 Columns, slab, wall construction

Start of Tiling

2 Installing door, window frame

3 Electrical work, plumbing, waterproofing

End

3 Floor Tiling (screeding, applying)

1 Set up tile layout

2 Wall tiling (plastering, applying)

4 Filling paste to the joints

5 Cleaning tiles

Trang 11

8 PREPARATION WORKS

8.1 Cleaning and check

Sub-base surface :

- Remove any dust, dirt, foreign matter on the wall, floor

- Damp the wall, floor surface with clean water

Tiles:

- Check dimensions, shape of tile to ensure their uniformities

- Moisten all tiles by soaking in the water for a while

8.2 Mock up

The mock-ups for tiling work on site will be done by ACSC before application for all toilets The location

of mock-up with the plan layout drawings shall be proposed and submitted by ACSC to Kajima Vietnam for approval The location of mock-ups shall be chosen by KOA in such a way that the openings of a door and window, floor drains, penetrated pipes, floor and wall shall be involved

8.3 Forming the bed of tiling

Wall tiling:

- Check the distance of the walls to suit with the tile layout

- Using theodolite to set up all finished planes of wall tile to ensure their plumbness, flatness and perpendicularity at the corners Mark the set up lines onto the walls

- Using string to set base points for the plaster coat onto the walls by deduct the thickness of the tile

- Apply the method of plaster work to plaster onto the wall to get true surfaces where the tiles will be applied Tile backing shall be cement plaster applied in conformity with requirements in the specification

Floor tiling:

- Based on level benchmark and designed slope of the floor, set up the finish surface of floor tiles then mark its intersection lines with the walls onto the wall surfaces

- Using string to set base points for the screed layer onto the floor slab by deduct the thickness of the tile

- Level pegs shall be installed by following marked lines on floor surface for water dividing lines to keep the floor slope at least one day before floor screed The spacing of level pegs shall be less than 2.0 m

- For toilet floor areas which are waterproofed, a special care of protection to waterproof layers shall

be taken by Subcontractor Material for installation of level pegs shall be screed mortar

- Screed the mortar onto the slab then flatten with tool such as straight bar Mortar to bed is of 1 cement to 3 sand mixture and well mixed on the site

- A straightedge tolerance of 2.0mm/2m shall be allowed for floor screed surface finish

- Trowel by hand to get a true, flat finish surface

Trang 12

8.4 Set up tiles layout

- All check lines for walls of room and grid lines shall be re-marked on floor screed Marked lines such

as check lines and grid lines on floor shall be matched to lines marked on walls

- Room dimensions, wall corners, wall lines shall be checked for right angle based upon on the marked lines If any discrepancies are found then repair shall be carried out and accepted by Kajima Vietnam before tiling or other finish

- For wall tiling, the Subcontractor shall ensure that the lines of FFL+1000 (Floor Finish Level)

and the lines for the top layer and first layer of wall tiles to be marked sufficiently and correctly

- Based on the working drawing, using the level machine, theodolite, measure tape to set up the tiles layout and mark the tile joints onto the wall or floor bed The dimensions of tiling area will include the width of the tiles and the joints which shall be uniform 2mm wide

- Tiles will be arranged so that there will be no tile has the width smaller than the half width of their original dimensions They will also be set so that the center of any fitting such as floor drain, faucet will be right on the intersection of the joints

9 CONSTRUCTION METHOD

9.1 Mortar & mixing mortar

- Sand for mixed mortar shall be natural sand free from any deleterious materials such as clay, flaky

or elongated particles, mica, shale or other laminated materials, organic impurities, iron pyrites Sand shall

be clean, hard, durable, crushed It shall be thoroughly washed and all dirt, shells etc…removed before use

- Water for brick work shall be clean and uncontaminated potable water from the city main supply or any other approved source free from harmful matter

- Mortar type to be used shall be sand-cement mortar, class mark #100 (28days compressive

strength 7.5 Mpa) with its proportion: 1 part of cement: 4 part of sand in volume

- The mortar proportion will be verified with the result of trial mix on site and testing prior to be use

- Mortar will be mixed by mixer which has capacity of 100 liters on site Material of mortar will be measured in containers with defined volume to maintain control and accuracy of proportion

- Mix by placing one-half the water and sand in operating mixer Then add cement and remainder of sand and water Mix batch for not less than 3 minutes after all ingredients are in the mixer

- Workability or consistency of mortar on the board shall be sufficiently wet to be worked under the trowel

9.2 Tiling sequence:

- Ceramic tiles shall be or soaked in water before installation

- Tile will be installed by using thin set of tile grout to apply on the prepared bed surface The

thickness of cement adhesive will not exceed 3mm

- To ensure a uniform of joint width, PVC spacers shall be used to ensure joint width shall be 2.0 mm

Trang 13

- Wall tiling will start row by row from the bottom to the top.

DIRECTION OF TILING

2mm

- PVC beads shall be installed at outer corners of wall and PVC tiling bead joint shall be butt or mitred at ends

Trang 14

20 10 30

2

2 Tile size

WALL TILE FINISH

WALL

PVC ANGLE BEAD

- At the inner corners, there will be joints 2mm wide The termination of wall tiling at inner corner

of wall shall follow the principal of “Joint line of wall tiles at inner corners shall be invisible for the direction of view from room entrance”.

2mm JOINT

WALL TILE

2mm JOINT WALL TILE

180 30

-Where tiles connect with door frame, there will be joint 5mm wide then filling with sealant

Trang 15

DOOR FRAME 200

40 20

RC STILLENER

5

- Permanently using straight bar to check the plumpness, flatness of the finished surface; square meter to check the perpendicularity at the intersection of the walls

- Always cleaning the tile surface to ease the inspection of tiling

Floor tiling:

- Floor tiling should be carried out after the wall tiling completed Unless specified on the drawings, floor tiling joint lines and wall tiling joint lines shall be aligned and the wall tile installation must be completed before floor tiling

- The floor tile arrangement for 2 rows in perpendicular directions from start point on the floor shall

be carried out to check the correctness between the drawings and the actual site condition

- Where the floor is required to slope the Subcontractor shall check for floor tile joint line at water dividing line The level of installed tiles along the water dividing line shall be at the required level to ensure the design slope

- Floor tiling shall start from the centre of the room In order to avoid any cumulative error of floor tile installation, the start of floor tiling from the room corner shall be avoided

Trang 16

- Permanently using straight bar to check the flatness of the finished surface; spirit level to check the slopping of the floor

- Always cleaning the tile surface to ease the inspection of tiling

Work sequence:

- Preparing the right tile units Cutting, beveling them before, if necessary

- Fully plastering the adhesive onto the back of the tiles.

- Placing the tile unit in position

- Slightly move and press the tile to the bed surface

- Using rubber hammer to slightly clap onto the tile

- Insert the plastic stick the check the joint width and adjust the tile until get the true position

- Using straight bar the check the flatness of the tile unit with the true surface

- Repeat the clapping, adjusting the tile unit until it reach all requirements

9.3 Finishing:

Filling the joints:

- Using white cement grout to paste onto the wall, floor tiles to fill the joints

- Before grout become set, using clothes or sponge to skillfully remove the excess grout to make the joint neat and clean

Trang 17

Cleaning, protecting:

- Thoroughly remove any stains of grout, dust on the tile surface

- Protect the tile from damages of any following construction activities Special cares should be taken with hard and heavy tools, equipment such as door, scaffolding, machine…

10.RESOURCES

10.1 TOOL & EQUIPMENT

The equipment to be used for the construction of s is listed below

No Description Specification Unit Q’ty Remarks

1 Concrete mixer 100 liters ea 2

3 Tools (measure tape, rubber

hammer, spirit level… etc) ea 1

4 Theodolite, level machine ea 1

10.2 MATERIALS

Type of material:

1 Floor & Wall tiles Ceramic 300x300 (mm) Royal 302137

2 Tiling bead PVC 10x10x15 (mm) T10-W

3 Cement Package PC40 Fico, Nghi son

4 Tile Grout (adhesive) Ready mixed 25kg/bag Striving method

5 Joint filler (White) Ready mixed 1kg/bag Skymax

4 Sand Fine Dong Nai As approved material

Materials handling, storage and delivery

- Tile:

Tile will be sealed at firm and delivery to site by truck

It should be keep in warehouse and level ground with the height not exceed 1.5m

- Cement:

Ngày đăng: 20/10/2016, 15:17

TỪ KHÓA LIÊN QUAN

TÀI LIỆU CÙNG NGƯỜI DÙNG

TÀI LIỆU LIÊN QUAN

w