METHOD STATEMENT FOR PAINTING WORK

Trang 1

Riviera Point Condominium Development

DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

Riviera Point Project

METHOD STATEMENT

FOR PAINTING WORK

Dept

Prepared by

QC/QA Safety Construction Engineering

Rev Date Description

Approved (by) Ssangyong ICIC KLV Safety RPLLC

A 3-Jun-2013 Issue for Acceptance SC Park M.Tan Bernarrd CM Leong

B 11-Jul-2013 Issue for Acceptance SC Park M.Tan Bernarrd CM Leong

C 20-Aug-2013 Issue for Acceptance SC Park M.Tan Bernarrd CM Leong

Trang 2

Document Reference and Revision: Comment of MOS for painting work_RevB Submission Date:

1 Duc, RPLLC Based on pages 4/96 & 49/96, please clarifyputty, it is Jotun or Seamaster? material use exterior Jotun exterior Putty is right

2 Duc, RPLLC Page 5/96, mixing and stirring process shall be ready inside floor area

In case, side wall on gondola is impossible to be supplied from each floor, that’s why the mixing bucket should carry on gondola from ground

3 Duc, RPLLC How to check and control the density for layers (skim coating, sealer & coating) What is specify in our contract?

By visual checking and controlling the dilution while mixing to water & putty or paint

In order to check for density, paint layers will be checked by the tool of wet film thickness

4 Duc, RPLLC Page 12/96, item 30 “to ensure surface obtain good covering, uniform color and smooth” please specify cover method?

By visual checking and controlling the dilution while mixing to water & putty or paint

5 Duc, RPLLC Page 14/96 please separate method statement for gondola installation work It will be submitted on September Now the painting Method is focused on Mock up

room

To provide:

-Protection method to material during rainy days not specify

- Protection for painted surface has no solution when

it rained, however, before applying paint, the rain possibility will be presumed that checking humidity by phychro-meter, also refer to the national weather forecast, based on that we will get decision to

Trang 3

electric outlet The maximum size of gondola is 0.8mx7.5m Those information can be referred to the presentation data for working platform of architectural works Workers shall be taken on the ground floor Each painting session of area is normally 3-5 points checking for a wall

- Groove line’s substrate will be treated on architectural cage after that putty and painting work

is on gondola

7 Vuong, RPLLC Page contents: what is meaning “please! Refer to the MS for tower

crane (General)”, please

-It is corrected

-Please refer to presentation data for working platform of architectural cage, there has description

of gondola usage

8 Vuong, RPLLC Page 6/96, please check external mock up painting have ceiling or not The external ceiling is the balcony ceiling

9 Vuong, RPLLC Page 17/96, where is method statement of Jotun Exterior Putty It has been described on annex 1.1 and 1.2

10 Vuong, RPLLC Please re-check item 5.2.3, Ssy will use external putty for internal wall & ceiling, it is correct or not? Paint for internal surface: Using Jotun Interior putty It is corrected

11 Vuong, RPLLC Please re-check item 5.2.3, Ssy will use Jotasealer Primer for internal wall & ceiling, it is correct or not? Because the product is used for

external

It is corrected by proper product name, both name are slightly different between Jotasealer 03 for external and Jotasealer primer for internal

12 Vuong, RPLLC Page 34/96, please revise 3comment for page 39/96 rd stage, it is 1st layer not 2nd layer Same It is corrected

13 Bernarrd/ Minh, RPLLC Please provide the completed content as stipulated in MS guideline page 2 It is corrected

14 Bernarrd/ Minh, RPLLC Please provide RA, JSA to the relevant work scope accordingly It is inserted

15 Bernarrd/ Minh, RPLLC Please provide the current organization chart It shall be submitted separately by official submission because the subcontractor would be changed

16 Bernarrd/ Minh, RPLLC Please provide the PPE listing as to the proposed work scope It is inserted

Trang 4

17 Bernarrd/ Minh, RPLLC Please provide material safety data sheet (MSDS) in relationship to all material to be used as proposed in this method It is inserted at annex

18 Bernarrd/ Minh, RPLLC Do not allow to carry out mixing skim coat on scaffold (page 33/96) It is corrected

20 Tan, ICIC

Based on technical data of Jotun Exterior Putty mixing ratio of putty and water is 3:1 by weight It means that 1 bag/40kg of putty will be mixed with 13 litres of water, why did your MOS indicate 16 litres of water?

Confirmed dilution ratio: 40Kg Putty/ 13 litres of water for normal case

We need extra water, in case the plain surface is too dry so that it can get adequate adhesion

21 Tan, ICIC

Based on technical data of Jotun Exterior Putty and Jotun Internal Putty, the drying time of them is different one recoated after 8 hours and another is 24 hours So please separate

The standard drying duration is indicated on technical data sheet However, its time depends on the condition on humidity & windy The other words, inside areas there are times to get higher humility and less ventilation than outside one, in this case, the drying time should be adjusted by crafts mas’ perception on each job’s detail

22 Tan, ICIC Based on technical data of Jotasealer, mixing sealer with the thinner maximum 5%, please comply It will be complied as technical data sheet

23 Tan, ICIC Item 27 - page 11/96: technical data did not indicate it, please explain and get advice of manufacturer Supplier confirmed that when the paint comes to dry in the bucket over 2 hour, water should be added in it

in order to keep the proper viscosity

Trang 5

27 Tan, ICIC

There will be some location where you can not use Architecture working cage and Gondola for painting work So could you tell us you intend to use Spider man for painting work if any you have to get approval from RP client

The remained external area can be accessed all around because the gondola can adjust to approach with extension by 1.7m

B

28 Duc, RPLLC Reply item 4: not cleared

It shall be able to controlled how finished topcoat is

It could incur some damage very soon So we will try to reduce it also

o After completion of applying, check about colour and aesthetic for the finalization

30 Bernarrd, RPLLC No more comment

31 Tan, ICIC Reply item 23: Please provide official confirmation of supplier It is attached on annex of certification

32 Tan, ICIC

Reply item 25: what have difference between Jotun putty and Seamaster putty? As this MOS did not mention to Seamaster putty? Both are same performance to make proper substrate It isn’t indicated the name anymore as

reply no 1

Reviewer’s suggested status code for this revision only:

ICIC Consultant Review Consultant TYLIN Structural JRP MEP Review Consultant Consultant KPK Cost Other (state) Other (state) Other (state) RPLLC

This section is to record the reviewing party’s suggested status code only: the official status code for the submitted item is recorded on the first sheet of this document

Trang 6

Rivera Point Condominium Development

DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

Trang 7

Rivera Point Condominium Development

DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

Project:Rivera Point Condominium Development

Produced by:Ssangyong E&C

1 SCOPE

This method statement is for the Painting work

The working Platform and Gondola will be installed step by step, safely fulfilling as the installation plan by special team based on each method statement

3 EQUIPMENTS AND TOOLS / TACKLES

 Gondola & Scaffolding :

 For treatment of substrate at the external wall surface

 For applying of paniting materials such as Skim coat, Putty, Primer, Paint at the external wall

 Hand tool :

 All tools and tackles supplied by special team under supervision of yong safety dept

Trang 8

Ssang-Rivera Point Condominium Development

DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

4 RESOURCES (Materials, Equipments & Human Resources)

4.1 List of material

Trang 9

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

YES

Working Platform Installation

Primer

1 st Skim coat or Putty

Inspection

by S.A.C

1 st finish coat

Fine Tune NO

2 nd finsh coat

2 nd Skim coat or Putty

NO

Painting complete YES

Trang 10

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

5.2 Description of working sequence

5.2.1 External Mock up painting

1) Surface must be dried To ensure moisture substance not exceeding 20%

 Checking with Moisture Meter

2) To remove foreign and unstable matters such as dirt powder, cement splashes and other contaminants

 Manual cleaning by chipping, scrapping or wire brushing

Trang 11

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

4) Surface must be free from algae of fungus growth

 Fungicidal washing

5) Use Jotun Exterior Putty to apply as plastering

 Jotun Exterior Putty

6) Mix 1 bag of Jotun Exterior Putty with 16 litres of water

 By volume

Trang 12

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

7) Use a mixer if available or adequate mixing equipment to mix for 5

minutes until homogeneous

 By drill mixer or pump mixer

8) Allow the mixtures to stand for about 10 minutes then mix again until homogenous Ready plaster should be used within 2 hours after mixing.

Trang 13

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

9) To apply Jotun Exterior Putty on the ceiling and walls surface for 1st

coat

 Patching by trowel only

Scaffolding

Trang 14

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

10) Wait for 8-16 hours or until the surface is partially settled then apply a

2nd coat

 Visual and manually checking

11) Sanding after surface dry (3h for minimum applying putty)

12) Interval time for every coat is 8-16 hours at 30oC, minimum

Scaffolding

Trang 15

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

15) Sanding the surface to give a smooth and even finish so as to give an aesthetics appearance

 Checking by visual and appropriate equipments

16) To ensure surface is smooth and even

 Sanding with appropriate sand paper

17) To ensure surface is dry, clean and stable

 Checking by visual and appropriate equipment

18) Proceed coating system as from sealer coat to finishing coat

 Refer to coating system data

19) Please refer to Method Statement of Jotun Exterior Putty

Trang 16

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

(Painting should start preferably within 24 hours after preparation If any delay, surface must be checked and re-preparation again if contain other contaminants.)

20) Skimcoat surface must be dried, to ensure moisture content not

exceeding 16%

21) Use Jotasealer Primer to apply as a sealer

 Jotashield Primer

Trang 17

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

23) Use adequate mixing equipment to mix for 3 minutes until

homogeneous

 By electric mixer if available

24) To apply 1 coat of diluted Jotashield Primer over the Skimcoat surfaces

 Applying by medium hair roller

25) Dry for minimum 2 hours at 300C before apply finishing coat

 Manually checking

Trang 18

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

26) To apply 2nd coat of diluted Jotashield over the 1st finishing coat

surfaces

 By appropriate checking method

27) Allow additional (1-3%) of water for dilution if the diluted paint pot life time over 2 hours

 Manually checking Scaffolding

Trang 19

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

30) To ensure surface obtain good covering, uniform color and smooth finish

 By appropriate checking method

31) To ensure surface is dry and stable

 Manually checking

32) Ensure adequate curing period of paint film are secured (250C * 7 days)

if the paint film performance property test is required

 By visual assessing

Trang 20

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

5.2.2 External Wall Painting

1) Surface must be dried To ensure moisture substance not exceeding 20%

 Checking with Moisture Meter

2) To remove foreign and unstable matters such as dirt powder, cement splashes and other contaminants

 Manual cleaning by chipping, scrapping or wire brushing

Trang 21

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

4) Surface must be free from algae of fungus growth

 Fungicidal washing

5) Use Jotun Exterior Putty to apply as plastering

 Jotun Exterior Putty

6) Mix 1 bag of Jotun Exterior Putty with 16 litres of water

 By volume

7) Use a mixer if available or adequate mixing equipment to mix for 5

minutes until homogeneous

 By drill mixer or pump mixer

Trang 22

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

8) Allow the mixtures to stand for about 10 minutes then mix again until homogenous

 Ready plaster should be used within 2 hours after mixing

9) To apply Jotun Exterior Putty on the ceiling and walls surface for 1st

coat

 Patching by trowel only

`

Trang 23

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

10) Wait for 8-16 hours or until the surface is partially settled then apply a

2nd coat

 Visual and manually checking

11) Snding after surface dry (3h for minimum applying putty)

12) Interval time for every coat is 8-16 hours at 30oC, minimum

13) To ensure in order to obtain an even surfaces and reduce roughness

14) To ensure surface is dry and stable

 Visual and manually checking

Trang 24

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

15) Sanding the surface to give a smooth and even finish so as to give an aesthetics appearance

 Checking by visual and appropriate equipments

16) To ensure surface is smooth and even

 Sanding with appropriate sand paper

17) To ensure surface is dry, clean and stable

 Checking by visual and appropriate equipment

Trang 25

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

any delay, surface must be checked and re-preparation again if contain other contaminants.)

20) Skimcoat surface must be dried, to ensure moisture content not

Trang 26

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

23) Use adequate mixing equipment to mix for 3 minutes until

homogeneous

 By electric mixer if available

24) To apply 1 coat of diluted Jotashield Primer over the Skimcoat surfaces

 Applying by medium hair roller

25) Dry for minimum 2 hours at 300C before apply finishing coat

Trang 27

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

26) To apply 2nd coat of diluted Jotashield over the 1st finishing coat

surfaces

 By appropriate checking method

27) Allow additional (1-3%) of water for dilution if the diluted paint pot life time over 2 hours

Trang 28

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

30) To ensure surface obtain good covering, uniform color and smooth finish

 By appropriate checking method

31) To ensure surface is dry and stable

 Manually checking

32) Ensure adequate curing period of paint film are secured (250C * 7 days)

if the paint film performance property test is required

 By visual assessing

Trang 29

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

5.2.3 Internal Wall & Ceiling painting

1) Surface must be dried To ensure moisture substance not exceeding

20%

 Checking with Moisture Meter

2) To remove foreign and unstable matters such as dirt powder, cement

splashes and other contaminants

 Manual cleaning by chipping, scrapping or wire brushing

3) Surface must be free from oil and grease

 Wiping with cloth dampened solvent

Trang 30

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

4) Surface must be free from algae of fungus growth

 Fungicidal washing

5) Use Jotun Exterior Putty to apply as plastering

 Jotun Interior Putty

6) Mix 1 bag of Jotun Interior Putty with 16 litres of water

 By volume

7) Use a mixer if available or adequate mixing equipment to mix for 5

minutes until homogeneous

 By drill mixer or pump mixer

Trang 31

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

8) Allow the mixtures to stand for about 10 minutes then mix again until

homogenous Ready plaster should be used within 2 hours after mixing

9) To apply Jotun Exterior Putty on the ceiling and walls surface for 1st

coat

 Patching by trowel only

Trang 32

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

10) Sanding after surface dry (3h for minimum applying putty)

11) Wait for 8-16 hours or until the surface is partially settled then apply a

2nd coat

 Visual and manually checking

12) Interval time for every coat is 8-16 hours at 30oC, minimum

13) To ensure in order to obtain an even surfaces and reduce roughness

14) To ensure surface is dry and stable

 Visual and manually checking

15) Sanding the surface to give a smooth and even finish so as to give an

Trang 33

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

16) To ensure surface is smooth and even

 Sanding with appropriate sand paper

17) To ensure surface is dry, clean and stable

 Checking by visual and appropriate equipment

18) Proceed coating system as from sealer coat to finishing coat

19) Refer to coating system data Please refer to Method Statement of

Jotun Exterior Putty

(Painting should start preferably within 24 hours after preparation If any delay, surface must be checked and re-preparation again if contain other contaminants.)

20) Skimcoat surface must be dried, to ensure moisture content not

exceeding 16%

21) Use Jotasealer Primer to apply as a sealer

 Jotasealer Primer

Trang 34

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

22) Mix the sealer with thinner approx 5-10% before application if require

 By volume

23) Use adequate mixing equipment to mix for 3 minutes until

homogeneous

 By electric mixer if available

24) To apply 1 coat of diluted Jotaplast Primer over the Jotasealer 03

sufaces

 Applying by medium hair roller

25) Dry for minimum 2 hours at 300C before apply finishing coat

Trang 35

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

26) To apply 2nd coat of diluted Jotaplast over the 1st finishing coat

surfaces

 By appropriate checking method

27) Allow additional (1-3%) of water for dilution if the diluted paint pot life time over 2 hours

Trang 36

Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

31) To ensure surface is dry and stable

 Manually checking

32) Ensure adequate curing period of paint film are secured (250C * 7 days)

if the paint film performance property test is required

 By visual assessing

Trang 37

DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)

FOR PROPOSED CONDOMINIUM DEVELOPMENT (RIVIERA POINT)

AT DISTRICT 7, HO CHI MINH, VIETNAM

FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

ANNEX 1

Risk Assessment& Job Safety Analisys

Trang 38

Risk Assessment (RA) Process Chart

RA Preparation

SSYENC Engineers and Supervisors to prepare RA, with input from all involved

RA Preparation / RA Approval

Sub Contractors RA Team to prepare the RA and Sub Contractors management personnel to the RA report

To address any comments

Trang 39

Environmental, Safety and Health Result Criteria

Catastrophic 5 • Fatality, fatal disease or multiple major injuries

Major 4 • Serious injuries or life threatening occupational disease (includes

amputations, major injuries, occupational cancer, acute poisoning) Moderate 3 • Injury requiring medical treatment of ill health leading to disability

(includes lacerations, burns, sprains, minor fractures, dermatitis, deafness, work related upper limb disorders)

Minor 2 • No injury, injury or ill health requiring first aid treatment only (includes

minor cuts and bruise, irritation, ill health with temporary discomfort)

Negligible 1 • Not likely to cause injury or ill-health

Table II: Accident Frequency categories

Rare 1 Not expected to occur but still possible

Remote 2 Not likely to occur under normal circumstances

Occasional 3 Possible or known to occur

Almost Certain 5 Continual or repeating occurrence

Table III: Risk Matrix

Risk Category

Accident Severity Rare (1) Remote

(2)

Occasion al(3)

Frequen

t (4)

Almost Certain (5)

Trang 40

Table IV: Definition of Risk Index

Risk level Descriptio

Risk shall be accepted subject to demonstration that the level of risk

is as low as reasonably practicable.