METHOD STATEMENT FOR SHOWER SCREEN WORK

Trang 1

Riviera Point Project

METHOD STATEMENT

FOR SHOWER SCREEN WORK

Dept

Prepared by

QC/QA Safety Construction Engineering

Rev Date Description

Approved (by) Ssangyong ICIC KLV Safety RPLLC

Trang 2

Rev No and Company Comments Contractor’s Reply (J.Y.Lee)

A

1 Leong, RPLLC -Taniglass subcontractor is not approved yet, they should not be mentioned in the method statement It has eliminated

3 Vuong, RPLLC -Method statement was written by Sub-Contractor, it must be full in-charge by Ssy

 Noted

 Some parts of it are reflected as their requirement that it went through a discussion with each count department in SSY

4 Vuong, RPLLC -Page 18/131: Where is show screen will be stored at the site Those are in the bath room Please see the item no 7.3

5 Vuong, RPLLC -Page 30&31/131: Provide size of gecko & screw

Please see the section detail in annex

There are two type of screws, longer one is 40mm (ø 4) to fix onto the wooden frame and shorter one is 10mm (ø 4) to fix onto the tile surface as its details

In terms of the plastic gecko in general, shall be matched for each screw length and diameter

6 Vuong, RPLLC How to control quality of mirror & glass? We will get randomly samples for testing or not?

The test was conducted for tempered glass sheet on middle of march in this year as attached certification

So we would think of that can be proved the quality of

it

7 Tan, ICIC Page 23/131: It is better if using screws to fix SS U bar on wall and floor Fixing u-bar, will be fixed by silicon with grasping slot within flexible silicon grip because there has a

waterproofing layer which have to avoid any damage

Page 27/131:

 How to prevent wall tile from breaking when installing the hinges?

 How to connect glass door to hinge?

 Cutting by grinder to make the glass sheet inserting slot

 It shall be used by the grasp device which has fastening bolt with rubber sheet in it

Trang 3

9 Tan, ICIC aluminium u-bar? be used to avoid any harm to the waterproofing layer

and tile also

Page 32/131: Based on approved shop drawing, the interval distance of silicone dot is 150mm not 350mm 150mm distance is accurate It has corrected as the drawing

11 Tan, ICIC Page 33/131: Will silicone be applied around mirror to cover the gap between mirror and aluminium V bar? The silicon for bonding agent shall not be covered on the mirror and v-bar frame because it will be possibly

occurred some mold on it

Reviewer’s suggested status code for this revision only:

ICIC Consultant Review Consultant TYLIN Structural JRP MEP Review Consultant Consultant KPK Cost Other (state) Other (state) Other (state) RPLLC

This section is to record the reviewing party’s suggested status code only: the official status code for the submitted item is recorded on the first sheet of this document

Trang 4

Project:Rivera Point Condominium Development

CONTENTS

1 Introduction

2 Definition and Abbreviation

3 General Procedure

4 Resources (Materials, Equipments&Human Resources)

5 Principle of Work Procedure

6 Working Plan

7 Method Statement

8 QA / QC Plan

9 Safety Management Plan

10 Risk and Control

11 Special Tool

12 Access and Egress

13 Emergency Preparedness

14 PPE

Trang 5

1 Introduction

This method statement relates to the installation work for Shower screen installation

The project site is located in District 7, HCMC of Vietnam

We recognize that safety, health and environment (SHE) are primary premise in all decisions, being made for successful construction and shall comply with the relavant local authorities of Ho Chi Minh City, Socialist Republic of Vietnam

We will develop the construction method with the focus to avoid any harm to the health and safety of owner’s personnel, contractor employees and the public and also to minimize adverse effect to the natural and around environment All necessary

specifications, inspection and quality control will be complied with the contract

documents, specification If there is any discrepancy in the descriptions below, it will be designated by RPLLC

Shop House

Trang 6

2 Definition & Abbreviation

The abbreviations are used for this method statement, as shown below:

① Project Definition

 Project: Riviera Point Project (Phase 1A)

 Main-Contractor: Ssangyong Engineering & Construction Co.Ltd

 Sub-Contractor: Subcontractor JSC

② Project Abbreviation

 SSY: Ssangyong engineering & Construction Co.Ltd

 RPLLC: Riviera Point Limited Liability Company

 KPL: Keppel Land Construction

 PM: Project Manager, CM: Construction Manager, SM: Site Manager

 PD: Project Director, PJC: Project company, KPLS: Keppel Land Safety team

 SCM: Senior Construction Manager,

 SEM: Senior Engineering Manager,

 SHE: Safety Health Environment,

 RFT: Raft,

 SAC: Safety Awareness Center,

 QA: Quality Assurance,

Trang 7

3 General Procedure

The main scope of work is for Shower screen installation.

Tempered Safety Glass: Produced by Super T production line, considered as the most modern line in Vietnam

Glass Hardware Screw & gasket

Trang 8

4 Resources (Materials, Equipments & Human Resources)

4.2 List of tools

No Material Name Description Q’ty Unit Notes

Trang 9

4.3 Human Resources – Deployment of Manpower (SsangYong)

4.4 Human Resources – Deployment of Manpower (Subcontractor)

Trang 11

4.5 Installing Workers

Team 06 : 4 worker per 1 team, 2 team per 1 block

4.6 The role involves (Project Manager)

 Responsibility for the overall management of the work activities including planning, scheduling, setup, safety standards and quality assurance and implementing installation scheduling, delegating, coordinating and carrying out the overall

production activities to ensure the highest level of productivity and product quality

4.7 Duties and Responsibilities (Project Manager)

 Provide leadership, direction and work delegation to all immediate subordinates

 Planning and ensuring all installation plans and deadlines are adhered

to Studying drawings and specifications and prepare necessary material for installation

 Ensuring continuous interaction and information exchange with production department and supervisors for day to day activities

 Responsible of contacts and coordination with clients, supervisors and other departments to ensure fabrication and installation schedules are met

 Responsible for all installation schedules and requirements including site preparation, safety standards and onsite work progress

 Effectively addressing customers complaints

 Responsible of preparing, submitting and presenting periodical projects progress

 Expected to attend all site meetings, consultants and clients meetings and to discuss all pertinent projects related issues at such meetings

 Participate in the Employee’s performance evaluation processes

Trang 12

 Perform other duties as required to support the activities and initiatives

of the company

5 Priciple of Work procedure

5.1 Working Flow Chart

Site Mock up test

Ssang Yong E&C

Approval

Trang 13

5.2 Coordination at the site

 Before starting the installation, it is necessary to prepare the site organization, delegating workers, and the required tools and utilities

 Communicating with M/C about site office preparation and permission for

transporting overweighed equipments

 Find out the equipments and utilities that will be provided by the M/C at the site, such as hoist, tower crane, electricity, water, and etc…

 Survey and understand the current progress of the main structure and the site regulations on safety, cleaning, fire prevention, and etc…

 Make entry identification card for all technical officers, supervisors and workers working at site

 Communicating with the M/C to find out the storage area at the site, and the storage size and condition for future inventory management at site

 Find out the transporting area at the site for product delivery, as well as the

preferred delivery time

5.3 Site Work Execution

1) Site measurements and marking

Since the actual site dimensions might differ from the approved shop drawings, Subcontractor will perform the site measurement on each item before fabricating

In case of any discrepancy, we shall coordinate with the Employer and the Main Contractor to come out with a reasonable solution After confirming with the

Trang 14

Main Contractor of the actual measurements on site, these figures will form the basis of the production dimensions

Equipment

Rolling Ruler

– 50mm in length, Leveling ruler

Preparation

All technical documents of dimensions, measurements, and coordinates on site

2) Working Cage Usage:

 Understand the safety requirements of the site scaffold, such as maximum load, allowed work, conditions, and etc…

 Confirm with the M/C with the dates that the working cage will be installed and taken down

 Negotiate with the M/C to finish all he scope of work that requires working cage before it is taken down

3) Installation of glass and sashes

a) Material: Must first confirm the type of glass that is used on the approved shop drawings The thickness, color, type, and characteristics

Measurement: for glass that are fixed into frames or other anchoring devices, the actual measurements from the site is required For sashes, the engineers

at the fabrication plant will calculate the dimensions that can be fitted into the sash

b) Technical requirement: Glass and sashes will be protected by PVC tapes and thick paper cushions at the edges/corners during transportation and storage.Confirm the backer rod, gasket system, and sealant application with the approved shop drawings before proceeding

 Make sure the direction of the glass is installed correctly (which side faces in or out)

 It might be necessary to signal marking on the glass to prevent accidentally walking onto glass

Trang 15

 Sealant injection gun

 Plastic knife with round side

 Covering Tapes (optional)c) Technical requirements

 The bite and the thickness of the sealants must be the same as stated

in the shop drawings

 Make sure the surface is dry and clean before applying, or use air

compressor to blow out water and dust

 Check if sealants are even out and the surface is smooth, if not then

use the plastic knife to smooth out the surface

 Clean with special detergent if sealants stain on other areas

 Remove all the covering tapes

Trang 16

 egotiate with other contractors if there are problems occurring on site

 Coordinate the product delivery, labor amount, installation progress, and usage of equipment and utilities

 Constantly check site conditions and master schedule, and report to the M/C if there are obstacles preventing work being done on site

6.1 Daily working schedule

 To estimate quantity and quality for each working unit

 Examine and propose implementation solution for the next day

List out the works to be done

according to the working schedule

Supervise and implement the daily work

Estimate the working progress at the end

of the day – assign works for the next day

Trang 17

6.2 Weekly working schedule

 To organize the weekly working meeting (at the end of the week) to handle these matters:

1 To estimate working progress daily and weekly

2 To set up and working progress for the next 10 days (in which 7 days for the next week)

3 To discuss and propose solutions for the remaining works/problems during the week

4 To discuss and propose requirements for next week about human resource, material, equipments and others matters concerning implementation of the project

 Participation:

 Representative of investor

 Supervisor, consultant of employer

 Representative of sub-contractor

 Main officers of sub-contractor

 Representative of design office (if any)

6.3 Monthly working schedule

 To set up monthly meeting at the end of each month (not to cancel weekly meeting) to handle such matters:

 Report of sub-contractor to Employer about all progress on site during

a month, to estimate working result within a month according to contract conditions, implementation progress, other remain problems that needed to resolve from last month’s meeting

 Report working schedule of next month

 Requirements and conclusions of Employer for implementing working schedule of next month and analyze suggestions of members of meeting

Trang 18

6.4 Cleaning before Hand Over to M/C

 When instructed, the sub-contractor will clean the work done before

hand over to the M/C

 The sub-contractor shall remove all the protection covers from the

hardware and glass, and then clean the surface

 If some stains remain on the surface, use specially designed chemicals

to gently remove the stain so that the surfaces will remain unharmed

Trang 19

7 Method Statement

7.1 Logistic Method

a, After the fabrication finish in the factory, the glass will delivery to the site by the lorry

b, When the Lorry come to the site, Workers down load all Glass

c, Product inspection by M/C before move to the Storage

d, Storage

 Delivery of materials should be carefully planned according to the installation schedule so that only the required quantities of materials are stored on site, where the possibility of damages is higher

Glazing work Storage

Trang 20

 Just-in-time (JIT) inventory management system is effective in minimizing unnecessary handling, storage and damages to the materials

 Require a stock area of approximately 30 to 40 m2

 Proper site storage is important in preventing damages to glass

A suitable storage location should be:

 sheltered from weathering and fallen objects; and

 located for ease of material handling and distribution

 Site unloading areas shall be provided for incoming material It should be close to stock point area for ease of unloading and distribution

 All glass are to be checked dimension & quantity prior to site storage against delivery order/invoice

 In addition, the various components should be arranged according to the installation sequence to facilitate ease of retrieval, i.e to minimize searching and unnecessary shifting of materials which may lead to damages

Trang 21

7.2 Lifting Method

 All vehicle movements and deliveries will be subjected to SSY

 The storage of materials on site ground level will be kept to an absolute minimum and therfore delivery scheduling will be carried out to ensure supply is on a “Just

in time” basis

Glass

1) After the opening finished,

Workers will transport frame from

the Storage to the Hoist

 If the Glass frame are small and

short, the worker will bring by

hand

 If the Glass frame are heavy or

big, we will use small car or

forklift

Trang 22

7.3 Material Distribution Plan

a Typical floor material distribution

Trang 23

b Plan for transport the glass on work floor

All the worker must wear the gloves before bringing

the Glass frame

When the Glass frame is delivery to the site, it will

gather at the storage or in the safety zone

The workers will use the Small Car to transport the

Glass frame from the storage to the Hoist

The Small Car and Glass frame will be in put in the

Hoist and will be transport to the floor

When Glass fame comes to the floor, it will be put in

the Platform safety

7.4 Installation

7.4.1 Preparatory works before glazing

 The protective tapes should only be removed when glazing works is to be

carried out

 The following verification works should be carried out prior to glazing work:

• The orientation of the glass panels should be standardised such that the positioning of these

Trang 24

7.4.2 Installation of Glass partition in Bath-room

a Marking the install location

 Determine the needed dimension to install on walls, floors

Trang 25

b Making fixation ditch (15x15)

 Use the concrete wearing to cut mortar on walls under the predefined position clear cut ditch installation

 Use mortar or silicone to seal the U bar to walls

NOTE: U-inox (U-bar) installation will be conducted before tiling

Trang 26

c Putting the U-inox(U-bar) into the ditch (15x15)

Trang 27

d Installing the fixed glasssheet

 Use gasket Glass gib to insert in U-bar

 Install the fixed glass sheet

Trang 29

e Sealing around the fixed glasssheet

 adjust the glass sheet to the right position, required tolerance

 use silicone gun to connect the glass sheet with U-bar and walls

Trang 30

f Installing the glass door

 install door hinge accessories to the door

 define the location to drill gecko on the wall

 drill to navigate gecko

Trang 32

g Installing the door handle

h Check the door operation

 Adjust the door to operate easily and correctly

i Hand over to the main-contractor

 After finishing installation, clean and handover to main -contractor and client

Trang 33

7.4.3 Installation of mirror in the bath-room

a Marking the install location

 Use both measuring tape and laser shooting machine to define the installed location

Trang 34

b Install the aluminum V-bar

 Drill gecko to bind the aluminum to walls

Trang 35

c Install the plywood pad

 Use screw machine to bind the plywood pad to walls

 Bind location as figure

Trang 36

d Installing the back board of mirror

 Use silicone to dot on the plywood at interval @350

Trang 37

e Attach the mirror onto the back board.

 Put in the mirror onto the frame

 Final fixation after 24hs to dry the silicone

Trang 38

8 QA / QC Plan

8.1 Ensuring Quality at Production

 After approved detail drawings are given by the designers, design department of Subcontractor will provide shop drawing of the project This set of drawing will be summited to Employer and architect for approval

 After Employer approves and signs the shop drawings, technical department of the factory will make purchasing order and list of material to give to production department

 Before starting to fabricate, a final on site measurement will take place, and the actual figures will be used as the basis of production

8.1.1 Quality control procedure :

 At production, after processing of each phases, there will always be quality control part for that phase After completing each part, Quality control department will check and stamp on each parts or units before transporting to sit Please see the production flow chart on the next page

Contract

Operation Manager Processing

Shop Drawing Design

List of Material

ORDER MATERIAL JOB ORDER

CUTTING LIST

Fabrication Q/A

Transport to Job Site Employer

Trang 39

8.2 Ensuring Quality at Site

8.2.1 QA / QC Policy of Subcontractor

 After transporting products to site, site manager will be responsible to supervise the installation at site to ensure in-time progress and right technical process Site manager will regulate and handle all problems at site

 Site manager will be responsible to operate his supervisor and write down name and amount of workers, tools and equipment, works, guideline of site or drawings given by consultant as well as any events or problems, in the site diary This site diary must be ready at site and could be viewed or studied by consultants or investor at any time

 If there are any serious mistakes or any arising requirements from investor as well as main contractor, site manager must report as soon as possible to operation manager for handling solutions

 In case, mistakes do not cause by SUBCONTRACTOR but influence to quality

as well as progress of work, site manager will communicate with main contractor or investor, along with related officers to come out with solutions In this case, SUBCONTRACTOR will have right to ask for compensation

 Installation equipment: SUBCONTRACTOR will be responsible to supply equipment and suitable tools to install safely and meet quality standard Investor will be responsible to supply scaffold system, tower crane, and hoist for installation

 Ensure security at site: Main contractor or investor will be responsible to arrange safety collecting store for material with lock for sub - contractors SUBCONTRACTOR will be responsible to protect its material and tools while implementing until time for hand over

 Site manager will work directly under project manager Site manager will be responsible for managing and controlling works at site, including installation, working safety, quality control, progress, and environment

 Site manager will attend regular meetings on progress, and daily matters at site

 Site manager will be responsible for coordinating with other contractors on site

Trang 40

 Site manager will be responsible for pushing and checking daily works of supervisors and will make in-time decision if in need

 Engineers and supervisors at site will work directly under site manager, to ensure the high quality installation and in-time progress

 SUBCONTRACTOR will assign enough skillful labors for the project to ensure the progress of project

 Project manager will be jointed the weekly meeting to settle all the problems concerning schedule of project and other issue on site

 Project manager take responsibility to coordinate with other contractors in the site

 Project manager take responsibility to supervise and check the working result

of all supervisors and make knowledgeable decision for the issue happening on site

 The engineers and supervisors will work under the project manager to assist on meeting the requirements of quality and progress

8.2.2 PRODUCT QUALITY STANDARDS

a) Tolerance of deviation of quality standard

 Acceptance deviation of raw material : ± 1mm

 Allowable error number of construction : ± 1.5mm

b) Quality standard of the construction allowable error

 Verticality drawing of the door frame: within ± 2mm

 LEVEL : ± 2mm

 Allowable error of the bending : within ± 2mm

 Space from Door frame and door leaf: within ± 3.0mm

 Door opening and shutting verticality error: within ± 2mm

8.2.3 SPECIFIC STANDARD

 Glass door Installation Works shall be carried out in accordance with the requirements of: