Excavation foundation Lean concrete Pile head treatment Installation of form work Formwork fabrication Casting concrete Curing concrete Back filling... - Casting lean concrete + Completi
Trang 2Prepared by Lương Văn Lượngng Văn Lượngng Deputy Site Manager
Reviewed by Ph m Vũ Namạm Vũ Nam Site Manager
Approved by Nguy n Vănễn Văn
Trang 3METHOD STATEMENT
FOR
RC FOOTINGS
Contents
1 INTRODUCTION 4
1.1 PURPOSE 4
1.2 DEFINITIONS: 4
2 BUILDING DESCRIPTION: 5
3 ORGANIZATION CHART 8
3.1 Organization Chart 8
3.2 Assignment 9
4 FLOW CHART AND DIRECTION OF WORK 10
5 SCHEDULE 11
6 SPECIFIC STANDARD 11
7 TOOL & EQUIPMENT 12
8 MATERIALS 12
9 MATERIALS HANDLING, STORAGE AND DELIVERY 13
10 PREPARATION WORKS 13
11 CONSTRUCTION METHOD 15
11.1 Excavation foundation 15
Trang 411.4 Installation of Form work 19
11.5 Steel works 20
11.6 Concrete work 21
11.7 Back filling 22
12 QUALITY CONTROL 22
13 SAFETY PLAN 24
14 APENDIX 25
Trang 51 INTRODUCTION
1.1 PURPOSE
The purpose of this Method Statement is to set the policy for construction procedures and qualityaccording to Contract Specifications To outline the work instruction by which RC Footings is carriedout
1.2 DEFINITIONS:
PROJECT PARTICULARS:
Project name : SMC MANUFACTURING (VIET NAM) FACTORY-PHASE 1 PROJECT
Address : Long Duc Industrial Park, Long Duc Ward, Long Thanh District, Dong Nai Province,
Viet Nam
PARTY:
Client/ Owner : SMC MANUFACTURING VIETNAM CO., LTD
Contractor : KAJIMA OVERSEAS ASEA PTE LTD
Responsible for the supervision of Contractors who will construct the podium and all related activities as outlined in this procedure
SCOPE OF WORK
The works to be carried out by Sub-Contractor (ACSC) and shall apply for works at Factory No.1 of SMC
MANUFACTURING (VIET NAM) FACTORY- PHASE 1 PROJECT
1 Construction Reinforcement Concrete Structure works included:
a Pile head treatment
Trang 62 BUILDING DESCRIPTION:
Location:
Factory No.1 are located at the corner of Road No.D5 &N2-5 in Long Duc Industrial park as below
Description:
- Building purpose : Factory
- Foundation : Spun piles (D300, 350, 400 mm)
- Structure :RC structures + steel rafter; Slab on grade
Trang 7GROUND FLOOR PLAN
Thay mat catnay bang ban
ve moi
Trang 8- Slab thickness:
o Factory Ground floor slab : 300 mm thk
o Storage/Utilities Ground Floor slab : 150 mm thk
Trang 9Deputy Site Manager 1
NGUYỄN HOÀNG TRINH (MP:090 291 1235)
nghoangtrinh@acsc.com.vn
Deputy Site Manager 2
LƯƠNG VĂN LƯỢNG (MP: 093 734 3055)
Thái Doãn Long (MP:097 799 7711)
Hoàng Văn Hải (MP:908 818 1059)
Safety Supervisors
Phạm Văn Mạnh (MP:097 235 2459)
Nguyễn Văn Triểu (MP:093 996 0180)
Construction teams
Trang 103.2 Assignment
NGUYỄN MINH TUẤN
TRẦN AN TOÀNTRƯƠNG THANH VIỆT
Trang 114 FLOW CHART AND DIRECTION OF WORK
The work sequence of construction the RC footings is shown at the following flow chart
Excavation foundation
Lean concrete
Pile head treatment
Installation of form work Formwork fabrication
Casting concrete
Curing concrete
Back filling
Trang 125 SCHEDULE
Construction Schedule of Footings is attached in Appendix-2
6 SPECIFIC STANDARD
Reinforced Concrete Footings shall be carried out in accordance with the requirements of:
- SMC MANUFACTURING (VIET NAM) FACTORY-PHASE 1 PROJECT Specification for Footing works
- Current Vietnamese Construction Standards
+ TCVN 4447-2012 Vietnamese standard 4447-2012 (Earth works - construction, check and acceptance)
+ TCVN 5593 : 1991 Vietnamese standard 5593-1991 (Building engineering work - Permissible tolerances in geometry)
+ TCVN 1651-2008 Vietnamese standard 1651-2008 ( Steel for the reinforcement concrete, part1+2)
+ TCVN 4453 – 1995 Vietnamese standard 4453-1995 (Concrete structures- codes for
construction, check and acceptance)
+ TCXDVN 371 - 2006 Vietnamese standard 371-2006 (Acceptance of constructional quality of
building works)
- Related Materials approved by KAJIMA & Owner
Trang 137 TOOL & EQUIPMENT
The equipment to be used for the construction of Footings is listed below
Submersible Pump 4 inches, H=24m
Straightening
machine
Nos 1 Use for reinforcing steel work
Diameter <8mm
Screwdriver /Drilling
machine
Nos 14 Manufacturing formwork
8 MATERIALS
Trang 14b/ Steel rebar: (supplied by KOA)
- With Diameter < 10mm: SR295
- With Diameter >10mm : SD390, B15-B35
c/ Form work:
- Plywood, 18mm thk reinforced with steel box 5x5 (cm), 4x8 (cm)
9 MATERIALS HANDLING, STORAGE AND DELIVERY
- Concrete : Ready- mixed concrete are transported from batching plant to site in concrete truck (6
to 12 m3 capacity) The concrete must be delivered to site within maximum 60 minutes depend
on the mix design of concrete supplier
- Formwork : Formwork will be pre-fabricated then stocked on yard with protection of plastic cover Before installing, the formwork will be transported to site and placed near the excavation
- Steel rebar : Steel bars are stored on the steel platform or concrete blocks to prevent the contact
of steel rebar with the ground All steel rebar are stocked in the steel yard with roofing and cover with plastic sheet to protect them with rain water
- Other materials are keeping in storage and they are transported to the site work when they are
in used
10.PREPARATION WORKS
- Excavation foundation
+ Receiving the construction area transited by KOA
+ Receiving the coordinate, benchmark system from main Contractor (KOA)
+ Clearing the ground and remove any obstruction on the ground
+ Set up drainage system for rainwater and underground water inside and outside pit
+ Prepare internal road from the excavation to the stock yard of surplus soil
+ Setting out excavations with their center lines, dimension and marking on the ground
Trang 15+ Manufacturing the steel plate of pile cap starter bars.
+ Marking the cutting level of the piles
+ Preparing and check the cutting machine
- Casting lean concrete
+ Completing the excavation above design level about 100mm high
+ Drainage and pump water regularly, keep the pit dry
+ Trimming the surplus soil by hand to the design elevation
+ Compacting the base of foundation and testing, if required
- Installation of form work
+ Completing lean concrete
+ Setting out and marking the gridlines and dimensions of footings on lean concrete surface.+ Pre-fabricate formwork
+ Cleaning and applying release agent on formwork surface, if required
- Installation of rebar
+ Shape and dimension of rebar
+ Machine for fabricate rebar
+ Obtaining the approved Shop drawings
- Casting concrete
+ Inspecting of rebar and formwork (record, pictures)
+ Prepare internal road for delivery concrete
+ Cleaning formwork, lean concrete's surface, pump water out of pit
+ Check finishing level of concrete
+ Covered starter rebar by PVC sheet before casting
+ Prepare bucket or slide for casting from top to bottom
+ Order the concrete
Trang 1611.CONSTRUCTION METHOD
11.1 Excavation foundation
Step 1: Survey and mark the foundation on the ground
Step 2: Excavate the soil: Using 2 backhoe machines (0.7 m3) to excavate the soil Factory No.1 is divided into three zones: zone 1 (axis A-E/ 1-6); zone 2 (axis A-E/ 7-11), zone 3 (axis A-E/ 12-15)
BACK HOE MACHINE NO.2
Trang 17 Step 3: Transportation and disposal surplus soil.
a Stocked soil:
Surplus soil will be transported to the soil reservation location on the site designated by KOA For the back filling process, the soil is gathered as masses which less than 1.5m height and more than 1.5m distance far from the edge of opening hole It is temporary covered by canvas to prevent the dust and used for back fillingprocess later
The volume of soil stocked on construction area (for backfilling) are calculated based on the excavated soil deducted the volume of concrete of footings and stump columns occupied in excavation The volume of excavated soil, volume occupied with concrete and remaining stock soils are shown in table below:
3 F1-F1 A 2.00 46.85
F1 8.00 155.25 F2 8.00 150.96
Trang 182 F1A(-1800) 8 3.39
3 F2( -2100) 27 49.14 F2(-2800) 2 3.64
Volume of compacted soil to be backfilled= 2,377.74 – 253.78 = 2123.95 m3
Volume of compacted surplus soil to be removed= 253.78 m3
Volume of ripped surplus soil to be removed= 253.78 x 1.3 = 329.92 m3
Volume of ripped soil to be backfilled = 2123.95 x 1.3 = 2761.14 m3
where 1.3 is the coefficient of ripping.
The ripped soil to be backfilled will be stocked on construction areas at height 1.5m with quantity and volume
as shown in table:
Trang 19The location of stocked soil on site as shown in the attached drawing.
The surplus soil will be transported by truck to the stock yard (≈2000 m2) designated by KOA Remaining soil will be leveled at height of 0.5m from existing ground level
b De-watering excavation:
Because of construction in rainy season, a collection pit (WxLxH: 50 x 50 x 50 cm) will be dig in each
ACSC Soil stockarea
Trang 2011.2 Lean concrete.
Step 1 : Trimming the soil: This work is carried out by digging to form an even and firm base at the right bottom levels of foundation
Step 2 : Using the soil compactor to compress the soil to get the level K >= 0.95
Step 3 : Using steel box 50x100 to manufacture the form work for foundation lean concrete layer
Step 4 : Casting lean concrete grade B10, stone 1x2
Lean concrete Steel box 50x100 Welding line
11.3 Pile head treatment
Step 1 : Designated cut-off level should be marked by marker around concrete surface of the pile to keep cutting edge clear and the perimeter of cut-off level marking should be cut in about 20mm depth by small concrete cutter
Step 2 : Cutting the spun piles at the designed level After cutting, the eccentricity of the pile center should be surveyed and recorded (by others)
The surplus segments of cut plie will be moved out of the excavation by excavator then transported and temporarily stocked in the designated stock yard Later all the remaining
of cut piles will be moved out the site by ACSC
Trang 21PILE CAP DETAIL
STEEL PLATE Ø170x2mm
REBAR - SD295A
4 Ø12 - L=1000
CONCRETE INSIDE B20
300 60180 60
VIEW "A"
STEEL BAR 2Ø10
Step 3 : Install the assembly of steel plate and rebar inside the pile head It is temporary hung by the wire fixed to 02 cross rebars on top of pile head Starter rebars are attached
to steel plate by welding
Step 4 : Casting concrete B20 inside pile head and vibrating concrete
11.4 Formwork calculation:
Formwork of footings are made of plywood 18mm thk and steel boxes
11.5 Installation of Form work
Step 1: Install the pre-fabricated formwork at the locations and dimensions, which are marked before
Step 2: Fix the bottom of formwork with steel box, nails
Step 3: Adjust the formwork to be plumb and straight with steel propping and adjusting jack
Trang 22Base jack
Round tube steel D49 Steel box 40x80mm
GFL± 0.000
Refer to bottom level of foundation
TYPICAL ELEVATION OF FORM WORK INSTALLATION FOR FOUNDATION
TYPICAL LAYOUT OF FORM WORK INSTALLATION FOR FOUNDATION
Wooden plate thk 18mm Steel box 50x50mm
Step 1: Cleaning rebar surface
Step 2: Fabricate the steel rebar by cutting, bending in compliance with approved shop drawings Tagging the steel rebar
Step 3: Transport the fabricated steel rebar to site
Step 4: Marking the positions of rebars on lean concrete surface and place the rebars in sequence bottom first and then top Position for lap and lap length as direction
Step 5: Tie the steel rebars securely with wire in correct positions and distance
Step 6: Insert spacers under and outside of steel cage to form the concrete cover
Trang 23TYPICAL LAYOUT OF REBAR INSTALLATION FOR FOUNDATION
Step 4: Check the finished top level of concrete surface and remove surplus concrete
Step 5: Finishing the concrete surface with troweling
DRAINAGE HOLE STEEL LADDER
SAFTY BARRICADE
1110 2000
Trang 24HESSIAN SHEET
11.8 Back filling
+ Marking the elevations of each backfilled layer on footing/stump columns The thickness of each layer is not exceed 0.3m/ layer
+ Backfill the excavation with excavated soil layer by layer
+ Leveling the soil
+ Compacting using rammer to reach the designed compaction ratio K≥ 0.95
+ Repeat the backfill and compaction until reach to the finished level
12.QUALITY CONTROL
With regards to the quality control, all works shall be carried out following the established Project Quality Control Plan Method to treat mistake or defect during constructing:
- Excavation foundation:
+ Locate position of project by survey machine
+ Determine the level of bottom slab by leveling machine
+ Check dimension of pit by tape
+ Tolerance for border, center line, dimension of pit: ± 20cm
- Lean concrete:
+ Check the surface by survey machine, tolerance ±1cm
Trang 25+ Check rigidity and stability of bracing.
- Installation of rebar
+ Checking material: certificate, check dimension by caliper, take the sample for checking physical-mechanical
+ Check the length, number, position, anchor length, joint by visual and ruler
+ Thickness of protection: checking by tape
+ Tolerance for installation: Spacing among main rebars: 20mm, Stirrups spacing: 10mm.+ Tolerance for protection layer: Foundation: 10mm
+ Tolerance for fabrication: The whole length: 20mm, bending: 20mm
+ Lap length: Rebar SD390 Ribbed bar: 40d (tensile), 15d (compressive)
- Casting concrete
+ Level tolerance on surface: 20mm
+ Horizontal tolerance of section: ± 8mm
- Back filling
+ Inspect each layer after compacting
+ Testing compaction factor as technical requirements and method of owner
Trang 2613.SAFETY PLAN
With regard to health and safety control, all the works shall be carried out following the established Project Occupational Health and Safety Control Plan (ST-PL-POHSCP)
No Description of job Hazards Hazard events Preventive measures Action by
1 Excavation works +Traffic accident
duringmobilization/demobilization + Accident duringexcavation andtransportationthe soil
+ The soil around
of foundation can
be slide
Injury or death to workers or operators
+ Security standby and control
Mobilization/demobilizationshould not carry out duringheavy traffic jam (morningtime/evening time)
+ Excavator should observeroads speed limits
+ Follow strictly the method
to prevent the landslide
Heavy objects must stand by
at least 1.5m from the edge ofopening excavation
+ Apply the barrier, ribbon &
signboard to prevent theworkers fall down to the pit
+ Excavator driver must haslicense, excavator must beverify certificate and goodactive status
Forman / Supervisor / Worker
2 Pile cap treatment Fall down of
concreteequipmentaccessoriesworker hit bythese fallingobjects
Injury of people/worker
+ Workers must alert whenthey start breaking work
+ Workers wear protectiveequipment
during breaking works
Forman / Supervisor / Worker
3 Form and Re-bar
Installation and
Concreting Works
Fall down of concrete equipment accessories worker hit by these falling objects
Injury of people/worker
+ Workers must alert wheninstallation of heavy steelmaterials and duringwelding works
+ Wear protective equipmentduring
installation and concreting works
Forman / Supervisor / Worker
Injury of people/
worker
+ Provide qualified personnels to do and supervise the job
Forman / Supervisor
5 Backfilling works Workers struck or
hit by falling fill materials or equipments
Injury of people/
worker
Provide proper equipment platform and qualified signal man for dump trucksunloading backfill
materials
Forman / Supervisor