Erection Process: Step1: Column installation: - Crane hoists the columns to the right position; it’s ready to be anchored by bolts.. - Crane hoists the bracers and beams to the right
Trang 1EXPLANATION THE METHOD STATEMENT
PROJECT : NGHI SON REFINERY AND PETROCHEMICAL
PROJECT: NGHI SON REFINERY AND PETROCHEMICAL COMPLEX PROJECT ITEM : CENTRAL WAREHOUSE
LOCATION: NGHI SON - THANH HOA
I Method Statement:
A Principles:
- Assembly steel structure of this project is based on the general instructions
- Make the agreement with other partners before assembly
- Assembly works follow to erection plan drawings
B Assembly Method:
1 Receiving materials:
- The materials is produced at Vinaconex EC company, then be pack and load to the truck It’s ready to be transport to site by road way
- Before the materials can get into the site, they have to be checked by tender, inspector or consultancy
- Then materials will be store at contractor’s yard (remark 6 on drawing)
MAX IS 2 ROW
I STEEL
MAX IS 2 ROW
I STEEL
6
Materials place 10cm higher than ground floor level at least and at dry areas
SOFT MATERIAL
PROS FRAME STEEL FRAME
Trang 2SOFT MATERIAL
I STEEL
I STEEL
Easy to use is the priority to place material
Safety in reload material:
Safety in reload material process: crane driver must have the specific license for reload the material During that, the reload work area have to be in restrict, fence and warning sign have to be place around the area
Storing material principle: The material have to be organized that easy to be used for erection Columns go first then following bracers, rafters , purlins
Materials will be store at Contractor’s yard in good condition
2 Assembly & Stock yard:
Vinaconex EC gives the erection plan following :
Size: 60 x 96 = 5760 (m2)
There are 02 teams for this Project:
08
03
08 04
05
06
07
LEGEND:
FIRE STATION
WORKSHOP BUILDING
01
02
CENTRAL CHEMICAL STORE
03
CATALYST STORAGE BUILDING
04
CENTRAL WAREHOUSE
05
LABORATORY BUILDING
06
CANTEEN BUILDING
07
LAY DOWN AREA
08
IN OUT
D
CONTR ACTOR'S YARD
E
SITE OFFICE
INSPECTOR AND CONSULTANT OFFICE
A
B
TENDER OFFICEC ONTAINER 40T SL:01)
C
CLEANING MACHINE AREA
D
CONTRACTOR'S YARD
E
Trang 3oTeam 1:15 workers.
oTeam 2:15 workers
All workers will be equipped in safe condition and follow the Vinaconex EC site regulation
All workers who work at high level must be test for health
The used cranes must have some certificates to work
209 Standard will be applied for inspection works
The inspection works of repairing painting, tightness of linking bolts must be done before assembly works
a) Erection Plan:
Erection Plan will follow the erection plan drawing
Installation Column, Bracer, Beam
Installation Rafter
Installation Purlin
Installation Roof Sheet and Wall Sheet
Finishing works
b) Erection:
Equipments:
- 02 Kato Cranes for installation
- Using scaffolds for installation
Erection Process:
Step1: Column installation:
- Crane hoists the columns to the right position; it’s ready to be anchored by bolts
- Connect temperately bolts to settle the columns
- Adjust the columns to the right centre point
- Tightening the anchor bolts
- Using temperately bracer to keep the columns
- After all works, using the scaffolds for workers remove the crane out of the columns
Trang 4 Step 2: Bracer and beam installation:
- Bracers and beams are parallel installing to column
- Crane hoists the bracers and beams to the right position
- Connect temperately bolts to settle the bracers and beams
- Adjust the bracers and beams to the right centre point
- Tightening the connect bolts
- Using temperately bracer to keep the bracers and beams
- After all works, using the scaffolds for workers remove the crane out of the bracers and
beams
Safety in columns, bracers and beams installation process:
During thecolumns installation, workers have to wear all of safety equipments
Standing under crane is forbidden
Step 3: Rafter Installation:
TẦM VỚI XE CẨU
HÌNH ẢNH LẮP DỰNG CỘT MINH HỌA
F
1 2 3 4 5
Trang 5- After installation for column, bracer and beam, we start to move rafter to the right position
to let it ready to be erect
- All kind for rafter parts will be connected to make the full rafter on land before the crane hoists them for installation
Erection at axis 2
Installation process:
- Using 02 cranes for rafter erection
- 02 crane will install rafters from A to E
- Hoist rafter to the connecting position
- Temperately settle rafter
- Adjust the rafter for correct position
- Tightening the bolts
- Checking the good condition at connecting point
- After rafter erection, install purlin system to settle the all frames
Safety in rafter installation:
All of the workers do the erection at high level have to wear safety equipments
Standing under crane is forbidden
Erection the remaining axis
Installation process:
After rafter axis 2 is installed, the erection the remaining axis starts
- Using 02 cranes for rafter erection each axis
- Hoist rafter to the connecting position
- Temperately settle rafter
- Adjust the rafter for correct position
- Tightening the bolts
- Checking the good condition at connecting point
- Two rafters are erected to complete, next purlins will install
Continue the process until the axis 9
Trang 6Safety in rafter installation:
All of the workers do the erection at high level have to wear safety equipments Standing under crane is forbidden
Step 4: Purlin Installation:
Installation process:
- Purlins are installed the after installation rafter axis 3
- New purlins are put on roof and connected with old purlins by screw
- Purlins is installed the first full bay
- The next bay is installed more 50 percent
Trang 7 Step 5: Roof sheet and wall sheet Installation:
Finishing Work
- After installation completed, VINACONEX EC check and take over,
tighten one more time connection of columns, roof purlins, purlin
bracing, and accessory
- Check and solve the erection defects and errors, if any; repaint some
point if needed and invite inspector to check steel structure before
move on roofing
Installation
- Roof panel will roll on the ground, then crane will lift on the roof for installing
- Making the roof panel with full length of one side roof
Trang 8- By this way, VINACONEX EC commits the best solution for water roofing.
- Cleaning up the roof and finish work for steel structure part
- Wall panels will rolled on the direct ground
Purlin
Steel column Safety belt
Safety belt
Trang 9II Method of safety, fire protection, hygiene and environment protection
- During the erection process, VINACONEX EC requires workers, engineers, inspectors and all people at site have to meet site general regulation
- Ensure the safety of staff and employees and technical supervision involved the
construction site
- The occupational safety applied TCVN 5308-91 "Technical Rules for safety in construction"
- Scope of application:
Applies to all officials and employees of the construction, VINACONEX EC when
engaged in the field
Guiding people to participate in construction of the parties involved plus with
VINACONEX EC Company to ensure safety for everyone
- Notes management measures to ensure the safety of employees:
- All workers in the technical school to learn about workplace safety
- Employees as pregnant women, children younger than 9 months of age,
people with the disease (heart attack, deaf ears, eyes less ) in the process
of construction are forbidden
- Absolute Prohibition workers not drink beer while working
- Buy insurance for employees
- To appoint officers in charge of labor safety supervision of occupational safety at the site
- Construction camp medicine cabinet at PMU of VINACONEX EC Company
Application of sanctions for management support, risk behaviors cause or has caused labor unsafe actions
construction
o Arrange site signage
system
operating cranes erect
structures above prohibited
activities on the ground in the above range
- Are required to use personal protective equipment when
traveling or working on the site such as: labor helmet,
shoes
- When working on the required high-student, seatbelts, helmets, shoes
- The electrical equipment must be carefully checked lines, sockets, joints, portable power tools must be tested at least 3 months 1 times on the phenomenon of touch, cool on the cover, on protection status of the grounding wire
Trang 10- In the case of construction during the night: the system must have the capacity headlights illuminated the entire construction area
- All of the steel structure working area has to be cover by
safety net
P
BULONG NEO
LƯỚI BAO CHE
BULONG NEO
BULONG NEO
GIÁO BAO CHE
P