10 2.3.3 Inspection of Excavations All excavations are to be inspected and must be approved by VINACONEX E&C engineer before gravel and lean concrete is laid in case the work is carried
Trang 1CONTENT
CHAPTER 1 TEMPORARY WORK & PREPARATION 4
1.1 GENERAL 4
1.2 SITE INSPECTION, ATTACHING BATTER BOARDS, SCAFFOLDING 4
1.3 TEMPORARY ACCESS ROAD 5
1.4 MATERIAL STORAGE YARDS, CONSTRUCTION SHEDS AND OTHER
TEMPORARY WORKS 6
1.5 REMOVAL OF TEMPORARY UNITS AND OTHERS 6
CHAPTER 2 EARTH WORK 7
2.1 GENERAL REQUIREMENT 7
2.2 EARTH WORK SUPPORT 8
2.3 METHOD OF EXECUTION 8
CHAPTER 3 REINFORCEMENT WORKS 12
3.1 MATERIALS 12
3.2 PROCESSING AND ASSEMBLY 12
3.3 ARRANGEMENT OF BARS 13
3.4 HOLES IN BEAMS AND OTHER CASE 13
CHAPTER 4 FORMWORKS 15
4.1 MATERIALS AND CONSTRUCTION 15
4.2 ASSEMBLY 16
4.3 FORMWORK INSTALLATION 17
4.4 FORMWORK REMOVAL 17
4.5 HEAD TREATMENT FOR FORM TIGHTENING PARTS 18
CHAPTER 5 CONCRETE WORK 19
5.1 GENERAL 19
5.2 CONCRETE CASTING PLAN 19
5.3 MATERIALS FOR NORMAL WEIGHT CONCRETE 20
5.4 MIX PROPORTION OF ORDINARY CONCRETE 20
5.5 PRODUCTION, TRANSPORT AND PLACEMENT OF CONCRETE 21
5.6 TESTING 24
5.7 TROWEL FINISH FOR FLOOR CONCRETE 25
CHAPTER 6 ERECTING COMPONENTS 27
6.1 GENERAL CHARACTERISTIC OF EXECUTIAT THE SITE 27
Trang 26.2 EXECUTED ORGANIZATION 28
6.3 ORGANIZING AND WORKING METHOD 29
6.4 ERECTING METHOD 31
6.5 GENERAL REGULATION 37
CHAPTER 7 STRUCTURAL STEEL WORK 38
7.1 GENERAL 38
7.2 MATERIALS REQUIREMENTS 38
7.3 GENERAL SHOP DRAWINGS 39
7.4 ANCHOR BOLT SETTING 43
7.5 WELDED JOINTS 45
7.6 PAINTING 50
7.7 OTHER NOTICES ON FABRICATING STEEL STRUCTURES 50
CHAPTER 8 FINISHING WORKS 52
8.1 WATERPROOFING 52
8.2 BRICK WORK 53
8.3 DOOR FRAMES INSTALLATION 53
8.4 PLASTER WORK 55
8.5 TILE WORK 57
8.6 PAINTING WORKS 61
8.7 CEILING WORK 62
8.8 METAL WORK 63
CHAPTER 9 INTERNAL ROAD 65
9.1 ROADWAY EXCAVATION 65
9.2 METHOD APPLIED FOR CONSTRUCTION OF SUB-GRADE 65
9.3 THE METHOD APPLIED FOR CONSTRUCTION OF BASE AND SUB-BASE COURSE 66
9.4 THE CONSTRUCTION METHOD OF ROAD STRUCTURE 68
CHAPTER 10 HSE PLAN 74
10.1 GENERAL 74
10.2 SAFETY ORGANIZATION: 74
10.3 SAFETY PLAN: 75
10.4 SAFETY REPORTS: 85
10.5 NOTIFICATION OF ACCIDENT: 85
Trang 33
Trang 4accordance with specifications or instruction of the Engineer
Major sequence and plan for construction
1.2 SITE INSPECTION, ATTACHING BATTER BOARDS, SCAFFOLDING,
Etc
1.2.1 Checking Site Conditions and Staking Out
After verifying the conditions on site, the location of the building shall be indicated by staking out or other suitable method and this shall be inspected by the Engineer
Trang 5Benchmarks shall be inspected by the Engineer
1.2.3 Attaching Batter Boards
After staking out the site, install batter boards at the corners and other important points of the building, and provide temporary making for setting line
at a place where the work will not be affected
The top of the batter board shall be planed using a planer and attached horizontally to the ground stakes with nails
When attaching batter boards clearly indicate the location of the building and horizontal reference and ask the Engineer to inspect the batter boards
1.2.4 Scaffolding
Scaffolding, landing stages, temporary enclosures etc shall be built with appropriate materials and structures in accordance with the labor law, building standard law, requirements for public disaster prevention in construction and other relevant laws
1.3 TEMPORARY ACCESS ROAD
1.3.1 Clearing and Grubbing and Tree Removal
The Contractor shall clear and/or grub, including disposal as required all surface objects and all trees, down timber, rotten wood, stumps, roots, snags, brush, other vegetation, rubbish, and other protruding obstructions not designated to remain
In area under roadway embankments, from which the topsoil or unsuitable materials are to be removed or which are designated to be compacted, the Contractor shall remove all stumps and roots to a depth at least 20 cm below the original ground surface and at least 15 cm below the bottom of the lowest pavement layer
In roadway cut area, all stumps and roots shall be remove to a depth of not less than 30 cm below the finished sub-grade level
Voids left after removal of roots shall be filled with suitable compacted materials as approved by the Engineer
1.3.2 Topsoil Stripping
The Contractor shall remove the topsoil in area under roadway embankment or where designated by the Engineer, and stockpile / dispose of it to the approved area as directed by the Engineer
When the topsoil will be used for dressing of the slopes of the embankment or other area as directed by the Engineer or as indicated on the drawings, the Contractor shall place and spread the stockpiled topsoil in such designated area After spreading, the topsoil shall be raked to form a smooth surface free from weeds, roots, sods and large stones
Removal of topsoil shall be executed to the depth as directed by the Engineer, and the topsoil shall be kept separate from other excavated materials
1.3.3 Disposal of Cleared Materials
All cleared material is the property of the Engineer and shall be used or disposed of as the Employer sees fit
The Contractor shall haul all cleared material from the clearing and grubbing
Trang 6operation to locations designated by the Engineer No accumulation of debris shall remain on or adjacent to the right-of-way
1.4 MATERIAL STORAGE YARDS, CONSTRUCTION SHEDS AND
OTHER TEMPORARY WORKS
1.4.1 Materials storage yards
Material storage yards or construction sheds, etc shall be allocated and constructed to suit the stored material and depend on site organizing plan 1.4.2 Storehouses for explosives
Storehouses for flammable materials such as paints and oil shall conform to the relevant laws and be situated as far as possible from buildings, construction sheds, material storage yards etc The roof and interior and exterior walls and ceilings shall be of fire-preventive construction or be covered with a fire protection material; each door shall be lockable, and provided with a
"CAUTION: FLAMMABLES" notice and fire extinguisher
1.4.3 Contractor's Offices and other rooms
The contractor's office, toilet, etc shall be provided
Signboards displaying the name of the construction work, name of owner and other details shall be installed at a suitable location on the construction site
1.5 REMOVAL OF TEMPORARY UNITS AND OTHERS
If a temporary construction is disturbing the progress of work or the use of other buildings within the premises, then the contractor shall negotiate with the Engineer for its removal
In the event that there is no place to move the temporary construction, then part of the construction may be used if approved by the Engineer
The temporary constructions should be removed, the construction area as well nearby areas cleared and cleaned and the ground surface leveled before the formal completion of the construction work
Trang 72.1.2 Excavation and backfilling
Excavation should be suited to the situation in surrounding areas, geology and groundwater conditions, and slope surface protection or landslide protection shall be employed in accordance with the relevant laws so as to prevent the collapse of sediment
Where buildings adjacent to the excavation area are likely to be collapsed or broken, adequate measures shall be taken in advance to prevent such occurrences
Where underground water supply or drain pipe, gas pipe or cables are likely to
be discovered, a survey shall be conducted In the event that a buried object is found, it shall be carefully handled so as not to cause damage All necessary emergency measures shall be taken, and the final outcome shall be determined through discussing with the Engineer and/or the authority concerned
All minor obstacles to construction work shall be removed The treatment of major obstacles shall be discussed with the Engineer
The bottom of cutting shall be excavated without disturbing the ground, and inspected by the Engineer upon completion of the excavation
2.1.3 Drainage
Rainwater, spring water, stagnant water, etc that may hinder construction shall
be removed via drain ditches, catching basins or pumps Where unusual freshet is seriously affecting the execution of the work, this matter shall be brought to the attention of the Engineer
Appropriate measures shall be taken before draining water from the excavated area so as not to influence the bottom of the cutting, the surface of slope, construction site or neighboring areas
2.1.4 Backfilling and Filling
Prior to Backfilling, remove formwork and other objects located in the area to
be backfilled Consult the Engineer in the event that formwork shall remain as they are
Consult the Engineer if the excavated soils are not suited to the backfilling and fill
Extra fill settlement or allowance may be required depending on the soils
Trang 88
2.1.5 Grading
Grading (leveling) shall be performed for a width of approximately 1m around the building in order to drain away water
2.1.6 Disposal of Earth Generated during Construction
Earth generated from the construction work shall be transported outside the premises and disposed of in a suitable manner in accordance with local regulations
In the event that some of earth generated from the construction work can be reused, under consultation with the Engineer and/or the local authority
2.2 EARTH WORK SUPPORT
Earthwork shall be supported safely and securely in accordance with the local regulations and/or the Engineer’s directions
Earthwork supporting system shall be submitted to the Engineer for approval with calculation sheet
During execution due attention should be given to the stress and deformation with a view to potential disasters
When installing earthwork support works, constantly check and measure the adjacent ground for potential landslides Should any abnormal state be detected, adequate steps shall be immediately taken and a report made to the Engineer
Removal of earthwork support structures shall be performed in a careful manner after verifying the safety level The holes left after steel sheet piles are pulled out shall be immediately backfilled with sand or other suitable material directed by the Engineer, thereby preventing deformation of the ground
2.3 METHOD OF EXECUTION
2.3.1 Excavation
All excavation shall be carried out to the required lengths, depths, inclinations and curvatures as may be necessary for the constructions of the work or as shown on the drawings in whatever material that may be found, including top soil and the surplus soil shall be disposed of as VINACONEX E&C engineers may instruct
Excavation for foundation shall extend a sufficient distance from the footing (approximately 50 cm) to create appropriate space for placing and removal of forms
The bottoms of all excavation shall be leveled carefully, unless otherwise on the drawing or by VINACONEX E&C engineers’ instructions
2.3.2 Excavation Process
- Machine Excavation
The purpose of machine excavation is to speed up the process Follow this procedure, excavation machine can not break the underground soil structure which according to the design of foundation Excavator will not be able to excavate the small space, but that soil will be excavated
Trang 9Checking-level pole will be used to correct the level of ground during excavation by hand
Trang 1010
2.3.3 Inspection of Excavations
All excavations are to be inspected and must be approved by VINACONEX E&C engineer before gravel and lean concrete is laid (in case the work is carried out by a sub contractor of VINACONEX E&C) The sub contractor shall inform VINACONEX E&C engineer in time to allow VINACONEX E&C’s inspector to make the visual inspection of the excavation works
2.3.4 Additional Excavation
If it is necessary for any reason to form, extend and/or deepen foundations under or around any part of the work, the additional excavation shall be processed
2.3.5 Inspection before Filling
No filling in shall be commenced until the concrete foundations have been inspected by VINACONEX E&C engineer in charge
2.3.6 Upholding Sides of Excavation
When it is necessary, upholding the sides of excavations shall be processed to prevent any damage to adjacent structure and buildings caused by collapsing
of sides and embankments of excavations
2.3.7 Timber, etc Left in Excavations
Timbering, dust, debris, rubbish, etc Shall not be left in when excavations are being filled
2.3.8 Removal of Surplus Soil
All surplus excavated material, rubbish and waste matter shall be removed from the site The place for disposal shall be selected by site manager or by sub contractor
2.3.9 Keeping Excavation Free From Water
Powered pumping, drainage or otherwise shall be used to keep the whole of
Trang 1111
the excavation free from water issues which may be arised by rain, flood, drain, springs or any other cause If the work is carried out by a sub contractor
of VINACONEX E&C, they shall consult VINACONEX E&C engineer being
in charge before he starts with the excavation works that suitable equipment,
in good working condition is available on the project site
2.3.10 Conclusion
There are many important matters that we have to pay attention in order to carry out the project successfully:
- Preparation period of work: study drawing and engineering
specifications, quantity surveying, execution method
- Master schedule and detail schedule of work
- Supervision on site and meeting with all of Team every day
- Report in tomorrow’s work meeting every day (location, quantity,
transportation way)
- Writing report after the wok has been completed
Trang 12cover-3.2 PROCESSING AND ASSEMBLY
Do not use gas pressure welded joints for SD 295A, or lap joints for sizes over D29
Reinforcing bars with dangerous bends, cracks, splits or other defects shall not
be used under any circumstances
Reinforcing bars in coil form shall be straightened by a straightening machine before use
Reinforcing bars shall be cut with shear cutters or saws Gas cutting is permitted where unavoidable, if approved by the Engineer
Spot welding and arc strike shall not be permitted for reinforcing bars Reinforcing bars, however, is spot-welded after preheating if approved by the Engineer
- Hooks at each end of the reinforcing bars shall be provided where:
- The main reinforcements are located at the four corners of a column, at
lap joints and at the top of column at the highest story
- The lap joints to the main reinforcement of beam are located at the
outer corners and at the both ends of the lower portion of beam, except for foundation beams
- Base reinforcing bars for pile foundation
- Hoop, stirrup and yoke bar
Trang 133.2.2 Thickness of Cover Concrete and Interval of Reinforcing Bars
The minimum thickness of cover concrete of reinforcing bars and welded wire fabric shall conform to show on the structural drawings in the Design Documents When using bars larger than D29 as the main reinforcement of columns or beams, the minimum thickness of cover concrete for main reinforcement specifications shall be calculated by multiplying the diameter
by at least 1.5
The thickness of cover concrete used for the processing of reinforcing bars for column and beam specifications shall be the sum of the minimum thickness of cover concrete plus 10mm as standards
For steel frame reinforced concrete structures, the gap between the main reinforcement and steel frame parallel to each other shall conform above
3.3 ARRANGEMENT OF BARS
Reinforcing bars for all concrete structures shall be arranged in strict accordance with the requirement shown on the structural drawings in the Design Documents, unless otherwise directed by Site Engineers
3.4 HOLES IN BEAMS AND OTHER CASE
Reinforcement of through holes in beams shall conform to the following, unless otherwise shown on the structural drawings in the Design Documents
- Diameter of the holes shall be less than one-third of beam depth If the
hole is not round in shape its diameter of circumscribed circle shall conform to the above
- Limit of the center of the hole shall be separated at least 1.2D (where D
is beam depth) from the face of a column or an orthogonal beam (small beam) as a rule
- If the holes are placed in parallel, then the distance between the centers
of two through holes shall be at least three times the average diameter
of the holes
- Vertical bars and upper and lower vertical beams shall be arranged in
the form of stirrup
- Bars of reinforcement shall be placed inside main bars or, where this is
not possible, placed inside after obtaining approval from the Engineer
- Special reinforcement may be omitted if the diameter of the holes is
less than one-tenth of the beam depth and also less than 150mm
- Excess length of welded wire fabric shall be more than one gird mesh
and projection shall be over 10mm
- Ring bar attached to welded wire net shall be welded to the wire net at
least at 4 points
Trang 1414
- Start point of layout for welded wire net shall be below the stirrup for
horizontal bars and at the center of through hole for vertical bar
Trang 1515
CHAPTER 4 FORMWORKS
4.1 MATERIALS AND CONSTRUCTION
Sheathing boards and timbering shall be used These shall be able to withstand external forces such as working load, deadweight of concrete, lateral pressure, vibration and horizontal load, and have a form which does not bring about dangerous levels of distortion or strain
Metal or wooden member shall be used in timbering
The following items shall be satisfied: For exposed concrete finishes, the finish on the concrete surface shall conform to the concrete finish surface specification
When using a steel deck instead of sheathing boards the plate for floor concrete forms shall be provided at a stable floor surface
Form tightening parts shall be bolt type, although annealed wire may be used for catch basins
Release agent (such as form oil), if applied, shall be obtained approval form the Engineer before application
Old members may be used in some cases as concrete forms: When using old sheathing boards, tightening holes or the like shall be repaired as required and surfaces completely cleaned
Trang 1616
4.2 ASSEMBLY
Sequence of construction for column & wall
Working drawings for concrete works shall be submitted to the Engineer for approval
The required setting-out shall be performed prior to assembly, and the most important setting shall be inspected by the Engineer
Sheathing boards shall be assembled in accordance with the location, shape and dimensions of concrete to be molded
All sleeves, boxes, metal parts to be embedded and other objects inside forms shall be firmly attached before pouring concrete Sleeves shall conform to
"through holes and other"
Supports shall be fixed vertically and directly above other supports in the lower story as a general rule
Forms shall not be connected to other temporary works such as scaffolding, batter boards, etc
When using steel deck plates as floor concrete forms, and appropriate strength shall be provided for form members to be connected together
Cones shall be used for form - tightening parts in the following locations :
- Face directly touching earth (except footings, foundation beams
without basement, etc.)
Trang 1717
- Backing for waterproof
- Exposed finish concrete surface
- Surface to be directly finished with thin finish material such as paint
coat, wall paper, etc
- Surface on which an insulating material is to be attached
- In order to achieve high quality of concrete work, steel form will be
used for the project Our amount of steel form is enough to meet requirement of the project In case of lack of form, additional form will
be fabricated The fabrication process includes material, tools and machine's preparation Special form will be made especially according
to structure design All of additional form is to meet the general requirements, stiff and hard enough
4.3 FORMWORK INSTALLATION
4.3.1 Marking
Marking is the first step of setting form process A grid line system must be established in advance so that marking work can base on Center- lines of structure will be made base on the established grid line's system
4.3.2 Assembly Work
All steel form must be sufficiently prepared in advanced Steel form must be cleaned and applied a thin layer of special oil to avoid concrete remaining when remove form
Foundation
Sequence of work includes placing steel form for foundation, adjust the level and verticality with a plumb bob After everything is set, start fixing with form ties and support
Form after being set must be vertical Top level of potential concrete must be marked on form surface
Column and Wall
Before setting, form must be cleaned carefully at its bottom
During process of erection form for wall and column, verticality must be checked with a plumb bob
After everything is set, start fixing with form ties and diagonal support and bracing
Form after being set must be vertical Top level of potential concrete must be marked on surface of form
4.3.3 Time of Keeping Form in Its Place
Form can only be stripped when it meets the requirements about concrete strength as standard
4.4 FORMWORK REMOVAL
Before removal of form, engineer must confirm the strength of concrete whether it is enough or not
Trang 1818
During process of removing, people must be kept away the area
All of material after being taken out must be well arranged and cleaned up by the form oil to the next using
Removal of forms:
- Forms shall not be removed until the minimum standing time was
elapsed
- Minimum standing time shall be determined in terms of the age or
compression strength of concrete Data and calculation sheets used in verifying safety and concrete test results in section 5 shall be submitted
to the Engineer for approval If the onset of strength is considered to have been delayed due to cold weather, the above shall be determined
by compression strength instead
- Supports of a cantilever beam, canopy with a large span, large-size
floor slab or an extremely large working load shall be kept for longer periods as required
- Supports shall not be re-shored Sheathing boards below floor slabs and
beams shall be removed after taking out supports
4.5 HEAD TREATMENT FOR FORM TIGHTENING PARTS
When there is no finish on a visible face after forms are removed, the heads of form-tightening parts shall be removed and a rustproof paint shall be applied Mortar filling shall be generally performed below the face For a thin finish such as paint coat, the mortar bed shall be flush with concrete surface
Trang 1919
CHAPTER 5 CONCRETE WORK
5.1 GENERAL
5.1.1 Scope
This Chapter shall apply to the following concrete construction work:
- Concrete types shall be normal weight concrete and lightweight
concrete However, this shall not apply to the section of light weight concrete in direct contact with the ground
- Concrete casting plan for sub-structure, super-structure
- Concrete should be ready-mixed concrete and mixed at site concrete
- Placement of concrete shall be performed using concrete pumps,
bucket chutes etc
5.1.2 Standard Design Strength
The standard design strength (F0) of concrete, indicated by the compressive strength at the age of 28 days, shall be shown on the structural drawings in the Design Documents
5.1.3 Classification of Ready Mixed Concrete
Kinds of ready mixed concrete shall conform to specify by the structural drawings in the Design Documents
Sequence of construction of building floor slab
5.2 CONCRETE CASTING PLAN
5.2.1 Sub-structure
Casting for each pilecap (foundation) in each group of every segment VINACONEX E&C uses concrete pumping truck for casting concrete to ensure the implementation is on schedule
Assembling of widen scaffold
Construction of formwork
Construction of reinforcement
Concrete works
Trang 2020
5.2.2 Super-structure
After the completion of rebar work and formwork, VINACONEX E&C uses concrete pumping truck with the 36m rod in height Casting concrete for each concrete frame
5.3 MATERIALS FOR NORMAL WEIGHT CONCRETE
- Aggregates shall be ordinary aggregate, while coarse aggregates shall
be gravel, crushed stone, blast furnace slag aggregates or a mixture of these Fine aggregate shall be sand and may contain crushed sand
- Quality of aggregates:
- Aggregates shall be of higher strength than hardened cement paste in
concrete, and shall be suitable for use in reinforced concrete
- Grading of aggregates shall be made by mixing suitable quantities of
fine and coarse grained materials
5.3.3 Water
Water shall not contain dangerous levels of impurity which may adversely affect concrete and/or reinforcing bars
5.3.4 Admixtures
Admixtures shall be of good quality suitable for reinforcing bars
5.4 MIX PROPORTION OF ORDINARY CONCRETE
5.4.1 General Conditions for Mix Proportion
The mix proportion of concrete shall provide the required strength, workability, uniformity and endurance
Design slump shall be the required slump plus the change anticipated after hardening of concrete
Design air content shall be the air content plus required air content for change anticipated after production, and the required air content shall be 4.50/vl Unit water volume shall be less than 185 kg/m3 in design mix proportion to be used Where unavoidable this may be less than 200kg/ m3 if approved by the Engineer
Minimum cement content shall be follow the design mix proportion
Water/cement ratio shall be less than 650/wt for the design mix proportion Admixture can be used for concrete The admixture shall conform to the following according to cement content, unless otherwise shown on the structural drawings and directed by the Engineer
Trang 2121
5.4.2 Approval for Design Mix Proportion
Prior to starting construction the Contractor shall be required to verify that design mix proportions at the concrete producing plant will produce the required strength, workability, uniformity endurance and other performance factors designated in this Section, based on the design mix proportion prepared
in accordance with Item (2) or (3), and also to obtain approval from the Engineer of the design mix proportion sheets
- Design mix proportion sheets of the concrete production plant shall
show materials used for production, basic data used in mix design and calculation sheets
- Design mix by production plant shall be similar to the mix of the
similar mix adjusted to compensate for the use of different materials
- In the case of other than item (2), trial mixing shall be carried out to
verify quality
- Trial mixing shall be performed in the presence of the Engineer until
design slump, design air content, and mix strength (including strength tests at the ages of 7 day and 28) are obtained
- Where unavoidable, mix strength may be estimated from the strength at
the age of 28 days based on the strength at the age of 7 days, using suitable data after obtaining approval from the Engineer
5.5 PRODUCTION, TRANSPORT AND PLACEMENT OF CONCRETE
5.5.1 General
Prior to the work, the following items shall be submitted in writing to the Engineer for approval :
- Method of concrete placement
- Forced feed capacity of concrete pump, layout and supporting method
for conveying pipe, procedures in the event of interruption of conveyance
- Procedures for concrete in the event that major anomaly arises
following forced feeding
- Where transport is not to be performed by concrete pump, a description
of equipment, performance etc
- Distribution of workers, auxiliary facilities or tools
- Machinery and tools shall be adjusted periodically prior to starting
work as well as during work
5.5.2 Production
Instructions to the manufacturing plant are indispensable for obtaining concrete with the quality stipulated in Section above
5.5.3 Process up until conveyance by Pressure Feeder or similar Machinery
Transport of concrete shall conform to the following :
- Preparation for placing concrete shall be carried out to enable concrete
to be poured within one hour and a half after the start of mixing
Trang 22- Immediately before unloading concrete, rotate the truck agitator at high
speed to agitate the concrete and make it uniform
- Always carefully check the quality of concrete to be unloaded
5.5.4 Forced Feeding and Transport on Site
Forced feeding of concrete
Conveying pipes shall be held using walking boards on supporting bases, supporting bases, trestles, suspending hardware, etc No hazardous vibration
of conveying pipe shall be transmitted to concrete forms or reinforcing bars The size of the conveying pipe shall be determined in consideration of the following (Minimum nominal diameter of conveying pipe for the maximum size of coarse aggregates)
- Distance and height of forced feed, affect on concrete of forced feed,
difficulty of using forced feed, air temperature
- Volume of forced feed per unit time and maximum size of coarse
aggregates
The length of the flexible hose shall be less than 6m as a rule when the nominal size of the conveying pipe is less than 100mm For pipes over 100mm the hose shall be less than 5m except for pump vehicles with booms
The maximum horizontal transportable distance of the forced feed machine shall be more than the horizontal equivalent of the total piping distance plus a certain allowance
Prior to force feeding concrete, rich mortar shall be input in order to prevent change in concrete quality Prior to force feeding mortar the inner surface of the equipment should be wet
The following sections of forced feed concrete shall be discarded Good sections of forced feed mortar prior to the forced feed of concrete can be poured in concrete forms if scattered so that only a small quantity is present at any one place
- Concrete changes significantly during forced feed
- Altered portion of mortar stated in (5) first ejected
When using a sloped chute the following requirements shall be met:
- Section is U-shaped and made from steel or iron sheet
Trang 2323
- Slope is 4/10 to 7/10
- Funnel longer than 600mm used at chute outlet
When discharging concrete from high places longitudinal flexible chutes shall
be used
5.5.5 Placement
Prior to concrete placement, clean the area when concrete will be placed, remove miscellaneous objects, and spray water to moisten the sheathing boards and construction joints
If a rainfall that may affect the quality of concrete is predicted curing shall be performed When curing is not possible concrete shall not be poured
Placement shall be carried out mainly by (1) as stated below for ordinary story heights or, depending on the situation, (2) after obtaining approval from the Engineer
- Each story is divided into the portion below the beam and the portion
below the top of the floor slab Placement shall be varied so that each portion is horizontal
- When there is a portion from which a wall beam rises up the concrete
shall be placed in succession in accordance with the setting conditions
of floor slab concrete
- Concrete forms are to be strengthened to prevent deformation, and
concrete is to be placed on the floor slab one at a time, from the end to the whole
- Use (1) for wall and beam concrete placement
Parapet or eaves shall be poured as one body with the structure supporting it as
a rule
Do not pour concrete directly from the flexible hose to the column
When interruption to concrete placement is necessary, predetermine the pouring section and limit the interrupting time to one hour as a general rule Compaction of concrete shall be performed to all parts of the concrete form Normal allocation shall be at least two bar-type vibrators per concrete conveying pipeline system, and two or more vibrator-operating workers plus more than seven workers for tapping compaction
Floor slabs shall be compacted by tapping the surface with tamper after rough leveling but before concrete setting to prevent cracking due to settlement, and shall be made to level surface
5.5.6 Joints of Successive Pours
Joints of successive pours (construction joints) shall be horizontal or vertical and located near the center of the span for beams and floor slabs, or on top of the floor slab, wall beam or foundation for walls and girders
Partition plates shall be used for the joints of successive pours such that mortar, cement paste will not leak out Where the horizontal construction joint
is on the outer surface, it shall be made straight using driving rulers (baby
Trang 245.6 TESTING
5.6.1 General
This Section applies to the testing of concrete and concrete materials Some of the tests may be omitted if the concrete is light, or for smaller sections, if approved by the Engineer
Areas used for testing of materials shall comply with the following as far as possible:
- For cement and aggregates, the location of concrete production
- For normal weight concrete, location where unloading takes place on
site
- For lightweight aggregate concrete, immediately before placement at
the location where placement of concrete forms takes place on site 5.6.2 Material Tests
Material tests shall be conducted in accordance test reports shall be submitted
to the Engineer for approval In case of the following result, the Contractor shall consult with the Engineer for solution:
- Crushed sand and crushed stone designated as type B is found to be
un-harmful
- Immutable weight control is specified as the measure for restricting
kind B and alkali aggregate for crushed sand and crushed stone, and the total alkali in concrete exceeds 3.0kg/m3 without being judged un-harmful
5.6.3 General Rules for Strength Tests for Concrete
Number of test pieces and collection of test samples
The number of test pieces shall be three for each type of test: age days, age 28days, assessing time to remove forms, etc
Test samples shall be collected three times separately from dollies at suitable intervals for the purpose of preparing the test pieces required in (i)
Trang 25Compression strength test shall conform to Test method for concrete compression strength
5.7 TROWEL FINISH FOR FLOOR CONCRETE
- Determine origin of reference height for each story
- Determine reference height for finishing work before pouring concrete
- Leveling with ruler :
- Maintain accurate height reference to either level or required gradient
- After pouring concrete, level roughly with a scoop or shovel and tamp
concrete with tamper until coarse aggregates sink below the surface
Trang 2626
Level the surface with a long straight board while accurately maintaining height in alignment with reference height using level or leveling string
- Elimination of irregularities in the middle After using the straight board
level the surface flat with wooden trowel
- Trowel finish:
- Rubbing with wooden trowel: After eliminating irregularities rub the
surface with wooden trowel, gauging the timing correctly with surface hardening
- Metal trowel finish:
After rubbing with wooden trowel, finish the surface smooth with metal trowel This finish work shall be performed before concrete has hardened too much so that the trowel is still possible
Do not spray water, cement or the like on the surface during finishing
In the case of trowel finishes use walking boards or stepping boards to avoid stepping directly on concrete surface
Take extra care at construction joints to avoid contaminating the finish surface
Finish smoothly with grinder after concrete sets in places where significant irregularities caused by trowel finishing are discovered 5.7.4 Curing
After surface finishing, perform the curing specified in Paragraph above Gauge timing in accordance with degree of setting of concrete Also in the case of Type A, provide curing and surface protection by covering with vinyl sheets or the like
When installing concrete forms for upper stories or transporting reinforcing bars, take special care not to damage the finished surfaces
Trang 2727
CHAPTER 6 ERECTING COMPONENTS
6.1 GENERAL CHARACTERISTIC OF EXECUTIAT THE SITE
- Traffic
- Construction plan
- Geological condition
- Ability of supplying electricity
- Ability of supplying water
6.1.1 General characteristic of project
Description of site organization
Site manager (take responsible under director of company) allots the work for engineers and working group under his management, co-operates with related companies to work Vice director takes responsible for supervisor the site under director’s instruction, however, separate with site manager to ensure the quality and meet schedule
Obligations, rights at the site
Site manager
- Representative of the company manages working at the site,
co-operates with main contractor, the owner to solve all the work in scope
of the project
- Degree: engineer
- Obligations and rights
- Take responsible under director and legislation for controlling
technique, quality, safety of project
- Arrange and manage the staff to study all the technical, quality,
material, technological requirements so as ensuring the quality of project
- Set up working method of project and all item relates to project Follow
exactly the working method which is approved by the director
- Tinspect regularly to find out the fault, therefore avoiding the bigger
problems
- Tcooperate and give a good condition for the owner’s supervisors, and
other supervisors to complete their duty
- Take responsible for gathering quality technical documents, preparing
documents for acceptant and handing over
Trang 2828
- Be well-understood all the instruction of the engineer, then divide the
work to the team’ member, as well as manage them to finish the work follow the design in time
- Inspect and assess the quality of team’s work, repair the faults and
report to engineer
- Refuse to use low quality material
- Right of propose commence and reward, discipline the team’s member
for their work
6.2 EXECUTED ORGANIZATION
6.2.1 Project introduction and working condition
Construction plan is large; locate in planning scheme of industrial park
Road for construct/ access route:
- Project characteristic: it is a rather large scale construction Access
route is convenient for transporting and gathering the elements
- Transportation of element is rather difficult because the project locates
far from the manufacturer
- Construction plan is large So it’s convenient for hoisting and erecting
elements by crane
- Electricity: the contractor asks the owner for supplying a nearest
electric box We will operate all electric equipments in the right procedure and safe as well as in efficient way
- Use and discharge water in the right way of presently regulation
6.2.2 Quantity of erecting work and general working method
List of necessary works
- Erect precast column
- Set up scaffold supported beam
- Erect precast beam
- Set up scaffold supported slab
- Erect precast slab
- Casting topping concrete
Quantity table of erecting typical precast slab
4 Concrete topping M3
Trang 2929
6.3 ORGANIZING AND WORKING METHOD
6.3.1 Organizing method
Characteristic of erecting procedure
Erecting method includes 2 procedures: unloading and erecting precast element These procedures need to be met the quality and technical requirements This results in the strength of the superstructure During erecting progress, there are many type of precast element, so the crane should be located at the most advantage location to erect as much as possible, so as reducing time for movement, setting up the crane It’s good to combine supplying, transporting and unloading suitably in order to reducing working time
Table of the greatest size and weight precast element
Item Type of
element
Length (m)
Width (m)
Height (m)
Choose working machinery
Choose working machinery for ground floor
- Base on total schedule of project
- Base on actual plan
- Base on the weight of precast element
- The contractor decides to chose the 50 ton crawl crane to unload and
erect the precast elements for meet schedule
- Erecting column, beam, and slab synchronously to minimize the
movement of crane in order to maximize working result
- It’s necessary to define suitable parameter for choosing the best crane
- Base on the farthest, highest position; weightiest element and the worst
position of crane to choose the best crane Labor force:
The contractor implements the work in cycled series All the workers need to pass the health checking for working in high positions Moreover, they need to
be fully equipped of safety facilities and trained for safe regulation:
- All the workers must be healthy, knowledge, skillful, experienced and
careful to work
Trang 3030
- All the workers must be trained for erecting procedure, working
method in each stage The engineers always supervise to ensure the worker working correctly
- All the workers must wear safe-bell when working in high position
- Labor force at the site
List of machineries and equipments
Trang 3131
equipments
Heavy-duty end cutting pliers
- Putting the high strength bolt through the holes on column
- Using anchor shackle to stick into hoist cable
- Using the wire to orientate columns in the specified direction design
- Lower slowly the column so that the starter bar fits the hole on bottom
of the column
- Anchoring the column by hard or soft turnbuckle
- Aligning the column
- Removing the hook, moving the crane to continue
- Alignment after erecting column:
- Using cable anchor to keep the column stable then proceed down crane
- Rectifying center axis of column coinciding with the structure’s one
- Ensuring level of column’s peak
- Turnbuckle adjustment to ensure the vertical of the column
- Using stucco sealing the columns to ensure no leak
Trang 3232
Before pouring grout into the vacuum column, these follow steps must be done:
- Cleaning the column foot
- Clearing blockages (if any) in the the holes need filling mortar
- Asking supervisors to inspect after erecting columns
- Conduct pouring grout
- When pouring mortar, only one hole is allowed to pour, then let the
grout free to fill other holes to avoid the air remaining in the hole that result in creating the pore
Before pouring non-shrink grout, surface of waiting hole and foot of column must be moisture Then pouring high strength non-shrink grout until the hole is full-filled Ensuring the grout tight grip on the foot of the column, closing up the space between columns’ foot and the surface slab, and no flowing out When pouring grout to note the following:
- To check the axis’s center, vertical before filling grout
- Ensuring to pour grout quickly so that reducing the quality of the
mortar’s cure
- When pouring grout to ensure it continued until full filled, avoid
pouring as many times that makes it dividing into many layers leading
to low quality
- After finishing work In dry season condition, it must be maintained
regularly 1 to 2 times per day within 3 days
- Because non-shrink grout is high strength, quick frozen So to
avoid spilling out, it should make a edge by mortar grade 75 or by wood If there is reason to pour into 2 times, amount of time between 2 times doesn’t exceed two hours apart First time, pouring full-filled the column’s foot up to approximately edge position, waiting the grout rather hard in surface then pouring second times to complete After 1-
2 days, using concrete to seal hole
Maintenance column joints:
- Column joints are wet using quick frozen, non-shrink high strength
grout After pouring, we pay special attention to the maintenance of joints as with conventional concrete:
- Avoid strong shock in the curing time
- Make sure the standard moisture of curing
- When the intensity reached > = 50% strength designed, dismantle the
entire anchored device
- After pouring grout a period of 24 hours, other stages are allowed
to proceed
- Tolerance after completion of temporary fixed:
- Deviation in foot column: 10mm
Trang 3333
- Deviation of vertical column’ peak: 6mm
- Bias of the overlapping beams level: 10mm
6.4.2 Erecting beam
When the column was erected hardly enough then proceed to install beams in the following order:
Prepare scaffolding to erect beams on top of the column
- Checking the size of the beam, marking the location of beam’s center
on the corbel, top column (or the binding beam – column location)
- Checking if the beam height above floor, it should be rectified Using
dedicated cable to anchor with the hook built on the beam
- When hoisting the girders, combining with using wire to locate the
beam in correct position
- Paying particular attention to avoiding collisions assembled beams to
columns and beams which are already installed
- Slowly lower beams to ensure starter bar placed into the column
- Calibrating beam’s center to coincide with the axis’s center, chocking
the corbel so as the column is vertical and the right height
- Cleaning dirt, watering contact surface at the top of the column
- Erecting formwork around the columns
- Pouring concrete when the around beams are installed
- Check the requirements to achieve the assembly tolerance index for the
- following:
Axis deviation beam: 10mm
Level of the beam is not vertical: 10mm
Bearing length deviation (direction of beam length): 15mm
Bearing width deviation (horizontal beam direction): 10mm
Bias on beam’s level as bearing on the floor: +5,-15mm 6.4.3 Erecting slab
The order of installation is similar to installation of beam:
When the girders were erected in place and ensured the correct procedures, technical regulations, then erecting the slab in the following order:
Checking the geometric dimensions of the slab
- Checking type of slab
- Using a special cable to hook into the hook on the floor
- Hoisting slab panel, combining with using wire to locate the slab in
correct position
- Aligning the top of slab panel follow the design
Trang 34Handling reinforcement: this work was conducted by mechanical methods The steels are clean free of mud, oil, grease or rust before handling The contractor handles each type of reinforcement and numbering each type
to avoid confusion Reinforcement is handled in right shape and dimensions as designed Technical staffs of the contractor regularly inspect the processing of reinforcement
Erecting rebar: Rebar was erected in order and follow the design for each type of reinforcement When erecting rebar, the contractor must the following conditions:
- The installation of rebar must be correct in type and number of design
- The first part erection does not interfere with the erection of the
following sections
- To take measures to stabilize the position of rebar to not move during
the concrete pour
- Thickness of the concrete cover block is equal to the thickness of cover
concrete
- The corners of the reinforcement stirrup with the bearing steel columns
are firmly tied
- The rebar was lapped following design After completing
the installation of reinforcement and acceptance, erecting form work b) Formwork:
For erecting formwork, due to the construction includes only one floor, so the formwork is just erected when casting topping concrete of the slab The contractor chose to use timber formworks and steel braces when constructing When erecting formwork, these following requirements must be ensured:
- Formwork and bracing system are hard, stable enough, and easy to take
apart They also don’t cause difficulties for the poured concrete and concrete compaction
- Formwork assembled sealed, tight not to lose cement water when
pouring and compaction concrete, while protecting the newly poured concrete under the influence of weather
- Formwork assembles to ensure proper shape and size of the structure
- The struts which support the formwork are layout in reasonable of the
density to ensure stability of formwork during concrete pouring and compaction
Trang 3535
- After erecting, formwork is inspected at the site with participation of
the owner’s supervisor and contractor Content of inspection and acceptance include:
- The shape and size compared with the shape and size of designed
structure to cast concrete
- Location of structure to pour concrete
- The plane between the pair of formwork
- The tight fit of the formwork
- The details are in place
- Cleaning the inside formwork
- Structural supporting member, stiffness and stability of
the formwork system
After all relevant parties make a confirming minutes for acceptance, then carrying out casting concrete
Dismounting formwork when the concrete is strong enough to withstand the weight of the structure itself and the impact load of later constructed phase Dismounting formwork must be done carefully to avoid impacting the concrete’s strength
c) Casting concrete:
- The contractor use ready mixed concrete in construction Before using,
we submit investor the certificate of product quality, capacity mixers to approval
- Asking the owner’s supervisor to acceptance before casting concrete (if
pass the acceptance)
- The samples of concrete are taken at the site and
humidity maintained according to the TCVN 3105 - 1993 at the mixing plant The samples are taken by set, each set consists of 3 samples at the same time according to TCVN 3105-1993, size of sample block size 15x15x15 cm
- The concrete is casted by pouring concrete pump cars In the process of
pouring concrete, contractor must ensure the following requirements:
- Not to distort the position of reinforcement, formwork doesn’t be
deformed or movement, as well as ensure the thickness of cover concrete
- Concrete is poured into layers until complete a proper structure of stop
at construction joint
- Regularly inspect formwork systems, detect and timely treatment when
formwork is going to be bulge
- The contractor use vibrator, surface vibrator to compact concrete
following below requirements:
Time of concrete compaction at each position is enough to ensure concrete is compacted carefully When observing grout float to the
Trang 36Concrete is inspected and accepted at the site following the current standards 6.4.4 Erecting Eaves
When the column has been erected hard enough and roof truss is already installed, then proceeding to erect eaves following these orders:
Preparing the scaffold to erect eaves into the column
- Checking the size of eaves, marking the location of eaves’ center on top
of the column
- Checking the bottom level of eaves and repairing if necessary Using
dedicated cable hook on a hook was built on eaves
- When hoisting the eaves, combining with using wire to locate the eaves
in correct position
- Paying particular attention to avoiding collisions assembled eaves to
columns and beams which are already installed
- Slowly lower eaves to ensure starter bar placed into the column
- Calibrating eaves’ center to coincide with the axis’s center, chocking
the top of column so as the beam is vertical and the right height
- Welding the angle bar to fix temporally the eaves before joining two
ends of eaves
- Cleaning dirt, watering contact surface at the top of the column
- Erecting formwork around casting place
- Pouring concrete to join two ends of eaves
Procedure of arranging precast elements
When components are transported to construct at the sites:
- Checking the dimensions, hole’s center, steel’s center, and
specifications of starter bar
- Checking surface of the product for non-porous, no cracks
- Preparing the plan: flat background, the ground must be compacted
well at position of placing components
- Laying according to regulations to ensure safe and non-affect the
structure The slab shouldn’t be laid 7 pieces in one stack, beams must
be laid according to the working direction of the beam, if beams are high >=500 mm, it should have special pallet
Trang 3737
6.5 GENERAL REGULATION
The training and guidelines on labor safety is the responsibility of unit which manages the worker:
- When designing and constructing buildings must comply with
the current regulations and standards related to labor safety, environmental sanitation and fire prevention
- Don’t construct until having enough document of organizational
design and construction design In that document must be measures to ensure labor safety, environmental sanitation, and fire prevention
- Board of management: director, site manager, team leaders, heads
of departments, labor safety staff must follow full and proper liability regime for the labor safety under current regulations
- Responsibility for the implementation of safety requirements when
using machinery (equipment, construction equipment), including the means of team protection and personal protection for those who
- On a construction at the site, if there are some co-constructions units,
the main contractor B must coordinate with other construction units
to work out measures to ensure labor safety In area where there are many construction units must set up the joint committee to monitor safety at the site
- When construction at the site of a facility is operating, the director
of the construction units and manager of facility must be together to set out measures of ensuring safety The parties must make full and timely general safety measures within their own responsibility
- Workers at the construction at the site must have all the following
criteria:
Age prescribed by the state for each job
Having a certificate of health as required by medical organization Annual health checks must be at least once In case of working
on high, heat, dust, harmful position, workers must take a private health check following the health regulations It doesn’t allow arranging in pregnant women, with children under 9 months, people with heart disease, hearing, and eyesight problems children under 18 years of age to do the above works
Having the certificate of training and satisfactory inspection of work safety in accordance with each job by the validation of the director
A fully equipped vehicle for personal protection in accordance with the working conditions under the regulations
Trang 3838
CHAPTER 7 STRUCTURAL STEEL WORK
7.1 GENERAL
7.1.1 Scope of Work
The Contractor shall submit the following items to the Engineer for approval
of the steel fabrication factory which the Contractor intends to employ for assembly of the structural steel
- Capacity and scale
- Past record
- Organization
- Mechanical facilities
7.1.2 Quality Control Standards
Quality control and inspection standards for construction in the steel factory and on-site shall be approved by Engineer in advance
Products to be used shall be tested and passed by in-house inspections in the steel fabricating factory, and inspection records submitted to the Engineer However for minor work, the submission of inspection reports may be omitted
if approved by the Engineer
7.1.3 Construction Management Engineer
The construction management engineer shall be a steel fabrication management engineer
The steel fabrication management engineer shall have knowledge and skills in the field of steel fabrication management
The steel fabrication management engineer shall be involved in steel fabrication relevant to the construction work, and shall strive to improve quality
7.2 MATERIALS REQUIREMENTS
7.2.1 Steel
Steel shall conform to the Technical Specification
7.2.2 High Strength Bolts
High strength bolts shall be "high strength bolts" or "torque shear type high strength bolts"
High strength bolts:
- Sets of bolts, nuts and plain washers shall be standard products (sets of
high strength hexagon bolts, hexagon nuts and plain washers for friction grip joints)
- Sets shall be Type 2 (F10T), and types based on torque coefficient
values shall be suitable for construction work
Trang 39Testing method shall correspond to the materials specified
For steel plates subjected to tensile force in plate thickness direction, the test (Grade classification and decision criteria for architectural steel plates using ultrasonic flaw detector) shall be conducted during production
For torque shear- type high strength bolts, the production control method and the results of quality control tests for the products shall be submitted to the Engineer for approval For minor work this may be omitted if approved by the Engineer
For principal welding materials other than standard products, data and documentation verifying quality level sufficient for welding shall be submitted
to Engineer for approval For minor and/or low-volume work this may be omitted if approved by the Engineer
7.3 GENERAL SHOP DRAWINGS
- Standard drawing for welding work
Prepare full scale drawings (including templates and rulers) and for inspection and approval by Engineer If automatic processing equipment (full-scale, marking-off, cutting and drilling) is used then this may be omitted if approved
by Engineer
Trang 4040
7.3.2 Verification of Standard measuring Tape
Standard measuring tape shall be Class 1 of Steel measuring tape The standard
Measuring tape for steel fabrication shall be compared with the standard measuring tape for the
Construction site to verify that discrepancies will not adversely affect construction work
The cutting surface of raw materials shall be normal to the axis of the member except when specified otherwise
Cutting shall be done using automatic gas cutting Where manual gas cutting
is unavoidable the material shall be carefully shaped with grinder to correct the shape and dimension
Shearing of steel plate is permitted for thickness of less than 13mm No shear edge shall be permitted at the free ends and welded joints of principal members
Any dangerous projections, recessed portions, burrs or notches on the cutting surface shall be corrected or removed
Bending shall be performed at normal temperature or by hot process The hot process shall be performed in red heat state without sudden cooling
7.3.6 Correction of Distortions
Distortion in raw materials or assembled members shall be corrected in respective processes
Installation of Components for Temporary Works
Approval shall be obtained from the Engineer before installing auxiliary members or making