MOS, Biện pháp thi công Tháp giải nhiệt, Method of Statement of Cooling Tower Installation, Tháp lắp Tháp giải nhiệt, Cách lắp Tháp giải nhiệt trong các toàn nhà cao tầng sử dụng hệ thống Chiller có Tháp giải nhiệt nước
Trang 1-METHOD STATEMENT FOR COOLING TOWER ASSEMBLY AND
INSTALLATION
Submission Ref :PSC-HK-MS-M-0010
Trang 2-Table of Contents 1 INTRODUCTION .3
1.1 Purpose .3
1.2 Scope .3
1.3 Exclusions .3
2 GENERAL 3
2.1 Program 3
2.2 Location - Address 3
2.3 Approvals 3
2.4 Labor resources 4
2.5 Communications .4
2.6 Site Resources Required 4
2.7 Temporary material 4
2.8 Protection 4
2.9 Equipment/Tools 5
2.10 Hot works 6
2.11 Confined space works 6
2.12 Emergency & Safety Equipment 6
2.13 Materials required for installation 8
2.14 Schedule of drawings 8
2.15 Schedule of inspection 8
2.16 Attendees 8
2.17 Safety Briefing 8
2.18 Mitigation of Risk 9
3 Actual Works Method Statement 9
3.1 Delivery and Store 9
3.2 Cooling tower assembly & installation methodology 10
3.3 Setting to work 22
3.4 Testing 22
3.5 T&C Register 23
3.6 Reports 23
4 Appendix 24
4.1 Certificate of calibration .24
4.2 Instrument catalogue and manual book 25
Trang 32.1.1 Ensure that the shop drawing used for the references at site is approved for construction.
2.1.2 Ensure that designated manpower to conduct works at site must be properly trained and well oriented by thesafety engineer
2.1.3 All equipments, tools and mobile scaffolding to be used must be inspected and approved by authorized safetyengineer at site
2.1.4 All staffs associated with the works shall be sufficiently experienced
2.1.5 When the workers climb up the working platform, ladder, his hands must be free
2.1.6 All materials to be used at site must be properly secured and clean
2.1.7 Working period to base on civil work and Cooling tower installation schedule which will be attached aftergetting approval (Waiting for approval)
2.2 LOCATION – ADDRESS
Application for 21st floor
Trang 4The Cooling tower team will coordinate and carry out as below organization chart
2.5 Communications
Office mobile phone or walkie-talkie will be used during working time
2.6 SITE RESOURCES REQUIRED
Temporary fire protection equipment
Site electric panel should be needed as site condition
Trang 5-Ensure the availability of equipment and tools provision for Cooling tower assembly and installation works as
follows:
1 Tape measure
3 Silver ink marker pen 4 Level measure
11 Hydraulic toe jack 12 Caution Tape
13 Pipe tube 14 Space roller (Doubletype)
Trang 7-4) Hand gloves
2.13 MATERIALS REQUIRED FOR INSTALLATION
3 Anchor bolt 4 Frame for Coolingtower
Trang 82.14 SCHEDULE OF DRAWINGS
-Refer to shop drawing layout of floors as below
CLMK_MECH_PC_2101
2.15 SCHEDULE OF INSPECTION/T&C FORM
Refer to ITP form as the attached file in below
2.16 ATTENDEES
2.16.1 Sub-contractor manager
2.16.2 Sub-contractor site manager
2.16.3 Main contractor MEP coordinator
2.16.4 Main contractor mechanical engineer
2.16.5 HKL M&E manager
2.17 SAFETY BRIEFING
2.17.1 Safety shall be in first priority during construction, safety staff shall be present on site all the time tosupervise and to remind workers to observe safety requirement Stop work order shall enforce once its dose not meetthe safety requirements
2.17.2 Safety shall conform strictly observed All workers and staff on site shall be oriented of safety requirements.All safety equipment such as cloths , shoes, helmet , gloves , safety belt should provide and regularly checked duringconstruction
2.17.3 The engineer shall inspect all subcontractor tools prior to be used on site
2.17.4 Safety Supervisor shall be present for all the safety site inspection
2.17.5 For the safety of worker, grounding wire for the electric ARC process must be provided and wet cloths,protective glasses, long sleeve cloth must be imposed to worker
2.17.6 Fire extinguisher shall be provided at welding area and safety provision must done to ensure usageworkability
2.17.7 Safety working with Scaffolding
2.17.7-1 All scaffolds must be erected under the supervision of a competent and experienced person- usually theconstruction superintendent This includes moving scaffolds from one position to another Each leg of a scaffoldmust be supported by and adequate footing Loose bards, bricks and other material do not provide a safe, adequatebase
2.17.7-2 Where the working platform in more than 10 feet off the ground, the scaffold shall have guardrailsinstalled
2.17.7-3 If people are working under the scaffold, toe boards must be used to prevent tools and materials fromfalling on them
Trang 9-2.17.7-4 Workers are not to climb the metal tubular frame of the scaffold to get the working platform Other, safermeans of access must be used – a ladder or access from the building
2.17.8 Safety working with Mobile Scaffold
2.17.9 Mobile scaffolds have restricted reach unless a guy wire secures them They are more susceptible tooverturning and require a smooth, level working surface A complete guardrail system must be used at elevationsabove 10 feet and shall be used at all working levels Scaffold should be moved when unoccupied and only bypushing from the base Wheel brakes must be set when scaffold is in use
2.18 MITIGATION OF RISK
Impact damage during pouring of concrete installation to be monitored constancy white concrete is poured Correctconnections or materials, ensure the final installation and connections are inspected and signed off withphotographic records by MEP coordinator on site M&E staff from contractor, architect and client
3 ACTUAL WORKS METHOD STATEMENT
3.1 Delivery and store
Materials arrived to site shall be inspected and stored according to manufacturer recommendations Materials shall
be stored in the covered and dry space During the receiving materials of Cooling tower, manpower shall be used tomake Cooling tower The Cooling tower and accessories shall be protected and covered with polythene sheets beforeinstalling Materials of Cooling tower is as below
Trang 103.2 COOLING TOWER ASSEMBLY AND INSTALLATION METHODOLOGY
-a) Safety officers and traffic control officers to station around the cordoned off areas until the crane andtransporters for Cooling towers arrive
Trang 11
-b) The Hoisting Manager must be on hand to supervise the positioning of the traffic control and safetyofficers, and to ensure that adequate numbers of 2-way radios are distributed for communications c) When the transporters are carrying the Cooling towers arrive, direct the transporter to the location reserved.d) All personnel must remain in position from this time until the lifting is declared over by the HoistingManager
e) Inspect Cooling towers Photograph and record any signs of external damages
f) Site logistic plan is shown as below
Trang 14-g) Rigging team secures rope to the lifting lugs of the Cooling tower modules to the manufacturer’srecommendations Tie a guy rope to each end of the Cooling tower module Lift up the Cooling towermodule by 30 cm
h) When the Cooling tower module is fully lowered onto the 21st floor – Plant room, remove the hoistingropes and push Cooling tower modules in location
i) Cover each Cooling tower module with protective canvas sheet
j) Repeat the above sequence to the remaining Cooling tower modules
Trang 16-Step by step to lift up Cooling tower modules as follow
Beam rigging method
Trang 17- Basin - Fan rigging method
Trang 18- Casing rigging method
Trang 19- Alternate discharge hood sealing rigging method
Trang 21-Cooling tower installation works are detailed as below table:
Task contents Technical requirments Related documents
To check location,
dimension and shape of
Cooling tower concrete
base
To clean and mark location
of Cooiling tower concrete
base and vibration isolator
To prepare manpower &
tools for lifting cooling
tower modules
To prepare instrument to lift
up Cooling tower modules
To install Cooling tower
To use Tower crane to lift
up Cooling tower modules
from crane to level 21
To lift down Cooling tower
modules on location
To take out the cover and
install vibration insolator
To clean the cover
Connection works
Pipe connection works
To check tilt of concrete base
Surface of steel frame must be flatted
All ouside connection joints of Cooling tower have
to be compatible with approved shop drawing
Cooling tower modules installation works aremade by experienced workers and engineers
To specify type and location of vibration isolator
Steel plate of vibration isolator has to fix withanchor bolt on the concrete base
Steel rope to lift and transfer has to overcomeCooling tower modules weight load
Not allow to take out package of cooling towermodules
All vibration isolators in standing freely andstability
Not allow to adjust vibration isolator whenCooling tower has not installed and connected towater pipe
Using wood to protect Cooling tower modules
All inlet and outlet lines of Cooling tower have to
be connected by flexible connectors
To clean pipe before connecting to pipe andacessories
All welding joints have to be cleaned and painted
Using flexibel conduit to connect cable to Coolingtower’s motor
Not aceptable to directly connect pipe withCooling tower
Shop drawing
Specification document.Vibration isolator manual
Trang 223.3 Setting to work
-Not applicable
3.4 Testing/Insepection
Trang 233.5 T&C Register
-Not applicable
3.6 Reports
Trang 24-4 APPENDIX
4.1 Certificate
Trang 254.2 Instrument catalogue and manual