Tiêu đề Method Statement MVAC 11 April 2015 for Duct & Pipe Insulation
Trường học Posco, South Korea
Chuyên ngành MVAC Services
Thể loại Bản Phác Thảo Dự Án
Năm xuất bản 2015
Thành phố Seoul
Định dạng
Số trang 41
Dung lượng 4,77 MB
File đính kèm MOS-Duct Pipe Insulation.rar (5 MB)

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Cấu trúc

  • 1. INTRODUCTION (3)
    • 1.1 Purpose (3)
    • 1.2 Scope (3)
    • 1.3 Exclusions (3)
  • 2. GENERAL (3)
    • 2.1 Program (0)
    • 2.2 Location - Address (3)
    • 2.3 Approvals (3)
    • 2.4 Labor resources (0)
    • 2.5 Communications (4)
    • 2.6 Site Resources Required (4)
    • 2.7 Temporary material (4)
    • 2.8 Protection (4)
    • 2.9 Equipment/Tools (5)
    • 2.10 Hot works (5)
    • 2.11 Confined space works (0)
    • 2.12 Emergency & Safety Equipment (6)
    • 2.13 Materials required for installation (7)
    • 2.14 Schedule of drawings (7)
    • 2.15 Schedule of inspection (7)
    • 2.16 Attendees (7)
    • 2.17 Safety Briefing (8)
    • 2.18 Mitigation of Risk (9)
  • 3. Actual Works Method Statement (9)
    • 3.1 Delivery and Store (9)
    • 3.2 Installation (PIPE) (0)
    • 3.3 Jointing of piping (0)
    • 3.4 Welding (0)
    • 3.5 Setting to work (37)
    • 3.6 Testing (37)
    • 3.7 T&C Register (37)
    • 3.8 Reports (37)
  • 4. Appendix (0)
    • 4.1 Certificate of calibration (40)
    • 4.2 Instrument catalogue and manual book (40)
    • 4.3 Certificate of welding (41)

Nội dung

MOS, Biện pháp bọc cách nhiệt hệ ống gió và hệ ống nước, MOS for Duct and Pipe Insulation, Cách bọc cách nhiệt hệ ống gió và ống nước trong các Tòa nhà cao tầng, nhà máy, cao ốc văn phòng, cách thi công cách nhiệt ống gió, cách thi công cách nhiệt ống nước

Trang 1

-METHOD STATEMENT FOR MVAC DUCT & PIPE INSULATION

Submission Ref :PSC-HK-MS-M-0006 Rev-00

NAME: Hong Soon

Date: 08-April-15

Revision: Rev-00

Trang 2

Table of Contents

1 INTRODUCTION .3

1.1 Purpose .3

1.2 Scope .3

1.3 Exclusions .3

2 GENERAL 3

2.1 Program 3

2.2 Location - Address 3

2.3 Approvals 3

2.4 Labor resources 4

2.5 Communications .4

2.6 Site Resources Required 4

2.7 Temporary material 4

2.8 Protection 4

2.9 Equipment/Tools 5

2.10 Hot works 6

2.11 Confined space works 6

2.12 Emergency & Safety Equipment 6

2.13 Materials required for installation 8

2.14 Schedule of drawings 9

2.15 Schedule of inspection 9

2.16 Attendees 9

2.17 Safety Briefing 9

2.18 Mitigation of Risk 10

3 Actual Works Method Statement 11

3.1 Delivery and Store 11

3.2 Installation (PIPE) 11

3.3 Jointing of piping .20

3.4 Welding .21

3.5 Setting to work 24

3.6 Testing 24

3.7 T&C Register 24

3.8 Reports 25

4 Appendix 27

4.1 Certificate of calibration .27

4.2 Instrument catalogue and manual book 27

4.3 Certificate of welding ……… 29

Trang 3

2.1.1 Ensure that the shop drawing used for the references at site is approved for construction.

2.1.2 Ensure that designated manpower to conduct works at site must be properly trained and well oriented by thesafety engineer

2.1.3 All equipments, tools and mobile scaffolding to be used must be inspected and approved by authorized safetyengineer at site

2.1.4 All staffs associated with the works shall be sufficiently experienced

2.1.5 When the workers climb up the working platform, ladder, his hands must be free

2.1.6 All materials to be used at site must be properly secured and clean

2.1.7 Working period to base on civil work and piping installation schedule which will be attached after gettingapproval (Waiting for approval)

2.2 LOCATION – ADDRESS

Application for Basement 3 and all high floors

2.3 APPROVALS

Materials of submission (Waiting for submission & approval)

Shop drawing (Waiting for submission & approval)

Trang 4

2.4 LABOUR RESOURCES

The pipe team will coordinate and carry out as below organization chart

2.5 Communications

Office mobile phone or walkie-talkie will be used during working time

2.6 SITE RESOURCES REQUIRED

Temporary fire protection equipment

Site electric panel should be needed as site condition

2.7 TEMPORARY MATERIALS

Materials cover needs to be prepared on the floor and cover pipe when needed

2.8 PROTECTION

Materials cover needs to be prepared on the floor and cover pipe when needed

Trang 5

-2.9 EQUIPMENT/TOOLS

Ensure the availability of equipment and tools provision for Duct and AC Piping insulation works as follows:

1 Tape measure

11 Mitre box for

Trang 7

2.13 MATERIALS REQUIRED FOR INSULATION

-Insulation materials as -Insulation sheet, -Insulation tube, -Insulation glue, -Insulation tape

Refer to shop drawing layout of floors as below:

2.15 SCHEDULE OF INSPECTION/T&C FORM

Refer to ITP form as the attached file in below

2.16 ATTENDEES

2.16.1 Sub-contractor manager

2.16.2 Sub-contractor site manager

2.16.3 Main contractor MEP coordinator

Trang 8

2.16.5 HKL M&E manager.

2.17 SAFETY BRIEFING

2.17.1 Safety shall be in first priority during construction, safety staff shall be present on site all the time tosupervise and to remind workers to observe safety requirement Stop work order shall enforce once its dose not meetthe safety requirements

2.17.2 Safety shall conform strictly observed All workers and staff on site shall be oriented of safety requirements.All safety equipment such as cloths , shoes, helmet , gloves , safety belt should provide and regularly checked duringconstruction

2.17.3 The engineer shall inspect all subcontractor tools prior to be used on site

2.17.4 Safety Supervisor shall be present for all the safety site inspection

2.17.5 For the safety of worker, grounding wire for the electric ARC process must be provided and wet cloths,protective glasses, long sleeve cloth must be imposed to worker

2.17.6 Fire extinguisher shall be provided at welding area and safety provision must done to ensure usageworkability

2.17.7 Safety working with Scaffolding

2.17.7-1 All scaffolds must be erected under the supervision of a competent and experienced person- usually theconstruction superintendent This includes moving scaffolds from one position to another Each leg of a scaffoldmust be supported by and adequate footing Loose bards, bricks and other material do not provide a safe, adequatebase

2.17.7-2 Where the working platform in more than 10 feet off the ground, the scaffold shall have guardrailsinstalled

2.17.7-3 If people are working under the scaffold, toe boards must be used to prevent tools and materials fromfalling on them

2.17.7-4 Workers are not to climb the metal tubular frame of the scaffold to get the working platform Other, safermeans of access must be used – a ladder or access from the building

2.17.8 Safety working with Mobile Scaffold

2.17.9 Mobile scaffolds have restricted reach unless a guy wire secures them They are more susceptible tooverturning and require a smooth, level working surface A complete guardrail system must be used at elevationsabove 10 feet and shall be used at all working levels Scaffold should be moved when unoccupied and only bypushing from the base Wheel brakes must be set when scaffold is in use

Trang 9

2.18 MITIGATION OF RISK

-Impact damage during pouring of concrete installation to be monitored constancy white concrete is poured Correctconnections or materials, ensure the final installation and connections are inspected and signed off withphotographic records by MEP coordinator on site M&E staff from contractor, architect and client

3 ACTUAL WORKS METHOD STATEMENT

3.1 Delivery and store

Insulation sheet & Insulation tube materials arrived to site shall be inspected and stored according to manufacturerrecommendations Materials shall be stored in the covered and dry space During the receiving materials ofInsulation, manpower shall be used to make Insulation The Insulation and accessories shall be protected andcovered with polythene sheets before insulating Materials of Insulation is as table below

Trang 10

3.2 DUCT & PIPE WORK INSULATION METHODOLOGY

3.2.1 Cutting insulation tube

How to cut Insulation tube

Trang 11

3.2.2 Pipe insulation with self-adhesive insulation tube

Trang 12

3.2.3 Angles in crewed pipe joints-option 1

Trang 13

3.2.4 Angles in crewed pipe joints-option 2

Trang 14

3.2.5 Insulating large pipes with insulation sheet

Trang 15

3.2.6 Flanges using insulation sheet

Trang 16

MVAC Services Page 16

Trang 17

3.2.7 Bend angle using insulation tube

-3.2.7.1 Bend with 90 ° angle using insulation tube

3.2.7.2 Bend with 45 ° angle using insulation tube

Trang 18

3.2.7.3 Segment bend with 1 middle part using insulation tube – 2+1

3.2.7.4 Segment bend with 3 middle parts using insulation tube – 2+3

Trang 19

3.2.8 T-piece using insulation tube

-3.2.9 Angle T-piece using insulation tube

Trang 20

3.2.10 Cross piece joint using insulation tube

3.2.11 Pipe reducer using insulation tube

Trang 21

3.2.12 Two part bend using insulation sleet – option 1 – Site application

Trang 22

MVAC Services Page 22

Trang 24

3.2.14 Valve converings using insulation sheet

3.2.14.1 Valve body

Trang 26

MVAC Services Page 26

Trang 27

-3.2.14.2 Neck - T/Pipe – T

Trang 28

MVAC Services Page 28

Trang 30

MVAC Services Page 30

Trang 31

3.2.14.3 Strainers, strainer valves and inclined seat valves using insulation sheet

Trang 32

MVAC Services Page 32

Trang 34

MVAC Services Page 34

Trang 36

3.2.15 Concentric reducer (equal) using insulation sheet

3.2.16 Essentric reducer (flat back) using insulation sheet

Trang 37

3.2.17 Actual site insulation work

Trang 38

MVAC Services Page 38

Trang 40

4.1 Certificate of calibration

Waiting for pressure gauge calibration The meantime, we may use brand new pressure gauge Calibration certificatewill be submiited later

4.2 Instrument catalogue and manual

Trang 41

-Welding machine

4.3 Certificate of welders

Below mentioned welders have qualification test certificate and they can weld with pipesize from DN65

to DN750 All welders will perform their experience by welding sample short pipe which will besubmiited to main contractor and HKL engineer for inspection and approval before the start the actualwelding works at site