METHOD STATEMENT FOR PAINTING WORK
Trang 1Riviera Point Condominium Development
DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Riviera Point Project
METHOD STATEMENT
FOR PAINTING WORK
Dept
Prepared by
QC/QA Safety Construction Engineering
Rev Date Description
Approved (by) Ssangyong ICIC KLV Safety RPLLC
A 3-Jun-2013 Issue for Acceptance SC Park M.Tan Bernarrd CM Leong
B 11-Jul-2013 Issue for Acceptance SC Park M.Tan Bernarrd CM Leong
C 20-Aug-2013 Issue for Acceptance SC Park M.Tan Bernarrd CM Leong
Trang 2Document Reference and Revision: Comment of MOS for painting work_RevB Submission Date:
1 Duc, RPLLC Based on pages 4/96 & 49/96, please clarifyputty, it is Jotun or Seamaster? material use exterior Jotun exterior Putty is right
2 Duc, RPLLC Page 5/96, mixing and stirring process shall be ready inside floor area
In case, side wall on gondola is impossible to be supplied from each floor, that’s why the mixing bucket should carry on gondola from ground
3 Duc, RPLLC How to check and control the density for layers (skim coating, sealer & coating) What is specify in our contract?
By visual checking and controlling the dilution while mixing to water & putty or paint
In order to check for density, paint layers will be checked by the tool of wet film thickness
4 Duc, RPLLC Page 12/96, item 30 “to ensure surface obtain good covering, uniform color and smooth” please specify cover method?
By visual checking and controlling the dilution while mixing to water & putty or paint
5 Duc, RPLLC Page 14/96 please separate method statement for gondola installation work It will be submitted on September Now the painting Method is focused on Mock up
room
To provide:
-Protection method to material during rainy days not specify
- Protection for painted surface has no solution when
it rained, however, before applying paint, the rain possibility will be presumed that checking humidity by phychro-meter, also refer to the national weather forecast, based on that we will get decision to
Trang 3electric outlet The maximum size of gondola is 0.8mx7.5m Those information can be referred to the presentation data for working platform of architectural works Workers shall be taken on the ground floor Each painting session of area is normally 3-5 points checking for a wall
- Groove line’s substrate will be treated on architectural cage after that putty and painting work
is on gondola
7 Vuong, RPLLC Page contents: what is meaning “please! Refer to the MS for tower
crane (General)”, please
-It is corrected
-Please refer to presentation data for working platform of architectural cage, there has description
of gondola usage
8 Vuong, RPLLC Page 6/96, please check external mock up painting have ceiling or not The external ceiling is the balcony ceiling
9 Vuong, RPLLC Page 17/96, where is method statement of Jotun Exterior Putty It has been described on annex 1.1 and 1.2
10 Vuong, RPLLC Please re-check item 5.2.3, Ssy will use external putty for internal wall & ceiling, it is correct or not? Paint for internal surface: Using Jotun Interior putty It is corrected
11 Vuong, RPLLC Please re-check item 5.2.3, Ssy will use Jotasealer Primer for internal wall & ceiling, it is correct or not? Because the product is used for
external
It is corrected by proper product name, both name are slightly different between Jotasealer 03 for external and Jotasealer primer for internal
12 Vuong, RPLLC Page 34/96, please revise 3comment for page 39/96 rd stage, it is 1st layer not 2nd layer Same It is corrected
13 Bernarrd/ Minh, RPLLC Please provide the completed content as stipulated in MS guideline page 2 It is corrected
14 Bernarrd/ Minh, RPLLC Please provide RA, JSA to the relevant work scope accordingly It is inserted
15 Bernarrd/ Minh, RPLLC Please provide the current organization chart It shall be submitted separately by official submission because the subcontractor would be changed
16 Bernarrd/ Minh, RPLLC Please provide the PPE listing as to the proposed work scope It is inserted
Trang 417 Bernarrd/ Minh, RPLLC Please provide material safety data sheet (MSDS) in relationship to all material to be used as proposed in this method It is inserted at annex
18 Bernarrd/ Minh, RPLLC Do not allow to carry out mixing skim coat on scaffold (page 33/96) It is corrected
20 Tan, ICIC
Based on technical data of Jotun Exterior Putty mixing ratio of putty and water is 3:1 by weight It means that 1 bag/40kg of putty will be mixed with 13 litres of water, why did your MOS indicate 16 litres of water?
Confirmed dilution ratio: 40Kg Putty/ 13 litres of water for normal case
We need extra water, in case the plain surface is too dry so that it can get adequate adhesion
21 Tan, ICIC
Based on technical data of Jotun Exterior Putty and Jotun Internal Putty, the drying time of them is different one recoated after 8 hours and another is 24 hours So please separate
The standard drying duration is indicated on technical data sheet However, its time depends on the condition on humidity & windy The other words, inside areas there are times to get higher humility and less ventilation than outside one, in this case, the drying time should be adjusted by crafts mas’ perception on each job’s detail
22 Tan, ICIC Based on technical data of Jotasealer, mixing sealer with the thinner maximum 5%, please comply It will be complied as technical data sheet
23 Tan, ICIC Item 27 - page 11/96: technical data did not indicate it, please explain and get advice of manufacturer Supplier confirmed that when the paint comes to dry in the bucket over 2 hour, water should be added in it
in order to keep the proper viscosity
Trang 527 Tan, ICIC
There will be some location where you can not use Architecture working cage and Gondola for painting work So could you tell us you intend to use Spider man for painting work if any you have to get approval from RP client
The remained external area can be accessed all around because the gondola can adjust to approach with extension by 1.7m
B
28 Duc, RPLLC Reply item 4: not cleared
It shall be able to controlled how finished topcoat is
It could incur some damage very soon So we will try to reduce it also
o After completion of applying, check about colour and aesthetic for the finalization
30 Bernarrd, RPLLC No more comment
31 Tan, ICIC Reply item 23: Please provide official confirmation of supplier It is attached on annex of certification
32 Tan, ICIC
Reply item 25: what have difference between Jotun putty and Seamaster putty? As this MOS did not mention to Seamaster putty? Both are same performance to make proper substrate It isn’t indicated the name anymore as
reply no 1
Reviewer’s suggested status code for this revision only:
ICIC Consultant Review Consultant TYLIN Structural JRP MEP Review Consultant Consultant KPK Cost Other (state) Other (state) Other (state) RPLLC
This section is to record the reviewing party’s suggested status code only: the official status code for the submitted item is recorded on the first sheet of this document
Trang 6Rivera Point Condominium Development
DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Trang 7Rivera Point Condominium Development
DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Project:Rivera Point Condominium Development
Produced by:Ssangyong E&C
1 SCOPE
This method statement is for the Painting work
The working Platform and Gondola will be installed step by step, safely fulfilling as the installation plan by special team based on each method statement
3 EQUIPMENTS AND TOOLS / TACKLES
Gondola & Scaffolding :
For treatment of substrate at the external wall surface
For applying of paniting materials such as Skim coat, Putty, Primer, Paint at the external wall
Hand tool :
All tools and tackles supplied by special team under supervision of yong safety dept
Trang 8Ssang-Rivera Point Condominium Development
DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
4 RESOURCES (Materials, Equipments & Human Resources)
4.1 List of material
Trang 9Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
YES
Working Platform Installation
Primer
1 st Skim coat or Putty
Inspection
by S.A.C
1 st finish coat
Fine Tune NO
2 nd finsh coat
2 nd Skim coat or Putty
NO
Painting complete YES
Trang 10Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
5.2 Description of working sequence
5.2.1 External Mock up painting
1) Surface must be dried To ensure moisture substance not exceeding 20%
Checking with Moisture Meter
2) To remove foreign and unstable matters such as dirt powder, cement splashes and other contaminants
Manual cleaning by chipping, scrapping or wire brushing
Trang 11Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
4) Surface must be free from algae of fungus growth
Fungicidal washing
5) Use Jotun Exterior Putty to apply as plastering
Jotun Exterior Putty
6) Mix 1 bag of Jotun Exterior Putty with 16 litres of water
By volume
Trang 12Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
7) Use a mixer if available or adequate mixing equipment to mix for 5
minutes until homogeneous
By drill mixer or pump mixer
8) Allow the mixtures to stand for about 10 minutes then mix again until homogenous Ready plaster should be used within 2 hours after mixing.
Trang 13Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
9) To apply Jotun Exterior Putty on the ceiling and walls surface for 1st
coat
Patching by trowel only
Scaffolding
Trang 14Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
10) Wait for 8-16 hours or until the surface is partially settled then apply a
2nd coat
Visual and manually checking
11) Sanding after surface dry (3h for minimum applying putty)
12) Interval time for every coat is 8-16 hours at 30oC, minimum
Scaffolding
Trang 15Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
15) Sanding the surface to give a smooth and even finish so as to give an aesthetics appearance
Checking by visual and appropriate equipments
16) To ensure surface is smooth and even
Sanding with appropriate sand paper
17) To ensure surface is dry, clean and stable
Checking by visual and appropriate equipment
18) Proceed coating system as from sealer coat to finishing coat
Refer to coating system data
19) Please refer to Method Statement of Jotun Exterior Putty
Trang 16Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
(Painting should start preferably within 24 hours after preparation If any delay, surface must be checked and re-preparation again if contain other contaminants.)
20) Skimcoat surface must be dried, to ensure moisture content not
exceeding 16%
21) Use Jotasealer Primer to apply as a sealer
Jotashield Primer
Trang 17Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
23) Use adequate mixing equipment to mix for 3 minutes until
homogeneous
By electric mixer if available
24) To apply 1 coat of diluted Jotashield Primer over the Skimcoat surfaces
Applying by medium hair roller
25) Dry for minimum 2 hours at 300C before apply finishing coat
Manually checking
Trang 18Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
26) To apply 2nd coat of diluted Jotashield over the 1st finishing coat
surfaces
By appropriate checking method
27) Allow additional (1-3%) of water for dilution if the diluted paint pot life time over 2 hours
Manually checking Scaffolding
Trang 19Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
30) To ensure surface obtain good covering, uniform color and smooth finish
By appropriate checking method
31) To ensure surface is dry and stable
Manually checking
32) Ensure adequate curing period of paint film are secured (250C * 7 days)
if the paint film performance property test is required
By visual assessing
Trang 20Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
5.2.2 External Wall Painting
1) Surface must be dried To ensure moisture substance not exceeding 20%
Checking with Moisture Meter
2) To remove foreign and unstable matters such as dirt powder, cement splashes and other contaminants
Manual cleaning by chipping, scrapping or wire brushing
Trang 21Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
4) Surface must be free from algae of fungus growth
Fungicidal washing
5) Use Jotun Exterior Putty to apply as plastering
Jotun Exterior Putty
6) Mix 1 bag of Jotun Exterior Putty with 16 litres of water
By volume
7) Use a mixer if available or adequate mixing equipment to mix for 5
minutes until homogeneous
By drill mixer or pump mixer
Trang 22Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
8) Allow the mixtures to stand for about 10 minutes then mix again until homogenous
Ready plaster should be used within 2 hours after mixing
9) To apply Jotun Exterior Putty on the ceiling and walls surface for 1st
coat
Patching by trowel only
`
Trang 23Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
10) Wait for 8-16 hours or until the surface is partially settled then apply a
2nd coat
Visual and manually checking
11) Snding after surface dry (3h for minimum applying putty)
12) Interval time for every coat is 8-16 hours at 30oC, minimum
13) To ensure in order to obtain an even surfaces and reduce roughness
14) To ensure surface is dry and stable
Visual and manually checking
Trang 24Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
15) Sanding the surface to give a smooth and even finish so as to give an aesthetics appearance
Checking by visual and appropriate equipments
16) To ensure surface is smooth and even
Sanding with appropriate sand paper
17) To ensure surface is dry, clean and stable
Checking by visual and appropriate equipment
Trang 25Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
any delay, surface must be checked and re-preparation again if contain other contaminants.)
20) Skimcoat surface must be dried, to ensure moisture content not
Trang 26Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
23) Use adequate mixing equipment to mix for 3 minutes until
homogeneous
By electric mixer if available
24) To apply 1 coat of diluted Jotashield Primer over the Skimcoat surfaces
Applying by medium hair roller
25) Dry for minimum 2 hours at 300C before apply finishing coat
Trang 27Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
26) To apply 2nd coat of diluted Jotashield over the 1st finishing coat
surfaces
By appropriate checking method
27) Allow additional (1-3%) of water for dilution if the diluted paint pot life time over 2 hours
Trang 28Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
30) To ensure surface obtain good covering, uniform color and smooth finish
By appropriate checking method
31) To ensure surface is dry and stable
Manually checking
32) Ensure adequate curing period of paint film are secured (250C * 7 days)
if the paint film performance property test is required
By visual assessing
Trang 29Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
5.2.3 Internal Wall & Ceiling painting
1) Surface must be dried To ensure moisture substance not exceeding
20%
Checking with Moisture Meter
2) To remove foreign and unstable matters such as dirt powder, cement
splashes and other contaminants
Manual cleaning by chipping, scrapping or wire brushing
3) Surface must be free from oil and grease
Wiping with cloth dampened solvent
Trang 30Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
4) Surface must be free from algae of fungus growth
Fungicidal washing
5) Use Jotun Exterior Putty to apply as plastering
Jotun Interior Putty
6) Mix 1 bag of Jotun Interior Putty with 16 litres of water
By volume
7) Use a mixer if available or adequate mixing equipment to mix for 5
minutes until homogeneous
By drill mixer or pump mixer
Trang 31Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
8) Allow the mixtures to stand for about 10 minutes then mix again until
homogenous Ready plaster should be used within 2 hours after mixing
9) To apply Jotun Exterior Putty on the ceiling and walls surface for 1st
coat
Patching by trowel only
Trang 32Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
10) Sanding after surface dry (3h for minimum applying putty)
11) Wait for 8-16 hours or until the surface is partially settled then apply a
2nd coat
Visual and manually checking
12) Interval time for every coat is 8-16 hours at 30oC, minimum
13) To ensure in order to obtain an even surfaces and reduce roughness
14) To ensure surface is dry and stable
Visual and manually checking
15) Sanding the surface to give a smooth and even finish so as to give an
Trang 33Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
16) To ensure surface is smooth and even
Sanding with appropriate sand paper
17) To ensure surface is dry, clean and stable
Checking by visual and appropriate equipment
18) Proceed coating system as from sealer coat to finishing coat
19) Refer to coating system data Please refer to Method Statement of
Jotun Exterior Putty
(Painting should start preferably within 24 hours after preparation If any delay, surface must be checked and re-preparation again if contain other contaminants.)
20) Skimcoat surface must be dried, to ensure moisture content not
exceeding 16%
21) Use Jotasealer Primer to apply as a sealer
Jotasealer Primer
Trang 34Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
22) Mix the sealer with thinner approx 5-10% before application if require
By volume
23) Use adequate mixing equipment to mix for 3 minutes until
homogeneous
By electric mixer if available
24) To apply 1 coat of diluted Jotaplast Primer over the Jotasealer 03
sufaces
Applying by medium hair roller
25) Dry for minimum 2 hours at 300C before apply finishing coat
Trang 35Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
26) To apply 2nd coat of diluted Jotaplast over the 1st finishing coat
surfaces
By appropriate checking method
27) Allow additional (1-3%) of water for dilution if the diluted paint pot life time over 2 hours
Trang 36Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
31) To ensure surface is dry and stable
Manually checking
32) Ensure adequate curing period of paint film are secured (250C * 7 days)
if the paint film performance property test is required
By visual assessing
Trang 37DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT (RIVIERA POINT)
AT DISTRICT 7, HO CHI MINH, VIETNAM
FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
ANNEX 1
Risk Assessment& Job Safety Analisys
Trang 38
Risk Assessment (RA) Process Chart
RA Preparation
SSYENC Engineers and Supervisors to prepare RA, with input from all involved
RA Preparation / RA Approval
Sub Contractors RA Team to prepare the RA and Sub Contractors management personnel to the RA report
To address any comments
Trang 39Environmental, Safety and Health Result Criteria
Catastrophic 5 • Fatality, fatal disease or multiple major injuries
Major 4 • Serious injuries or life threatening occupational disease (includes
amputations, major injuries, occupational cancer, acute poisoning) Moderate 3 • Injury requiring medical treatment of ill health leading to disability
(includes lacerations, burns, sprains, minor fractures, dermatitis, deafness, work related upper limb disorders)
Minor 2 • No injury, injury or ill health requiring first aid treatment only (includes
minor cuts and bruise, irritation, ill health with temporary discomfort)
Negligible 1 • Not likely to cause injury or ill-health
Table II: Accident Frequency categories
Rare 1 Not expected to occur but still possible
Remote 2 Not likely to occur under normal circumstances
Occasional 3 Possible or known to occur
Almost Certain 5 Continual or repeating occurrence
Table III: Risk Matrix
Risk Category
Accident Severity Rare (1) Remote
(2)
Occasion al(3)
Frequen
t (4)
Almost Certain (5)
Trang 40
Table IV: Definition of Risk Index
Risk level Descriptio
Risk shall be accepted subject to demonstration that the level of risk
is as low as reasonably practicable.