MOS, Biện pháp thi công đường ống, Cách thi công đường ống, áp dụng cho các Tòa nhà cao tầng, văn phòng cao ốc, trung tâm thương mại, nhà máy. Tài liệu dùng ngôn ngữ tiếng anh, phù hợp cho các Kỹ sư, Ban quản lý làm việc trong môi trường nước ngoài
Trang 1HCMC Metro Cp-2 Project
Doc.No.:Rev Date: _2015Rev.No : 0
Trang 2GS Neotek Vietnam
TABLEOF CONTENTS Pageno.
1 Aim 2
2 Scopeof Works 2
3 QualityControl 2
3.1 Purpose/Scope 2
3.2 Referencesand Standard 2
3.3 ProcessFlowChartfortheWorkPlanProcedure 3
4 Procedure 4
5 MaterialControl 4
6 Methodology 5
6.1 PPR PipesandFittingsInstallation 5
6.2 uPVCPipesandFittingsInstallation 16
6.3 HDPE PipesandFittingsInstallation 23
6.4 UndergroundPipesInstallation 24
7 MachineryandTools 25
7.1 Machineryandtoolsforconstruction 25
7.2 Machineryandtoolsfortesting 25
8 TestMethodandTestPlan,TestRecordForms,InspectionForms 26
8.1 TestMethod 26
8.2 InspectionandTestPlan 27
9 SafetyPlan 27
10 Appendix 28
Trang 3HCMC Metro Cp-2 Project
Doc.No.:Rev Date: _2015Rev.No : 0
Trang 4Engineer's/Consultant’sComments Approved
Materialsprocurement &delivery to site.
Rejected Inspection
Rejected
Approved
1 Hydraulic Test–Cold&HotWater Piping
2 Water Leak Test–Soil,Waste, Vent &Drainagepipe Inspection
1 Installationofequipment
2 F inalconnectiontoequipme
nt, valves andaccessories
Approved
Trang 5HCMC Metro Cp-2 Project
Doc.No.:Rev Date: _2015Rev.No : 0
5.2 SCOPE
Thisprocedureisapplicabletoreceiving,handling,storage, maintenanceandinspectionof itemsreceivedbyMain-confortheconstructionof HCM Metro CP-2 – Line 1 Project
5.3 RESPONSIBILITY
a) Main-conengineershallberesponsiblefortheimplementation ofreceivinginspectionand notifyingOwner’sProjectEngineer(1 dayin advance)
materialdeliveryITPformsforthematerialsw/c Main-conpurchasedinthe localmarket;and foroverseas,thearrivalofmaterialshallbeadvisedtoClient/Project Engineeronthe
shipmentdateandETAinHCM.Main-conEngineershallnotifytheClient/Project Engineer uponarrival inHCMoneday inadvance forreceivinginspectiontosite The
Trang 6GS Neotek Vietnam
ReceivinginspectionshallbeperformedbytheMain-conengineerandClient/ProjectEngineer formaterialandequipmentreceived
Trang 7HCMC Metro Cp-2 Project
Doc.No.:Rev Date: _2015Rev.No : 0
- JointhemimmediatelyuntilthemarkedweldingdepthiscoveredbythePP-R beadfrom thefitting
- Beforestartingthefusion,checkifthealuminum-PP-compositelayerhasbeen completelyremove
- All used devices and tools must have reached the necessary operating temperatureof 260deg.C
- Suitablemeasuringinstrumenthavetomeasureatemperatureofupto350deg
C
Trang 8GS Neotek Vietnam
Trang 9HCMC Metro Cp-2 Project
Doc.No.:Rev Date: _2015Rev.No : 0
Trang 10GS Neotek Vietnam
- Fusingtheweld-in saddlewiththepipetheoutersurface andthepipeinner wallconnectionreacheshigheststability
- Theweldingdevice/saddle weldingtoolmusthavereachedtherequired operatingtemperatureof 260deg.C
- TheWeldingsurfaceshavetobecleananddry
- Inserttheheating toolontheconcave sideoftheweld-in saddletoolintothe holedrilledin thepipe wall untilthetool iscompletelyin contactwith theouter wallofthepipe.Nexttheweld-in saddletoolisinserted intotheheating
sleeveuntilthesaddle surface isupagainst theconvexsideofthewelding tool.Theheatingtimeof theelementsis generally30 sec
- Inserttheweld-insaddlein to theheateddrilledhole.Pressedandwaitfor15 sec.Waitfor10minutestocoolbeforeexposedtofullloading
Trang 11HCMC Metro Cp-2 Project
Doc.No.:Rev Date: _2015Rev.No : 0
Page : 11 of _
TITLE : Method Statement for Plumbing & Sanitary
Piping works
Trang 12GS Neotek Vietnam
4) B utt W e l d i ng
Pipesandfittingsarefused,asexplainedbelowbybuttwelding(pipedimension 160,200,and250mm)
- Cutpipeintorequiredlength
- Plasticpipesarealignedandfixedbymeansof theclampingelements
- Pushthepipesontotheheatingplacewithadefinedadjustingpressure
- Whenheatingtimehasexpired,dividethemachineslide,removeheatingelement quicklyandjointthepipes(byputtingbothpartsof theslidetogether)
- Weldedconnectioncanbe unclampedandweldingprocessis finished
Trang 13HCMC Metro Cp-2 Project
Doc.No.:Rev Date: _2015Rev.No : 0
Trang 15HCMC Metro Cp-2 Project
Doc.No.:Rev Date: _2015Rev.No : 0
Trang 16GS Neotek Vietnam
Note:Seeshop drawing
detailsfor variouspipe outlet heightsasper san.fixtures supplierrecommendation.
Trang 17HCMC Metro Cp-2 Project
Doc.No.:Rev Date: _2015Rev.No : 0
- Markthemeasuredlengthonthepipe bypermanentmarkerpen
CutthepipeusingapowersaworaPVCcutter.Besureto cutthepipe squarely
Trang 18GS Neotek Vietnam
- Chamferthe
cornersandremoveallburrsbyreamer,fileorsandpaper,cleanawaydust,dirtandoils withacleanrugbeforeapplyingadhesive
Trang 19HCMC Metro Cp-2 Project
Doc.No.:Rev Date: _2015Rev.No : 0
Page : 19 of _
TITLE : Method Statement for Plumbing & Sanitary
Piping works
Trang 20GS Neotek Vietnam
- I
mmediatelyinsertpipeintofittingsocket,givingthepipeaonequarterturnandmakingsureitgoesallthewaytothesocketbottom
-Holdthejointtogetheruntilatightsetis attained
- Standardcontroltimesis30secondsfordiametersof50mmorless,take
60secondsfordiameterofmorethan50mm
Trang 21HCMC Metro Cp-2 Project
Doc.No.:Rev Date: _2015Rev.No : 0
Trang 23HCMC Metro Cp-2 Project
Doc.No.:Rev Date: _2015Rev.No : 0
to installation.
Trang 24- Cutpipeintorequiredlength.
- Plasticpipesarealignedandfixedbymeansof theclampingelements
- Pushthepipesontotheheatingplacewithadefinedadjustingpressure
- Whenheatingtimehasexpired,dividethemachineslide,removeheatingelement quicklyandjointthepipes(byputtingbothpartsof theslidetogether)
- Weldedconnectioncanbe unclampedandweldingprocessis finished
Trang 25HCMC Metro Cp-2 Project
Doc.No.:Rev Date: _2015Rev.No : 0
Page : 25 of _
TITLE : Method Statement for Plumbing & Sanitary
Piping works
The parts to be welded are fixed and aligned respectively
Positioning of heating element
Divide the machine slide, remove heating element
Trang 26GS Neotek Vietnam
Join the pipe, cool down under pressure
6.4 Underground pipe installation (Drainage piping):
- Before commencement of any installation work, ensure that materials to be used had been inspected
- Excavation shall be carried out, as may deemed to be necessary for the construction of the work and dewatering pump may be required which subject to site condition
- Prepare setting out of main / branch drains based on approved shop drawings
- Excavate the required trench for the main / branch drain as per setting out
- Excavation for trench shall be of straight line and provide gradient for the pipes and beds
- Shoring shall be provided for unstable earth condition, (if necessary)
- Check the excavated depth progressively until the required invert level is achieved
- Treat the excavated layout trench with sand layer is compacted
- Proceed to pipe laying as per proposed invert level Level instrument is use to check the invert level
- The socket end of pipe is to be placed facing the upward stream of the gradient and shall be secured with rebar and engineering brick
- Ensure both ends of pipe are provided with 200mm clearance, for the end pipe entering to the Sump/
MH rebar internal wall and before the form work close-up to Sump / MH
- Upon curing of the concrete haunch pipe, remove all formworks and any unwanted materials out of the trench including any strutting supports Trench is then backfilled with selected excavated sand The sandlayer is compacted up to 200 mm and the soil layer is backfilled & compacted progressively until to the finish level
Trang 27HCMC Metro Cp-2 Project
Doc.No.:Rev Date: _2015Rev.No : 0
Trang 28halftimesthemaximumpressurewhicheveris greater.
(Seespecs.Section07.4)
Thepressuredropshall notdropmorethan5%
Soil,Waste,Ventand
Drainagepipe Waterfillingtest(bywater)(Fillwithwatertotopofhighest
partof installarea,24 hours)
Toleranceof 1~2mm c
hangeofwaterlevel
L eaka g e t est ( b y w a t e r )
- Two(2)typesof waterpumpsshallbe usedfortesting,
- Portablemotorizedpumpandmanualhandpump
- Two(2) waterpressuregaugesshallbeinstalledatthetest pointof thepipefor
monitoringthetestpressurein thepipe.Rangeof pressuregaugeshallbefollowas,
a) 0bar ~25bar: WaterSupplySystem
b) 0bar ~15bar: HotWaterSupplysystem,PlumbingandSanitaryFixtures,Water
Thetestdurationisatleast( 24)hou rs , thepressuredropshallnotdropmorethan 5%
• Afterapproval oftheleakagetest,release thetestpipepressureto0baranddrain
outthewaterinthepipe
Trang 29HCMC Metro Cp-2 Project
Doc.No.:Rev Date: _2015Rev.No : 0
- Oncethestackisfilledwithwatertofull and kept for 15 min.,aninspectorshall
makeavisualinspection of thesectionbeingtestedto checkforleaks
- Recordtheintervalbetweenpipe edge andwatersurfaceandwaterlevelshallbe marked onpipesurface.24hoursorlongerlater,checkintervalchangebyvisualcheck The
changewaterlevelshallnotbe approved
- Oncethesystemhasbeensuccessfullytested,itshouldbedrainedandthenextsection shouldbe preparedfortest
Main-conshallcarryoutitsworksinthesafestmannerpossible Jobhazardanalyses shall
beprepared andapproved priortosetting outwithspecifictaskstoperform The healthofthe
workersshallbe aparamountconcernof theCompany
Safetyshallbestrictlyobserved.Allsafetyequipmentsuchasclothes,shoes,helmet,
gloves,safetybeltwillbeprovidedandregularlycheckduringconstruction
Main-conEngineershallinspectallSub-contractor’stoolspriorto be useon site
Trang 30GS Neotek Vietnam
Equipmentintendedforuseshallhavebeeninspectedandtagged“SafeforUse”
SafetyonInstallationofPipeonHighElevation
Installedhangersandsupportsshouldbeinspectedfirstandbe approvedbeforeinstallation of pipe
Priortoinstallationofpipeonhighelevation, anappropriate liftinggearshouldbeusefor liftingpipe Acompetentexaminershoulddeterminetheappropriateliftinggearforsuch weightof
pipebeforeliftingof pipeshouldproceed
10 Appendix