Trang 1Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Assessment Duration : 7days
Document No : Refer to the submital list
Riviera Point Project
METHOD STATEMENT
FOR CEILING WORK
Dept
Prepared by
Approved (by)
Trang 2calculation
25/83 is 1000mm, which one is correct?
The standard spacing is 1000 ㎜ is correct but the case on page 21, 22 is the perimeter condition which need to adjust the last hanger’s gab within 400 ㎜
SingSung is correct or not? Will SingSung do ceiling work? It has been corrected
RPLLC
Please add telephone Number of Mr Cho, Duc & Ho Thu
Bernarrd/Minh,
Trang 3Project: Riviera Point Project
Document No: RP_MOS -CW _SSY_ 01
For the joint treatment working method, shall be indicated until taping
before doing ceiling work?
The skim coat shall be finished prior to install the ceiling
Page 15/83 – item 6.1.4:
1st line: please indicate interval distance of screws which connect wall angle V21x21 to concrete
5th line: with subjecting interval distance of two hangers does not exceed manufacturer’s requirement
3rd & 4th line: starting point of the hanger is 400mm for longitudinal direction and 610mm for transverse direction But step 4 of page 20/83 is 300mm Which one will be applied?
Interval distance of screws is 600mm to connect with the angle V21x21 to the concrete wall
It is important for sure to follow the manufacturer’s recommendation
The longitudinal distance of 400mm is correct
Trang 4bars is max 400mm not 800mm Noted
Page 24/83 – item 7.2: what is the relationship between ceiling work and floor substrate? And why does ceiling work have the grouted joints?
It has therefore been deleted
Page 54/83: please clarify connection detail and work sequence whether you plan to apply special putty the joints
of gypsum panels?
It has been shown in the detail
should be conducted at site
There will be testifying and separately submit by our QC submission
Reviewer’s suggested status code for this revision only:
Trang 5Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Assessment Duration : 7days
Document No : Refer to the submital list
7 Quilty Control Plan
8 Safety Control Plan
9 Emergency Preparedness
APPENDICES 1~6 (please refer to the next page)
Trang 6ANNECES
Annex 1 ……….… Risk Assessment & Job Safety Analysis
Annex 2 ………… ………Organization Chart
Annex 3 ……… Drawings
Annex 4 ……… ……… Material safety data sheet
Annex 5 …….…… ……… First Aid Plan
Annex 6 …….……… Material Specification
Trang 7Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Assessment Duration : 7days
Document No : Refer to the submital list
1 Introduction
This method statement relates to the Ceiling work.
The project site is located in District 7, HCMC of Vietnam
We recognize that safety, health and environment (SHE) are primary premise in all decisions, being made for successful construction and shall comply with the relavant local authorities of Ho Chi Minh City, Socialist Republic of Vietnam
We will develop the construction method with the focus to avoid any harm to the health and safety of owner’s personnel, contractor employees and the public and also to minimize adverse effect to the natural and around environment
All necessary specifications, inspection and quality control will be complied with the contract documents, specification
If there is any discrepancy in the descriptions below, it will be designated by RPLLC
2 Definition & Abbreviation
The abbreviations are used for this method statement, as shown below :
1) Project Definition
- Project: Condominium housing development Riviera point (Phase 1A)
- Main-Contractor: Ssangyong Engineering & Construction Co.Ltd
2) Project Abbreviation
- SSY: Ssangyong engineering & Construction Co.Ltd
- RPLLC: Riviera Point Limited Liability Company, KPLC: Keppel Land Construction
- PM: Project Manager, CM: Construction Manager, SM: Site Manager
- PD: Project Director, PJC: Project company, KPLS: Keppel Land Safety team
- SCM: Senior Construction Manager, SEM: Senior Engineering Manager
- SHE: Safety Health Environment, RFT: Raft, SAC: Safety Awareness Center
- QA: Quality Assurance, QC: Quality Control, QS: Quality Surveyor
- DWG: Drawing, BSMT: Basement, FDN: Foundation, BLK: Block,
- MEP ; Mechanic, Electric, Plumbing
Trang 8[ Site Location of Riviera Point Project ]
3 Scope of work
The main scope of work is Ceiling work.
Trang 9Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Assessment Duration : 7days
Document No : Refer to the submital list
4 Resources (Materials, Equipments & Human Resources)
4.1 Resources for ceiling work - Material
3 Gypsum board
1220*2440*12.5mm(TE) 1210*2420*9mm (SE)
6 Moistbloc access
450x450 x 9mm 200x200x9mm
Trang 104.2 Resources for tiling work - Equipment
Trang 11Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Assessment Duration : 7days
Document No : Refer to the submital list
Trang 124.4 Plan of Vertical supplying material by Hoist
Material
Trang 13Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Assessment Duration : 7days
Document No : Refer to the submital list
4.5 Equipment Location & Lifting Loading Chart
4.6 Losistics Plan for Item
Trang 14M&E works
Ceiling Preparation works
Inspection for Preparation works
M&E Testing & commissioning
Ceiling frame installation
Inspection for Ceiling frame installation Ceiling board installation
Inspection for Ceiling gypsum board installation
Material Delivery to Site
be repaired by Structure Subcontractor & inspected by KPL
& SSY Piping & Ducting works to
be completed & no affect to suspension rods of ceiling , fire separation …
Check Offset lines marked by surveyor
& do lines marking for ceiling works ( ceiling level lines on walls, hanger rod lines on slab soffit….to be inspected by KPL & SSY
Installation of wall angel bars, drilling holes in slab for hanger rod (suspension rod) installation , runner , furring channel to be installed , then to be handed over to M&E for M&E testing & commissioning works& ensure that all M&E items completed After M&E tested , signed M&E inspection form to
be past to Construction Section to attach together with Ceiling inspection document KPL & SSY to check & inspect ceiling frame installation prior
to closing ceiling
Ceiling gypsum board to be installed (ceiling closing) Ceiling level , Alignment, evenness ,joint gap… to
be checked from time to time during installation Ceiling panel installation to be checked &
inspected by KPL & SSY
No Yes
Yes
Yes Yes
Trang 15FOR PROPOSED CONDOMINIUM DEVELOPMENT (RIVIERA POINT)
AT DISTRICT 7, HO CHI MINH, VIETNAM
FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Assessment Duration : 7days
Document No : Refer to the submital list.
Trang 165.2 Preparation of works
5.2.1 Material handling, storage and delivery
i Suspended Ceiling System Materials will be delivered on site by trucks
ii Likewise Gypsum Board Materials will be delivered on site by trucks
iii Regular Gypsum Board will be delivered in separate batches and Moisture Resistant Gypsum Board will be delivered in separate batches
iv All materials will be unloaded and stored at the HBC Ground Floor Storage areas & adequately protected
v They will be placed in palettes and protected from sun or heat and rain water incursion
vi Depending on the requirement of each Tower at each floor, the suspended ceiling materials are lifted using the hoist and delivered on each floor
vii In general delivery of Suspended Ceiling Materials will be done at night time However in some circumstances they will be delivered during daytime
viii Hoisting and delivery of Suspended Ceiling Materials on each floor will also be done during day time and as required it will be done during night time
ix Store materials at designated location and
x Prevent flood by providing perimeter surface drainage if necessary
xi Boarded platform at least 75 mm off the ground and undercover are
recommended to protect contact from water and construction debris
5.2.2 Material
1 Ceiling Gypsum board : Lagyp Brand (New name is Boral)
+ Regular board of size 2440 x 1220 x 9mm, + Moisture resistant board of size 2440 x 1220 x 12.5mm,
2 Concealed Grid Ceiling Frame : Le Tran Brand
* Channel Tek 2030 System for 1 layer of 9mm thick ceiling
Trang 17FOR PROPOSED CONDOMINIUM DEVELOPMENT (RIVIERA POINT)
AT DISTRICT 7, HO CHI MINH, VIETNAM
FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Assessment Duration : 7days
Document No : Refer to the submital list.
+ Carrying channel : 3600 x 20 x 30 x 0.6mm
+ Rurring Bar : 4000 x 45 x 12 x 04mm
+ Wall angle : 21 x 21 x 0.32mm
+ Clip lock PK21 & Clip lock TK-PK21
+ Suspension Rod : TY6-M6
+ Expension anchor bolt : TK6-M6
6 Working Method
6.1 Installation Method
6.1.1 Concrete Soffit Repair works :
Prior to commencement of suspended ceiling works a joint inspection will be conducted to check the actual status of concrete structure surfaces
The concrete soffit structure must be sound and with no apparent honeycomb either on the concrete slabs or beams
Any honeycomb or unsound concrete must be repaired properly with approved method
Remaining formwork, tape , nail… on the concrete soffit must be removed
All MEP services such as Fire Fighting, Mechanical and Electrical services are installed and tested
6.1.2 Plastering & Painting works finished
Ensure that all walls plastered & skimcoat works with 2 finish coats Also, plastering & skimcoat works at least along ceiling line inspected by KPL already prior to ceiling works
Trang 186.1.3 Preparation works
Based on GLs & Offset lines , FFL+1000 lines marked by surveyor, Subcon for ceiling works will do lines marking for ceiling level lines on walls & lines
for suspension rod installation
Check installed M&E items for affecting suspension rod installation & inform
relevant M&E subcontractor to rectify
Ensure that all piping & ducting works already completed
For the transverse direction the starting point is located 610 mm from the wall surface The succeeding point is located 800mm and spaced the same distance respectively
Trapeze hangers or other special arrangements of suspension system will be installed to suit the layout of air conditioning ventilation ducts, sprinkler pipes, electrical conduits and all other services as required
Drill holes on these locations for the expansion bolt size 40mm with diameter
of 5mm Clean the holes and install the expansion bolts
Install the suspension rods Adjust the suspension rods to suit the level of the ceiling Secure them properly on the anchor bolts
Install the Main Runners in longitudinal direction The starting Main Runner is located 400mm from the wall surface
The succeeding Main Runner is located 800mm and spaced the same
Trang 19FOR PROPOSED CONDOMINIUM DEVELOPMENT (RIVIERA POINT)
AT DISTRICT 7, HO CHI MINH, VIETNAM
FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Assessment Duration : 7days
Document No : Refer to the submital list.
Next install the carring channel They are installed in the transverse direction
Install the starting Furring bar from the wall surface The succeeding Furring
is also located and spaced the same direction
Make final check and adjustment to suit the required ceiling height after installing the gypsum board ceiling
For the locations of maintenance holes on the ceiling, special cut opening and runner will be provided
As mentioned earlier, all MEP services must be installed above ceiling All services that require proper testing must be tested and certified & approved
by KPL prior to closing the ceiling It means after concealed frame installed, the whole area should be handed over to M&E Subcontractors for remaining testing and /or commissioning works to be inspected by KPL , then to be handed over back to Ceiling Subcontractors for ceiling closing works
Area by area after getting back from M&E subcontractor with the approved M&E documents, the gypsum board ceiling will be installed
Cut out will be provided on lighting services, fire fighting, public address, etc This exercise will be done in coordination with all MEP, contractors during
the cutting in order to avoid wrong location and wrong size
Pencil marks, smudges or blemishes maybe removed with an art gum eraser
or with a moist cloth or sponge with mild soap Wiped off with a clean damp cloth or sponge
Trang 21FOR PROPOSED CONDOMINIUM DEVELOPMENT (RIVIERA POINT)
AT DISTRICT 7, HO CHI MINH, VIETNAM
FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Assessment Duration : 7days
Document No : Refer to the submital list.
Trang 226.1.6 Dropped ceiling execution
Step 1: Mark the height of the ceiling
- Mark the height of ceiling with a level or a laser device Mark the height
of ceiling plane on the wall or column Normally, the marking of the ceiling height should be made beneath the ceiling boards
Step 2: Fix the wall edging bars
Trang 23FOR PROPOSED CONDOMINIUM DEVELOPMENT (RIVIERA POINT)
AT DISTRICT 7, HO CHI MINH, VIETNAM
FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Assessment Duration : 7days
Document No : Refer to the submital list.
- Depending on the type of wall/partition, use a drill or nail hammer to fix the wall edging bars onto walls or partitions
Step 3: Ceiling division
- To ensure the even width of ceiling boards and ceiling frame, the ceiling must be properly divided, and the distance the centres of main bar
- Divide the ceiling and mark the tie suspension points
Step 4: Mark the tie suspension points
- Maximum distance between the suspension points is 1000mm;
distance between the wall to the first hook is 400mm
- In case of concrete floor, directly drill into the floor with a concrete drill, then connect with expanding wedges and 2-hole tabs and suspension ties plus slack adjusters, to the determined height of the ceiling
- In case of metal roofs, the suspention ties will be directly connected to the beams, or 2-hole tabs are used
Trang 24Step 5: Install the frame
- The main bars are connected to each other by fixing the hole at the end of one bar to that of another; The starting point is located 400mm from the wall surface, the distance between two main bars is 1000mm
- The cross bars are fixed to the holes on the main bars; the distance between two secondary bars is maximum 400mm
Trang 25FOR PROPOSED CONDOMINIUM DEVELOPMENT (RIVIERA POINT)
AT DISTRICT 7, HO CHI MINH, VIETNAM
FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Assessment Duration : 7days
Document No : Refer to the submital list.
Step 6: Align the frame
- After the frame installation is complete, adjust to align the frame for its really flat plane Use the slack adjusters to set the ceiling height in accordance with the height initially marked on the walls or columns
Step 7: Fix the boards onto the frame
- Fix the ceiling boards onto the aligned frame as per the ceiling board dimensions normally used:
- After the ceiling boards are fixed, align them for the ceiling plane really flat
- Clamps should be used to hold the light ceiling boards; clamps must be used for each side, and 1 clamp for each corner of the board
- Cut the ceiling boards: To cut boards 4 mm thick, use a fine-toothed saw
or a knife
- For boards over 6 mm thick, use a hand shears (rubber coated glove)
Trang 26Step 8: Acceptance and delivery
- Align the ceiling after the board fixing is completed; clean the place of execution
- Check that all jobs are complete
- Prepare for acceptance and delivery
Trang 27FOR PROPOSED CONDOMINIUM DEVELOPMENT (RIVIERA POINT)
AT DISTRICT 7, HO CHI MINH, VIETNAM
FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Assessment Duration : 7days
Document No : Refer to the submital list.
7.0 Quality control
Samples and test certificates of all materials shall be submitted for approval prior to use on site Sample construction shall be carried out prior to work on site and shall be witnessed by consultant, owner
7.1 Quality Management :
Construction management by standard - technical standards
Detailed planning and action by process
Materials are to be inspected on delivery
When there is any damage
Material shall be protected after installation
Surface flatness shall be controlled to be less than 2mm deviation per 1m
7.2 Quality Check :
Check floor substrate ( MEP line through, crack lines , unevenness , slope ) &
ensure that to have defects repaired prior to installation
Variation in plan between adjacent board pieces not exceed 1.5mm
7.3 Process Management:
Draw up construction plan feed back &fulfill
Risk Management: block the delay items before hand by, examine drawings closely
Send in shop design in site to make systematize drawing & fast responded because
of incomplete drawing
Each process to be followed by ITP
Continuous repetition of each process to be controlled on site
7.3 Main check points in each process
Spacing between expansion bolt less than 1000mm.
Tolerance of main runner spacing and cross runner spacing is +/- 2mm.
Trang 287.4 Quality Check List
Check result
1 st 2 nd 3 rd
1 Marking Check measures the line by
using ink to mark ± 3mm at 10m
2 Hanger Work Tolerance of fixing 1000 ±10mm
3
Structure Installation
Spacing between two main
runner CHANNEL TEK
2030
Compulsory
5
Jointing treatment
Jointing curve -0/+2mm at
450mm
Air bubble in paper tape Not allowed
Trang 29FOR PROPOSED CONDOMINIUM DEVELOPMENT (RIVIERA POINT)
AT DISTRICT 7, HO CHI MINH, VIETNAM
FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Assessment Duration : 7days
Document No : Refer to the submital list.
- Workers, Laborers
Personnel that have attended the project HSE induction and are familiar with the task to be performed and JSA that supports the work and addresses the hazards identified in the process
Forman / Supervisor
hazards identified in the process of the activities All personal protective
equipment issued to personnel shall be
of a standard, which is fit for purpose, inspected and found to be free from damage, instruction in its use and fitting has been given to each employee issued with it
Forman / Supervisor / Worker
Forman / Supervisor / HSE Dept
Forman / Supervisor
E
Storage-Moving
eyes protection etc… Stack of bricks in tidy When lifting, keep back straight and lift with legs not back Never twist when lifting Clear access all times
Forman / Supervisor / Workers
F
all personal Install sign board at the edge for the warning at height
Forman / Supervisor / Workers
Trang 30G
scaffolds and working platforms
Materials drop down from
working platform
All scaffolds and working platforms must be erected in compliance with statutory regulation Access must be provided to all scaffolds and work platform with enough strong handrails
Scaffolds and working platforms must
be left clear of tools, materials
Forman / Supervisor / Workers
H
Defective of Hand Tools,
Materials and Equipments
Inspect hand tools materials at daily prior to starting work Mark defective hand tools, material and place it out of service
Forman
I
Supervisor / Worker
Always earth ground welding generator sets, the cable do not cause a trip hazard at the work site
Forman / Worker
Forman /Supervisor / Worker
Trang 31FOR PROPOSED CONDOMINIUM DEVELOPMENT (RIVIERA POINT)
AT DISTRICT 7, HO CHI MINH, VIETNAM
FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Assessment Duration : 7days
Document No : Refer to the submital list.
9.0 Emergency preparedness
9.1 Emergency action when accident:
Means of emergency rescue must be readily available to the confined space entry attendant for emergency extrication of entrants
Finsing work Subcontractor
Trang 329.2 Emergency team and function
Duc
Trang 33FOR PROPOSED CONDOMINIUM DEVELOPMENT (RIVIERA POINT)
AT DISTRICT 7, HO CHI MINH, VIETNAM
FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Assessment Duration : 7days
Document No : Refer to the submital list.
9.3 Emergency Response Flowchart
Y ese
s
*Type of Emergency
fire;
explosion;
failure and collapse of structure;
failure and collapse of heavy
machinery and equipment;
leakage of hazardous materials;
adverse weather and flooding; and
any other incident leading to mass
In the event of Emergency
Inform SIC / Dy SIC
All persons evacuate to AA through nearest escape route Fire wardens to assist evacuation orderly
ERT to ensure that the situation is properly taken care
Any person missing?
ERT to investigate and file incident report
ERT to analyse and recommend preventive control
Trang 349.4 Rescue staffs (General only)
First aid, hospital arrangement, transportation arrangement, transport of victims, nursing arrangement
Team of Rescue Staffs (This staff was educated by SSY’s competency nurse): Main : Y.J Myoung - Assistant : Do Thanh chi
Main : Nguyen Khanh Hoang - Assistant : Dao Duy Tien
9.6 Site Supervision staffs
Inspection of the site, grasp the history of the occurrence, collect site information and evidences as well as photo records, preparation of sketches of the accident, supervision
The nearest hospital: 1 km, 5 minutes away from site
Name:“BENH VIEN QUAN 7”Address:101 Nguyen Thi Thap street, Tan Phu ward,
Y
es
Trang 35Rivera Point Condominium Development-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Preparing Duration : 7days Revision : S
Trang 36SSYENC Activities Sub Contractors Activities
RA Preparation
SSYENC Engineers and Supervisors to prepare RA, with input from all involved
RA Preparation / RA Approval
Sub Contractors RA Team to prepare the RA and Sub Contractors management personnel to the RA report
To address any comments
Trang 37Table I : Accident severity categories
Consequency Category Environmental, Safety and Health Result Criterial
Catastrophic 5 Fatality, fatal diseases or multiple major injuries
Major
4 Serious injuries or life-threatening occupational disease (includes amputations, major fractures, multiple injuries,
occupational cancer, acute poisoning)
Injury requiring medical treatment or ill –health leading to disability (includes lacerations, burns, sprains, minor fractures, dermatitis, deafness, work –related upper limb disorders)
Minor
2
No injury, injury or ill health requiring first aid treatment only (includes minor cuts and bruises, irritation, ill –health with temporary discomfort)
Negligible 1 Not like to cause injury or ill –health
Table II : Accident frequency categories
Rare 1 Not expected to occur but still possible
Remote 2 Not likely to occur under normal circumstances
Occasional 3 Possible or know to occur
Frequent 4 Common occurrence
Almost Certain 5 Continual or repeating experience
No
Trang 38Risk Category Rare
(1) Remote (2) Occasional (3) Frequent (4) Certain Almost
Table IV : Definition of Risk Index
1 – 3
Low Risk Acceptable
• No additional risk control measures may be needed
• Frequent review and monitoring of hazards are required
to ensure that the risk level assigned is accurate and does not increase over time
4 – 12
Medium Risk Tolerable
• A careful evaluation of the hazards should be carried out to ensure that the risk level is reduced to as low as reasonably practicable (ALARP) within a defined time period
• Interim risk control measures, such as administrative controls or PPE, may be implemented while longer term measures are being established
• Management attention may be required
Trang 3915 – 25
High Risk
Not Acceptable
• High risk level must be reduced to at least medium risk before work commences
• There should not be any interim risk control measures Risk control measures should ot be overly dependant
Trang 40TITLE: RISK ASSESSEMENT DOC NO./ REVISION
(Team Member name) PREPARED BY: Mr NGUYEN ANH DUC (Safety Manager)
~~
REVIEW BY: Mr PARK SEUNf~irector) APPROVED BY (PD) Mr CHO OCK ~ n Senior Manager)
A
r:::7
RISK ASSESSEMENT FOR CEILING WORKS
and suffer serious Provision of banks- man to Mode TBM is to be carried out with
1 or even fatal rate Remote (2) pre-task analysis and proper Rare (1) Low (2) Supervisor
delivery
injuries from vehicle to location (3) (6) planning prior to execution of (2)
machines on site traffic rule requirement Barrier if necessary
particularly when Watch man, banks man reversing duty
TBM for briefing All workers could how to handling