METHOD STATEMENT FOR SHOWER SCREEN WORK
Trang 1Riviera Point Project
METHOD STATEMENT
FOR SHOWER SCREEN WORK
Dept
Prepared by
QC/QA Safety Construction Engineering
Rev Date Description
Approved (by) Ssangyong ICIC KLV Safety RPLLC
Trang 2Rev No and Company Comments Contractor’s Reply (J.Y.Lee)
A
1 Leong, RPLLC -Taniglass subcontractor is not approved yet, they should not be mentioned in the method statement It has eliminated
3 Vuong, RPLLC -Method statement was written by Sub-Contractor, it must be full in-charge by Ssy
Noted
Some parts of it are reflected as their requirement that it went through a discussion with each count department in SSY
4 Vuong, RPLLC -Page 18/131: Where is show screen will be stored at the site Those are in the bath room Please see the item no 7.3
5 Vuong, RPLLC -Page 30&31/131: Provide size of gecko & screw
Please see the section detail in annex
There are two type of screws, longer one is 40mm (ø 4) to fix onto the wooden frame and shorter one is 10mm (ø 4) to fix onto the tile surface as its details
In terms of the plastic gecko in general, shall be matched for each screw length and diameter
6 Vuong, RPLLC How to control quality of mirror & glass? We will get randomly samples for testing or not?
The test was conducted for tempered glass sheet on middle of march in this year as attached certification
So we would think of that can be proved the quality of
it
7 Tan, ICIC Page 23/131: It is better if using screws to fix SS U bar on wall and floor Fixing u-bar, will be fixed by silicon with grasping slot within flexible silicon grip because there has a
waterproofing layer which have to avoid any damage
Page 27/131:
How to prevent wall tile from breaking when installing the hinges?
How to connect glass door to hinge?
Cutting by grinder to make the glass sheet inserting slot
It shall be used by the grasp device which has fastening bolt with rubber sheet in it
Trang 39 Tan, ICIC aluminium u-bar? be used to avoid any harm to the waterproofing layer
and tile also
Page 32/131: Based on approved shop drawing, the interval distance of silicone dot is 150mm not 350mm 150mm distance is accurate It has corrected as the drawing
11 Tan, ICIC Page 33/131: Will silicone be applied around mirror to cover the gap between mirror and aluminium V bar? The silicon for bonding agent shall not be covered on the mirror and v-bar frame because it will be possibly
occurred some mold on it
Reviewer’s suggested status code for this revision only:
ICIC Consultant Review Consultant TYLIN Structural JRP MEP Review Consultant Consultant KPK Cost Other (state) Other (state) Other (state) RPLLC
This section is to record the reviewing party’s suggested status code only: the official status code for the submitted item is recorded on the first sheet of this document
Trang 4Project:Rivera Point Condominium Development
CONTENTS
1 Introduction
2 Definition and Abbreviation
3 General Procedure
4 Resources (Materials, Equipments&Human Resources)
5 Principle of Work Procedure
6 Working Plan
7 Method Statement
8 QA / QC Plan
9 Safety Management Plan
10 Risk and Control
11 Special Tool
12 Access and Egress
13 Emergency Preparedness
14 PPE
Trang 51 Introduction
This method statement relates to the installation work for Shower screen installation
The project site is located in District 7, HCMC of Vietnam
We recognize that safety, health and environment (SHE) are primary premise in all decisions, being made for successful construction and shall comply with the relavant local authorities of Ho Chi Minh City, Socialist Republic of Vietnam
We will develop the construction method with the focus to avoid any harm to the health and safety of owner’s personnel, contractor employees and the public and also to minimize adverse effect to the natural and around environment All necessary
specifications, inspection and quality control will be complied with the contract
documents, specification If there is any discrepancy in the descriptions below, it will be designated by RPLLC
Shop House
Trang 62 Definition & Abbreviation
The abbreviations are used for this method statement, as shown below:
① Project Definition
Project: Riviera Point Project (Phase 1A)
Main-Contractor: Ssangyong Engineering & Construction Co.Ltd
Sub-Contractor: Subcontractor JSC
② Project Abbreviation
SSY: Ssangyong engineering & Construction Co.Ltd
RPLLC: Riviera Point Limited Liability Company
KPL: Keppel Land Construction
PM: Project Manager, CM: Construction Manager, SM: Site Manager
PD: Project Director, PJC: Project company, KPLS: Keppel Land Safety team
SCM: Senior Construction Manager,
SEM: Senior Engineering Manager,
SHE: Safety Health Environment,
RFT: Raft,
SAC: Safety Awareness Center,
QA: Quality Assurance,
Trang 73 General Procedure
The main scope of work is for Shower screen installation.
Tempered Safety Glass: Produced by Super T production line, considered as the most modern line in Vietnam
Glass Hardware Screw & gasket
Trang 84 Resources (Materials, Equipments & Human Resources)
4.2 List of tools
No Material Name Description Q’ty Unit Notes
Trang 94.3 Human Resources – Deployment of Manpower (SsangYong)
4.4 Human Resources – Deployment of Manpower (Subcontractor)
Trang 114.5 Installing Workers
Team 06 : 4 worker per 1 team, 2 team per 1 block
4.6 The role involves (Project Manager)
Responsibility for the overall management of the work activities including planning, scheduling, setup, safety standards and quality assurance and implementing installation scheduling, delegating, coordinating and carrying out the overall
production activities to ensure the highest level of productivity and product quality
4.7 Duties and Responsibilities (Project Manager)
Provide leadership, direction and work delegation to all immediate subordinates
Planning and ensuring all installation plans and deadlines are adhered
to Studying drawings and specifications and prepare necessary material for installation
Ensuring continuous interaction and information exchange with production department and supervisors for day to day activities
Responsible of contacts and coordination with clients, supervisors and other departments to ensure fabrication and installation schedules are met
Responsible for all installation schedules and requirements including site preparation, safety standards and onsite work progress
Effectively addressing customers complaints
Responsible of preparing, submitting and presenting periodical projects progress
Expected to attend all site meetings, consultants and clients meetings and to discuss all pertinent projects related issues at such meetings
Participate in the Employee’s performance evaluation processes
Trang 12 Perform other duties as required to support the activities and initiatives
of the company
5 Priciple of Work procedure
5.1 Working Flow Chart
Site Mock up test
Ssang Yong E&C
Approval
Trang 135.2 Coordination at the site
Before starting the installation, it is necessary to prepare the site organization, delegating workers, and the required tools and utilities
Communicating with M/C about site office preparation and permission for
transporting overweighed equipments
Find out the equipments and utilities that will be provided by the M/C at the site, such as hoist, tower crane, electricity, water, and etc…
Survey and understand the current progress of the main structure and the site regulations on safety, cleaning, fire prevention, and etc…
Make entry identification card for all technical officers, supervisors and workers working at site
Communicating with the M/C to find out the storage area at the site, and the storage size and condition for future inventory management at site
Find out the transporting area at the site for product delivery, as well as the
preferred delivery time
5.3 Site Work Execution
1) Site measurements and marking
Since the actual site dimensions might differ from the approved shop drawings, Subcontractor will perform the site measurement on each item before fabricating
In case of any discrepancy, we shall coordinate with the Employer and the Main Contractor to come out with a reasonable solution After confirming with the
Trang 14Main Contractor of the actual measurements on site, these figures will form the basis of the production dimensions
Equipment
Rolling Ruler
– 50mm in length, Leveling ruler
Preparation
All technical documents of dimensions, measurements, and coordinates on site
2) Working Cage Usage:
Understand the safety requirements of the site scaffold, such as maximum load, allowed work, conditions, and etc…
Confirm with the M/C with the dates that the working cage will be installed and taken down
Negotiate with the M/C to finish all he scope of work that requires working cage before it is taken down
3) Installation of glass and sashes
a) Material: Must first confirm the type of glass that is used on the approved shop drawings The thickness, color, type, and characteristics
Measurement: for glass that are fixed into frames or other anchoring devices, the actual measurements from the site is required For sashes, the engineers
at the fabrication plant will calculate the dimensions that can be fitted into the sash
b) Technical requirement: Glass and sashes will be protected by PVC tapes and thick paper cushions at the edges/corners during transportation and storage.Confirm the backer rod, gasket system, and sealant application with the approved shop drawings before proceeding
Make sure the direction of the glass is installed correctly (which side faces in or out)
It might be necessary to signal marking on the glass to prevent accidentally walking onto glass
Trang 15 Sealant injection gun
Plastic knife with round side
Covering Tapes (optional)c) Technical requirements
The bite and the thickness of the sealants must be the same as stated
in the shop drawings
Make sure the surface is dry and clean before applying, or use air
compressor to blow out water and dust
Check if sealants are even out and the surface is smooth, if not then
use the plastic knife to smooth out the surface
Clean with special detergent if sealants stain on other areas
Remove all the covering tapes
Trang 16 egotiate with other contractors if there are problems occurring on site
Coordinate the product delivery, labor amount, installation progress, and usage of equipment and utilities
Constantly check site conditions and master schedule, and report to the M/C if there are obstacles preventing work being done on site
6.1 Daily working schedule
To estimate quantity and quality for each working unit
Examine and propose implementation solution for the next day
List out the works to be done
according to the working schedule
Supervise and implement the daily work
Estimate the working progress at the end
of the day – assign works for the next day
Trang 176.2 Weekly working schedule
To organize the weekly working meeting (at the end of the week) to handle these matters:
1 To estimate working progress daily and weekly
2 To set up and working progress for the next 10 days (in which 7 days for the next week)
3 To discuss and propose solutions for the remaining works/problems during the week
4 To discuss and propose requirements for next week about human resource, material, equipments and others matters concerning implementation of the project
Participation:
Representative of investor
Supervisor, consultant of employer
Representative of sub-contractor
Main officers of sub-contractor
Representative of design office (if any)
6.3 Monthly working schedule
To set up monthly meeting at the end of each month (not to cancel weekly meeting) to handle such matters:
Report of sub-contractor to Employer about all progress on site during
a month, to estimate working result within a month according to contract conditions, implementation progress, other remain problems that needed to resolve from last month’s meeting
Report working schedule of next month
Requirements and conclusions of Employer for implementing working schedule of next month and analyze suggestions of members of meeting
Trang 186.4 Cleaning before Hand Over to M/C
When instructed, the sub-contractor will clean the work done before
hand over to the M/C
The sub-contractor shall remove all the protection covers from the
hardware and glass, and then clean the surface
If some stains remain on the surface, use specially designed chemicals
to gently remove the stain so that the surfaces will remain unharmed
Trang 197 Method Statement
7.1 Logistic Method
a, After the fabrication finish in the factory, the glass will delivery to the site by the lorry
b, When the Lorry come to the site, Workers down load all Glass
c, Product inspection by M/C before move to the Storage
d, Storage
Delivery of materials should be carefully planned according to the installation schedule so that only the required quantities of materials are stored on site, where the possibility of damages is higher
Glazing work Storage
Trang 20 Just-in-time (JIT) inventory management system is effective in minimizing unnecessary handling, storage and damages to the materials
Require a stock area of approximately 30 to 40 m2
Proper site storage is important in preventing damages to glass
A suitable storage location should be:
sheltered from weathering and fallen objects; and
located for ease of material handling and distribution
Site unloading areas shall be provided for incoming material It should be close to stock point area for ease of unloading and distribution
All glass are to be checked dimension & quantity prior to site storage against delivery order/invoice
In addition, the various components should be arranged according to the installation sequence to facilitate ease of retrieval, i.e to minimize searching and unnecessary shifting of materials which may lead to damages
Trang 217.2 Lifting Method
All vehicle movements and deliveries will be subjected to SSY
The storage of materials on site ground level will be kept to an absolute minimum and therfore delivery scheduling will be carried out to ensure supply is on a “Just
in time” basis
Glass
1) After the opening finished,
Workers will transport frame from
the Storage to the Hoist
If the Glass frame are small and
short, the worker will bring by
hand
If the Glass frame are heavy or
big, we will use small car or
forklift
Trang 227.3 Material Distribution Plan
a Typical floor material distribution
Trang 23b Plan for transport the glass on work floor
All the worker must wear the gloves before bringing
the Glass frame
When the Glass frame is delivery to the site, it will
gather at the storage or in the safety zone
The workers will use the Small Car to transport the
Glass frame from the storage to the Hoist
The Small Car and Glass frame will be in put in the
Hoist and will be transport to the floor
When Glass fame comes to the floor, it will be put in
the Platform safety
7.4 Installation
7.4.1 Preparatory works before glazing
The protective tapes should only be removed when glazing works is to be
carried out
The following verification works should be carried out prior to glazing work:
• The orientation of the glass panels should be standardised such that the positioning of these
Trang 247.4.2 Installation of Glass partition in Bath-room
a Marking the install location
Determine the needed dimension to install on walls, floors
Trang 25b Making fixation ditch (15x15)
Use the concrete wearing to cut mortar on walls under the predefined position clear cut ditch installation
Use mortar or silicone to seal the U bar to walls
NOTE: U-inox (U-bar) installation will be conducted before tiling
Trang 26c Putting the U-inox(U-bar) into the ditch (15x15)
Trang 27d Installing the fixed glasssheet
Use gasket Glass gib to insert in U-bar
Install the fixed glass sheet
Trang 29e Sealing around the fixed glasssheet
adjust the glass sheet to the right position, required tolerance
use silicone gun to connect the glass sheet with U-bar and walls
Trang 30f Installing the glass door
install door hinge accessories to the door
define the location to drill gecko on the wall
drill to navigate gecko
Trang 32g Installing the door handle
h Check the door operation
Adjust the door to operate easily and correctly
i Hand over to the main-contractor
After finishing installation, clean and handover to main -contractor and client
Trang 337.4.3 Installation of mirror in the bath-room
a Marking the install location
Use both measuring tape and laser shooting machine to define the installed location
Trang 34b Install the aluminum V-bar
Drill gecko to bind the aluminum to walls
Trang 35c Install the plywood pad
Use screw machine to bind the plywood pad to walls
Bind location as figure
Trang 36
d Installing the back board of mirror
Use silicone to dot on the plywood at interval @350
④
Trang 37e Attach the mirror onto the back board.
Put in the mirror onto the frame
Final fixation after 24hs to dry the silicone
Trang 388 QA / QC Plan
8.1 Ensuring Quality at Production
After approved detail drawings are given by the designers, design department of Subcontractor will provide shop drawing of the project This set of drawing will be summited to Employer and architect for approval
After Employer approves and signs the shop drawings, technical department of the factory will make purchasing order and list of material to give to production department
Before starting to fabricate, a final on site measurement will take place, and the actual figures will be used as the basis of production
8.1.1 Quality control procedure :
At production, after processing of each phases, there will always be quality control part for that phase After completing each part, Quality control department will check and stamp on each parts or units before transporting to sit Please see the production flow chart on the next page
Contract
Operation Manager Processing
Shop Drawing Design
List of Material
ORDER MATERIAL JOB ORDER
CUTTING LIST
Fabrication Q/A
Transport to Job Site Employer
Trang 398.2 Ensuring Quality at Site
8.2.1 QA / QC Policy of Subcontractor
After transporting products to site, site manager will be responsible to supervise the installation at site to ensure in-time progress and right technical process Site manager will regulate and handle all problems at site
Site manager will be responsible to operate his supervisor and write down name and amount of workers, tools and equipment, works, guideline of site or drawings given by consultant as well as any events or problems, in the site diary This site diary must be ready at site and could be viewed or studied by consultants or investor at any time
If there are any serious mistakes or any arising requirements from investor as well as main contractor, site manager must report as soon as possible to operation manager for handling solutions
In case, mistakes do not cause by SUBCONTRACTOR but influence to quality
as well as progress of work, site manager will communicate with main contractor or investor, along with related officers to come out with solutions In this case, SUBCONTRACTOR will have right to ask for compensation
Installation equipment: SUBCONTRACTOR will be responsible to supply equipment and suitable tools to install safely and meet quality standard Investor will be responsible to supply scaffold system, tower crane, and hoist for installation
Ensure security at site: Main contractor or investor will be responsible to arrange safety collecting store for material with lock for sub - contractors SUBCONTRACTOR will be responsible to protect its material and tools while implementing until time for hand over
Site manager will work directly under project manager Site manager will be responsible for managing and controlling works at site, including installation, working safety, quality control, progress, and environment
Site manager will attend regular meetings on progress, and daily matters at site
Site manager will be responsible for coordinating with other contractors on site
Trang 40 Site manager will be responsible for pushing and checking daily works of supervisors and will make in-time decision if in need
Engineers and supervisors at site will work directly under site manager, to ensure the high quality installation and in-time progress
SUBCONTRACTOR will assign enough skillful labors for the project to ensure the progress of project
Project manager will be jointed the weekly meeting to settle all the problems concerning schedule of project and other issue on site
Project manager take responsibility to coordinate with other contractors in the site
Project manager take responsibility to supervise and check the working result
of all supervisors and make knowledgeable decision for the issue happening on site
The engineers and supervisors will work under the project manager to assist on meeting the requirements of quality and progress
8.2.2 PRODUCT QUALITY STANDARDS
a) Tolerance of deviation of quality standard
Acceptance deviation of raw material : ± 1mm
Allowable error number of construction : ± 1.5mm
b) Quality standard of the construction allowable error
Verticality drawing of the door frame: within ± 2mm
LEVEL : ± 2mm
Allowable error of the bending : within ± 2mm
Space from Door frame and door leaf: within ± 3.0mm
Door opening and shutting verticality error: within ± 2mm
8.2.3 SPECIFIC STANDARD
Glass door Installation Works shall be carried out in accordance with the requirements of: