Trang 1Bài tập về Quản trị dự án trong xây dựng
Being responsible for the team working the first phase of the project, specifically “co-operate with local authorities for land clearance, compensation, land preparation (Backfilling) for construction with the deadline on June 20, 2013’’, my detailed action plan is as follows:
Part I: Introduction to management of the first task under the project
The main work of the first task under the project is land clearance, compensation and land preparation This task can be divided into two main activities as “Land clearance and compensation” and “Backfilling”.
The tasks are divided into 25 categories that need construction schedules In which,
“Land clearance and compensation” consists of 19 categories (details in table 1) and
“Backfilling” consists of 6 categories (details in table 2).
Diagram on management of the first task under the project
New Urban Zone Construction Project
MAGACO Corporation
Land clearance and compensation Backfilling
Planning &
Item
1
Item 2
Item
3 ÷17
Item 18
Item 19
Item 20
Trang 2Site inspection carried out in Tu Liem District where the project will be implemented states that land is mostly farming land with relatively terrain and no ponds or lakes over the area of 200 m2 However, 60 farmer households plotted in the area and need removing
Part II: Implementation of Land Clearance and Compensation.
A- Work of Land Clearance and Compensation
Work breakdown structure for Content of work for Land Clearance and Compensation
is listed in details as follows:
Table 1
1 Legal basis for implementation (referred in Appendix 1) 15-18/01/2013 Department & PMUAdministrative
2 Release the Council for Compensation – Rehabilitation &Resettlement (CCR&R) 15/01/2013 CCR&R
3
+ Prepare, approve detailed progress of land clearance, through
Compensation Council, rehabilitation and resettle, submit to the
District People’s Committee for approval
+ Prepare, inspect cost estimate for land clearance, decide to
approve the cost estimate
16-18/01/2013
CCR&R, Planning and Finance Department of district level, Ward People’s Committee, Employer
4
Release working Team for land clearance, publicly list all legal
documents relating to land clearance, inform through
broadcasting system of the ward 19-23/01/2013
CCR&R Working team, Ward People’s Committee and bodies under Ward
5 Measure cadastral map – prepare records of Land dimension ofhouseholds. 24-29/01/2013 hired by the Employer.Measurement party
6
Organize meeting with local people to inform land recovery
decision, deliver declarations of lands, assets on land, population,
records of Land dimension Collect declarations of lands, assets
on land, population
30-31/01/2013
Working team, Ward People’s Committee and bodies under Ward
7 Inspect current situations, make inspection minutes, clarifydeclared details of assets, plants, vegetables of households. 01-05/02/2013
Working team, Ward People’s Committee and bodies under Ward
8 Publicly list all results of clarification, confirmation 06/02/2013 Working team,
Employer
9
Prepare draft of detailed solution for compensation, rehabilitation
and resettlement to households whose land is recovered through
Acceptance Team for draft of detailed solution 07-08/02/2013
Working team, Employer
Trang 3+ Publicly list and collect opinions on draft of detailed solution
for compensation, rehabilitation and resettlement at working
office of Ward People’s Committee
+ Inspect solutions with complaints (if any)
09-20/02/2013 Working team, WardPeople’s Committee,
Employer
11 Answer all complaints and queries of people (if any) 21/02/2013
Working team, Ward People’s Committee, Employer
12 Complete, accept compensation solution after they have beenpublicly listed 22/02/2013 CCR&R
13 Department of Natural Resources and Environment advices theDistrict People’s Committee in land recovery decisions to land
users
23-25/02/2013 CCR&R
14 Submit to District People’s Committee for decision on detailedand general solution for compensation, rehabilitation and
resettlement
26-27/02/2013 CCR&R
15 Make decide on solution for compensation, rehabilitation andresettlement 01/03/201328/02- People’s CommitteeTu Liem Distrit
16
Publicly list detailed solution for compensation, rehabilitation
and resettlement approved by the District People’s Committee,
deliver approval decision and solution for compensation,
rehabilitation and resettlement to each household, inform the time
to receive funds of compensation, rehabilitation and resettlement,
time to get resettlement, time to handle area
01-05/03/2013 Working team, Ward
People’s Committee
17
+ Build payment plan for compensation, rehabilitation and
resettlement
+ Make payment plan for compensation, rehabilitation and
resettlement
06-10/03/2013 Working team,
Employer
18 Handle area (after payment of compensation, rehabilitation andresettlement or after handling resettlement houses and lands. 11-14/03/2013
CCR&R, Working team, Ward People’s Committee, Employer, People whose land is withdrawn
19
Enforce households that do not accept compensation for land
Working team, Ward People’s Committee, Employer, Police of Ward Note:
Council for Compensation – Rehabilitation & Resettlement is reffered as CCR&R.
B- Gantt diagram for land clearance and compensation.
Details in Appendix II as bellows:
Trang 4Appendix II
PROGRESS OF CONSTRUCTION, LAND CLEARANCE AND COMPENSATION
Implementing
date
2 Release the Council for Compensation – Rehabilitation & Resettlement (CCR&R) Jan 15
3 Prepare, approve detailed progress Prepare, inspect and approve cost estimate for land clearance Jan 16 - 18
4 Organize meeting, publicize documents, reports about land clearance through broadcasting system Jan 19 - 23
5 Measure cadastral map – prepare records of Land dimension of households Jan 24 - 29
6
Organize meeting with local people to inform land
recovery decision, deliver forms and documents for
people to declare Collect all declarations Jan 30 - 31
7
Inspect current situations, make inspection minutes,
clarify declared details of assets, plants, vegetables
8 Publicly list all results of clarification, confirmation Feb 6
9
Prepare draft of detailed solution for compensation,
rehabilitation and resettlement to households whose
land is recovered through Acceptance Team for draft
10
Publicly list and collect opinions on draft of detailed
solution for compensation, rehabilitation and
resettlement at working office of Ward People’s
Committee.Inspect solutions with complaints(if any) Feb 9 - 20
Trang 511 Answer all complaints and queries of people (ifany) Feb 21
12 Complete, accept compensation solution after theyhave been publicly listed Feb 22
13
Department of Natural Resources and Environment
advices the District People’s Committee in land
recovery decisions to land users Feb 23 - 25
14
Submit to District People’s Committee for decision
on detailed and general solution for compensation,
rehabilitation and resettlement Feb 26 - 27
15 Make decide on solution for compensation,rehabilitation and resettlement
Feb 28 - Mar 1
16
Publicly list detailed solution for compensation,
rehabilitation and resettlement approved by the
District People’s Committee, deliver approval
decision and solution for compensation,
rehabilitation and resettlement to each household,
inform the time to receive funds of compensation,
rehabilitation and resettlement, time to get
resettlement, time to handle area Mar 1 - 5
17
Build payment plan for compensation, rehabilitation
and resettlement Make payment plan for
compensation, rehabilitation and resettlement Mar 6 - 10
18
Handle area (after payment of compensation,
rehabilitation and resettlement or after handling
resettlement houses and lands Mar 11 - 14
19 Enforce households that do not acceptcompensation for land clearance Mar 15, 2013
Remarks:
Lunar newyear festival (Incl Lunar carlendar date: Dec 29, Jan 1, 2, 3 Equally with solar carlendar date from Feb 9 to Feb 12, 1023)
Trang 6Part III: Backfilling
1) Diagram of work implementation:
Investment owner
Bidder representative
Site steering committee
Dept of Planning Materials- Equipment
Dept of Technical – Progress of project
Dept of industrial
safety
Work
executive
team
Geodesic team
Water &
Electric executive team
Plastering team
Site cleaning team
Trang 72) Analyse of work item:
The main work is backfilling Implementation durations is from March 16 to March 20,
2013 Work breakdown structure for Content of work for backfilling is listed in details as follows:
Table 2
days
Number
of days
Person in charge
1
(20) Prepare offices, tents 16-21/3/2013 05
Head of Planning – Materials – Equipment Department
2
(21) Collect machineries, equipment 16-21/3/2013 05
Head of Planning – Materials – Equipment Department
3
(22)
Remove organic soil, transport
Heads of Labour Safety and Project Technical – Progress Departments
4
Heads of Labour Safety and Project Technical – Progress Departments
5
(24) Fill black sand, roll and compact 2/5 – 18/6/2013 47
Heads of Labour Safety and Project Technical – Progress Departments
6
(25) Complete other works, clean 12/5 – 20/6/2013 9
Heads of Labour Safety, Project Technical – Progress and Planning – Materials – Equipment Departments
Total: 98 days 16/3 – 20/6/2013
3) GANTT diagram for Backfilling
Based on the above mentioned planning, we have got GANTT diagram (Table of project’s progress) as bellowing Appendix III:
Trang 8Appendix III
TABLE OF PROJECT’S PROGRESS
ITEM: BACKFILLING NEW URBAN ZONE PROJECT
No of date
March
1 Prepare offices, tents 16/3 – 21/3 5
2
Collect machineries,
3
Remove organic soil,
transport and dispose 20/3 – 16/4 26
5
Fill black sand, roll and
6
Complete other works,
Trang 9Part IV: Estimate cost for implementation
PROJECT COST ESTIMATE Project : New Urban Zone Item: Land clearance, compensation and backfilling
Unit: VND
No Content Formula Value before tax VAT Value after tax Marks
1 Cost for preparing investment project and
land clearance solution
2,05%*500 Billion
10,250,000,00
0
1,025,000,00
0 11,275,000,000
2 Cost for compensation of land clearance 60*2 Billion 120,000,000,00 0 12,000,000,00 0 132,000,000,000
3 Cost for implementing project G1+G2+G3 281,558,139,545 28,155,813,955 309,713,953,500 Gxd
3.1 Backfilling G1 254,155,454,545 37,500,000,000 279,571,000,000
3.2 Water drainage G2 23,418,500,000 2,341,850,000 25,760,350,000
3.3 temporary housesCost for building G3 3,984,185,000 398,418,500 4,382,603,500
4 Cost for project management 2.12%*Gxd 5,969,032,558 596,903,256 6,565,935,814 GQLDA
5 Cost for consultancy and investment of the project 12,388,558,140 1,238,855,814 13,627,413,954 GTV
5.1 Cost for design 2,04%*Gxd 5,743,786,046 574,378,605 6,318,164,651
5.2 Cost for inspectingworking drawings 0,158%*Gxd 444,861,860 44,486,186 489,348,046
5.3 Cost for inspectingestimate 0,153%*Gxd 430,783,954 43,078,395 473,862,349
5.4 Cost for supervising theproject 2,053%*Gxd 5,780,388,605 578,038,860 6,358,427,465
6.1 Cost for inspecting andapproving acount 0,38%*Gxd 1,069,920,930 106,992,093 1,176,913,023
6.2 Cost for auditing 0,64%*Gxd 1,801,972,093 180,197,209 1,982,169,320
7 Provision cost 21,508,286,512 2,150,828,651 23,659,115,163
7.1 Provision cost foradditional works (1+2+3+4+5)*5% 21,645,039,225 2,164,503,922 23,659,115,163 GDP1
Remarks:
+ Fund for project (compensation, land clearance and backfilling) is calculated as 10% of total
fund for the whole project.
Trang 10Appendix I :
Legal basis for implementation of the project.
(Details of Item 1)
1 2003 Land Law
2 Decree No 197/2004/NĐ-CP dated 03/12/2004 of the Government on
compensation, rehabilitation and resettlement in the event of land recovery by State
3 Decree No 84/2007/NĐ-Cp dated 25/5/2007 of the Government with
additional provisions on issuance of land use right certificates; on land recovery; on exercise of land use right; on order and procedures for compensation, assistance and resettlement when the State recovers land; and
on resolution of complaints about land.
4 Decisions of Hanoi People’s Committee allowing MAGACO to implement the
project of new urban zone in Tu Liem District, Hanoi City.
5 Decision No 62/2008/QĐ-UBND dated 31/12/2008 of Hanoi People’s
Committee issuing Regulations on prices of land types in Hanoi City in 2009.
6 Notice No 14/TB-STC-QLCS dated 21/01/2009 of Hanoi Department of
Finance on announcing unit price as the basis for compensation, assistance to vegetables, animals on lands of land clearance in Hanoi City.
7 Decision No 40/2008/QĐ-UBND dated 22/10/2008 of Hanoi People’s
Committee issuing prices of building new houses, temporary houses, structures
in Hanoi city.
8 Maps of Hanoi City, Tu Liem District, map of project border.
9 Approved detailed map of the project.
10 Approval documents relating to the project.