Trang 1-METHOD STATEMENT FOR MVAC DUCT & PIPE INSULATION
Submission Ref :PSC-HK-MS-M-0006 Rev-00
NAME: Hong Soon
Date: 08-April-15
Revision: Rev-00
Trang 2Table of Contents
1 INTRODUCTION .3
1.1 Purpose .3
1.2 Scope .3
1.3 Exclusions .3
2 GENERAL 3
2.1 Program 3
2.2 Location - Address 3
2.3 Approvals 3
2.4 Labor resources 4
2.5 Communications .4
2.6 Site Resources Required 4
2.7 Temporary material 4
2.8 Protection 4
2.9 Equipment/Tools 5
2.10 Hot works 6
2.11 Confined space works 6
2.12 Emergency & Safety Equipment 6
2.13 Materials required for installation 8
2.14 Schedule of drawings 9
2.15 Schedule of inspection 9
2.16 Attendees 9
2.17 Safety Briefing 9
2.18 Mitigation of Risk 10
3 Actual Works Method Statement 11
3.1 Delivery and Store 11
3.2 Installation (PIPE) 11
3.3 Jointing of piping .20
3.4 Welding .21
3.5 Setting to work 24
3.6 Testing 24
3.7 T&C Register 24
3.8 Reports 25
4 Appendix 27
4.1 Certificate of calibration .27
4.2 Instrument catalogue and manual book 27
4.3 Certificate of welding ……… 29
Trang 32.1.1 Ensure that the shop drawing used for the references at site is approved for construction.
2.1.2 Ensure that designated manpower to conduct works at site must be properly trained and well oriented by thesafety engineer
2.1.3 All equipments, tools and mobile scaffolding to be used must be inspected and approved by authorized safetyengineer at site
2.1.4 All staffs associated with the works shall be sufficiently experienced
2.1.5 When the workers climb up the working platform, ladder, his hands must be free
2.1.6 All materials to be used at site must be properly secured and clean
2.1.7 Working period to base on civil work and piping installation schedule which will be attached after gettingapproval (Waiting for approval)
2.2 LOCATION – ADDRESS
Application for Basement 3 and all high floors
2.3 APPROVALS
Materials of submission (Waiting for submission & approval)
Shop drawing (Waiting for submission & approval)
Trang 42.4 LABOUR RESOURCES
The pipe team will coordinate and carry out as below organization chart
2.5 Communications
Office mobile phone or walkie-talkie will be used during working time
2.6 SITE RESOURCES REQUIRED
Temporary fire protection equipment
Site electric panel should be needed as site condition
2.7 TEMPORARY MATERIALS
Materials cover needs to be prepared on the floor and cover pipe when needed
2.8 PROTECTION
Materials cover needs to be prepared on the floor and cover pipe when needed
Trang 5-2.9 EQUIPMENT/TOOLS
Ensure the availability of equipment and tools provision for Duct and AC Piping insulation works as follows:
1 Tape measure
11 Mitre box for
Trang 72.13 MATERIALS REQUIRED FOR INSULATION
-Insulation materials as -Insulation sheet, -Insulation tube, -Insulation glue, -Insulation tape
Refer to shop drawing layout of floors as below:
2.15 SCHEDULE OF INSPECTION/T&C FORM
Refer to ITP form as the attached file in below
2.16 ATTENDEES
2.16.1 Sub-contractor manager
2.16.2 Sub-contractor site manager
2.16.3 Main contractor MEP coordinator
Trang 82.16.5 HKL M&E manager.
2.17 SAFETY BRIEFING
2.17.1 Safety shall be in first priority during construction, safety staff shall be present on site all the time tosupervise and to remind workers to observe safety requirement Stop work order shall enforce once its dose not meetthe safety requirements
2.17.2 Safety shall conform strictly observed All workers and staff on site shall be oriented of safety requirements.All safety equipment such as cloths , shoes, helmet , gloves , safety belt should provide and regularly checked duringconstruction
2.17.3 The engineer shall inspect all subcontractor tools prior to be used on site
2.17.4 Safety Supervisor shall be present for all the safety site inspection
2.17.5 For the safety of worker, grounding wire for the electric ARC process must be provided and wet cloths,protective glasses, long sleeve cloth must be imposed to worker
2.17.6 Fire extinguisher shall be provided at welding area and safety provision must done to ensure usageworkability
2.17.7 Safety working with Scaffolding
2.17.7-1 All scaffolds must be erected under the supervision of a competent and experienced person- usually theconstruction superintendent This includes moving scaffolds from one position to another Each leg of a scaffoldmust be supported by and adequate footing Loose bards, bricks and other material do not provide a safe, adequatebase
2.17.7-2 Where the working platform in more than 10 feet off the ground, the scaffold shall have guardrailsinstalled
2.17.7-3 If people are working under the scaffold, toe boards must be used to prevent tools and materials fromfalling on them
2.17.7-4 Workers are not to climb the metal tubular frame of the scaffold to get the working platform Other, safermeans of access must be used – a ladder or access from the building
2.17.8 Safety working with Mobile Scaffold
2.17.9 Mobile scaffolds have restricted reach unless a guy wire secures them They are more susceptible tooverturning and require a smooth, level working surface A complete guardrail system must be used at elevationsabove 10 feet and shall be used at all working levels Scaffold should be moved when unoccupied and only bypushing from the base Wheel brakes must be set when scaffold is in use
Trang 92.18 MITIGATION OF RISK
-Impact damage during pouring of concrete installation to be monitored constancy white concrete is poured Correctconnections or materials, ensure the final installation and connections are inspected and signed off withphotographic records by MEP coordinator on site M&E staff from contractor, architect and client
3 ACTUAL WORKS METHOD STATEMENT
3.1 Delivery and store
Insulation sheet & Insulation tube materials arrived to site shall be inspected and stored according to manufacturerrecommendations Materials shall be stored in the covered and dry space During the receiving materials ofInsulation, manpower shall be used to make Insulation The Insulation and accessories shall be protected andcovered with polythene sheets before insulating Materials of Insulation is as table below
Trang 103.2 DUCT & PIPE WORK INSULATION METHODOLOGY
3.2.1 Cutting insulation tube
How to cut Insulation tube
Trang 113.2.2 Pipe insulation with self-adhesive insulation tubeTrang 12
3.2.3 Angles in crewed pipe joints-option 1
Trang 133.2.4 Angles in crewed pipe joints-option 2Trang 14
3.2.5 Insulating large pipes with insulation sheet
Trang 153.2.6 Flanges using insulation sheetTrang 16
MVAC Services Page 16
Trang 173.2.7 Bend angle using insulation tube
-3.2.7.1 Bend with 90 ° angle using insulation tube
3.2.7.2 Bend with 45 ° angle using insulation tube
Trang 183.2.7.3 Segment bend with 1 middle part using insulation tube – 2+1
3.2.7.4 Segment bend with 3 middle parts using insulation tube – 2+3
Trang 193.2.8 T-piece using insulation tube
-3.2.9 Angle T-piece using insulation tube
Trang 203.2.10 Cross piece joint using insulation tube
3.2.11 Pipe reducer using insulation tube
Trang 213.2.12 Two part bend using insulation sleet – option 1 – Site applicationTrang 22
MVAC Services Page 22
Trang 243.2.14 Valve converings using insulation sheet
3.2.14.1 Valve body
Trang 26MVAC Services Page 26
Trang 27-3.2.14.2 Neck - T/Pipe – T
Trang 28MVAC Services Page 28
Trang 30MVAC Services Page 30
Trang 313.2.14.3 Strainers, strainer valves and inclined seat valves using insulation sheetTrang 32
MVAC Services Page 32
Trang 34MVAC Services Page 34
Trang 363.2.15 Concentric reducer (equal) using insulation sheet
3.2.16 Essentric reducer (flat back) using insulation sheet
Trang 373.2.17 Actual site insulation workTrang 38
MVAC Services Page 38
Trang 404.1 Certificate of calibration
Waiting for pressure gauge calibration The meantime, we may use brand new pressure gauge Calibration certificatewill be submiited later
4.2 Instrument catalogue and manual
Trang 41-Welding machine
4.3 Certificate of welders
Below mentioned welders have qualification test certificate and they can weld with pipesize from DN65
to DN750 All welders will perform their experience by welding sample short pipe which will besubmiited to main contractor and HKL engineer for inspection and approval before the start the actualwelding works at site