Personnel concerned in preparatory work shall be designated prior to the commencement of PID preparation work and clarify the required basic items for the purpose of minimizing the revisions. (2) Project Engineering Manager shall establish the engineering schedule for the issuance of each step of PID (Issuance Step I to IV) taking into account the requirementsPersonnel concerned in preparatory work shall be designated prior to the commencement of PID preparation work and clarify the required basic items for the purpose of minimizing the revisions. (2) Project Engineering Manager shall establish the engineering schedule for the issuance of each step of PID (Issuance Step I to IV) taking into account the requirements

Trang 2

The issuance schedule of each step of P&ID (Issuance Step I to IV) might be flexible (either shorter or longer), however the P&ID steps (Issuance Step I to IV) and items to be indicated in each

step of P&ID shall be adhered to

2

Trang 3

Work procedure

(3) Utilization of Estimation Engineering result is indispensable for development of P&ID

(4) The P&ID is also to be reviewed by the related disciplines

other than the discipline responsible for the basic design before issuing to the client

This review is defined as “Internal P&ID Review” Also Marked-up P&ID based “Internal P&ID Review Meeting” should be held as the occasion demands

3

Trang 4

Work procedure

(5) The responsibility for the preparation, revision and handling

of the P&ID and relevant coordination shall in principle be

transferred from the process engineer to the project engineer upon issuance of the “P&ID for Construction”

(a) Up to issuance of the “P&ID for Construction” : Process

engineer

(b) Upon issuance thereof : Project engineer

(6) Intelligent Computer oriented P&ID System “IRENE” (JGC),

“PDS” (INTERGRAPH) will be useful since they handle stream

property data

4

Trang 5

Phase for P&ID Preparation

(1) To clarify downstream work and define the items to be indicated in each step of P&ID

(Issuance Steps I to IV)

(2) To minimize recycle work caused by missing and erroneous information

(3) To minimize the number of NPIC, FS

Purpose of Phase Control

5

Trang 6

Phase for P&ID Preparation

The process of preparing the P&ID is divided into the following 7 phases from the commencement to the

completion of the P&ID work.

Phase-1 : Preparatory step for preparation of the P&ID Phase-2 : P&ID for engineering start (Issuance Step I)

Phase-3 : P&ID for client’s approval (Issuance Step II)

Phase-4 : P&ID for piping layout (Issuance Step III)

Phase-5 : P&ID for construction (Issuance Step IV)

Phase-6 : P&ID revision according to NPIC

Phase-7 : P&ID as built

Definition of Each Phase

6

Trang 7

Phase for P&ID Preparation

Premise

(1) The process engineer shall prepare:

- Drawing Standard for P&ID Preparation

- Design Criteria for the preparation of the P&ID

• Serving as standards for the preparation of the P&ID,

• Having factors to decide including the design

philosophy of the client

Phase-1 Preparatory Step for P&ID Preparation

7

Trang 8

Phase for P&ID Preparation

(5) Design Base confirmation with client

(6) Numbering system confirmation with client

(7) Instrument Selection basis confirmation with client

Phase-1 Preparatory Step for P&ID Preparation

8

Trang 9

Phase for P&ID Preparation

Purpose

Preliminary Issue for engineering start

Issue Schedule

1.5 ∼ 2.5 Month

Subsequent Downstream Work

(1) P&ID Internal Review Meeting

(2) Preparation of Plot Plan Rev 0

(3) Major (large bore size) and critical piping layout

study which may influence the Plot Plan.

Phase-2 P&ID for Engineering Start

(Issuance Step-I: P&ID Rev-0 Draft)

9

Trang 10

Phase for P&ID Preparation

Premise

(a) Completion of Phase-1 premises

(b) Equipment list (Item No & Name) fixed

(c) VE to be already executed if necessary

(d) Prompt selection of critical equipment vendor.

(e) Line class to be fixed

(f) Previous Marked up P&ID, Off-The-Shelf P&ID

available.

(g) Participation of P&ID key person

Phase-2 P&ID for Engineering Start

(Issuance Step-I: P&ID Rev-0 Draft)

10

Trang 11

Phase for P&ID Preparation

Main Items to be Indicated

(a) General

Incorporation of Phase-1 information

(b) Equipment information

- Number of equipment items

- Type of equipment (based on estimation)

- Equipment item no and service name

Phase-2 P&ID for Engineering Start

(Issuance Step-I: P&ID Rev-0 Draft)

11

Trang 12

Phase for P&ID Preparation

Main Items to be Indicated

(c) Piping information

- All process lines, start-up/shutdown line, utility connecting line, etc.

- Valve type

- Piping miscellaneous equipment and type

- Steam (or hot oil or water) trace and/or jacketing requirements

- Vent and drain from process requirements (*)

- Connections for N2 purge, steam purge, chemical injection, water injection, etc (*) (non permanent connection)

- Fluid name, line size, line class and insulation (hot, cold, personnel protection) requirements

- Free drain, no pocket and other process requirements

Phase-2 P&ID for Engineering Start

(Issuance Step-I: P&ID Rev-0 Draft)

12

Trang 13

Phase for P&ID Preparation

Main Items to be Indicated

(d) Instrumentation information

- Instrument type and location of primary element

- All automatic operated valves (CV, ESV, HV, etc.)

- Instrumentation signal and control function

- PSV/RV location and discharge destination

(e) Vendor information

- All tie-in information of critical equipment obtained during proposal stage shall be indicated as

preliminary information.

- Black box of package vendor’s scope of supply

(*) This information could be shifted to next Phase-3

Phase-2 P&ID for Engineering Start

(Issuance Step-I: P&ID Rev-0 Draft)

13

Trang 14

Phase for P&ID Preparation

Internal P&ID Review Meeting

The internal review, presided over by the project engineering manager, shall be conducted from the overall and specialty standpoints and for the purpose of enabling personnel concerned in each discipline to

deepen their understanding of the relevant processes.

(1) Internal P&ID Review

The internal P&ID review is carried out basically by all the related

discipline engineers, especially the following:

(a) Project engineers, from the Contract requirement’s view point

(b) Engineers in charge of the piping design

(c) Engineers in charge of the instrument and control design

(d) Engineers in charge of the plant operation technology

Phase-2 P&ID for Engineering Start

(Issuance Step-I: P&ID Rev-0 Draft)

14

Trang 15

Phase for P&ID Preparation

Internal P&ID Review Meeting

(2) Preparatory Work

(a) The preliminary P&ID is prepared by the assigned process engineers, in cooperation with design discipline engineers and on the basis of various process information in the “Drawing Standard for P&ID Preparation”,

“Design Criteria for P&ID Preparation” which have been prepared at

Phase-1

After the process key engineer checks this preliminary P&ID, it should be sent to the project engineering manager, who distributes this P&ID to the related engineers to review.

(b) The P&ID reviewer, the same person as the job key person or

personnel specially appointed by the department manager, checks the P&ID, addresses the problem items and sends the list of his review

comments to the project engineering manager.

Phase-2 P&ID for Engineering Start

(Issuance Step-I: P&ID Rev-0 Draft)

15

Trang 16

Phase for P&ID Preparation

Internal P&ID Review Meeting

(3) P&ID Review

(a) With the P&ID review meeting presided over by the project

engineering manager, the P&ID reviewers involved are to explain their comments in this meeting.

• Then discussion is held concerning the comment raised by the P&ID reviewers.

• The (process) key person should attend this meeting for explanation

of the basic design and for clarification of the discussion.

• The project engineering manager should determine the conclusions concerning the comments, consulting with the P&ID reviewers and the (process) key person.

Phase-2 P&ID for Engineering Start

(Issuance Step-I: P&ID Rev-0 Draft)

16

Trang 17

Phase for P&ID Preparation

Internal P&ID Review Meeting

(3) P&ID Review

(b) If the P&ID review meeting is not held because of P&IDs simplicity,

or other reason confirmed by the project engineering manager, the engineering manager should collect the comment from the P&ID

reviewers and examine these comments.

The engineering manager determines the conclusion concerning the comments, consulting with the key person for the basic design

engineering.

Phase-2 P&ID for Engineering Start

(Issuance Step-I: P&ID Rev-0 Draft)

17

Trang 18

Phase for P&ID Preparation

Internal P&ID Review Meeting

(4) Review points

The personnel concerned in related departments shall review the P&ID mainly in respect of the under-mentioned items and from overall and specialty standpoints.

(a) Project engineer:

Cost, schedule, applicable laws and regulations, effect on

environmental pollution prevention measures.

(b) Mechanical (piping) engineering department :

Assumption of the plot plan and piping layout, and review of problems involved.

Phase-2 P&ID for Engineering Start

(Issuance Step-I: P&ID Rev-0 Draft)

18

Trang 19

Phase for P&ID Preparation

Internal P&ID Review Meeting

(4) Review points

(c) Instrumentation & control engineer:

Display method, measurement and control method, types of instruments (d) Furnace & combustion system engineer:

Furnace and all items around the flare stack.

(e) Package equipment and Rotating equipment engineers

Split of work and tie-in information

(f) Plant operation engineer:

All items concerning operation

The conclusion of the discussion and selected comments should be

recorded in the form of minutes by the project engineering manager.

Phase-2 P&ID for Engineering Start

(Issuance Step-I: P&ID Rev-0 Draft)

19

Trang 20

Phase for P&ID Preparation

Internal P&ID Review Meeting

(5) Following the P&ID Review

(a) Based on the conclusion of the P&ID review, the process

engineers should revise the preliminary P&ID

(b) The process key engineer should check that the revised P&ID reflects all the discipline’s comments, and then signs as

“Checked”

(c) The P&IDs should be approved by the project engineering

manager and signed off He should issue them to the client,

through the project manager

Phase-2 P&ID for Engineering Start

(Issuance Step-I: P&ID Rev-0 Draft)

20

Trang 21

Phase for P&ID Preparation

Premise

(1) Completion of Internal P&ID Review Meeting

(2) Direct participation of all related engineers in mark-up work

of P&ID

(3) Piping material specification draft to be issued

(4) Preliminary line index to be available

(5) Utility main header size

(6) Instrument index (Tag no & Loop no.)

(7) Cause and effect table if required

(8) Prompt receipt of AFC vendor’s design output

Phase-3 P&ID for Approval (Issuance Step-II: P&ID Rev-0 and Conceptual UFD)

21

Trang 22

Phase for P&ID Preparation

Main Items to be Indicated

- Piping line number (*)

- Piping class break

- Notes and precautions concerning piping layout

- Minimum distance, pipe straight run, etc

Phase-3 P&ID for Approval (Issuance Step-II: P&ID Rev-0 and Conceptual UFD)

22

Trang 23

Phase for P&ID Preparation

Main Items to be Indicated

(d) Instrumentation information

- Instrument identification and tag number

- Loop configuration and components

- Interlock function

- Measurement/alarm designation and location

- Instrument protection (seal, purge, trace, etc.)

- LC/LG preliminary information

(e) Vendor information

- AFC vendor information

(*) This information could be shifted to next Phase-4

Phase-3 P&ID for Approval (Issuance Step-II: P&ID Rev-0 and Conceptual UFD)

23

Trang 24

Phase for P&ID Preparation

Review Meeting with Client

In the case of obtaining client’s approval at this Phase-3, a review meeting will be held with the client depending on the volume of comments by client The client’s approval shall be obtained prior

to Phase-4

(1) Preparatory work :

A comment list showing the results of client's review shall be

previously obtained, and JGC’s views on the abovementioned results shall be established.

(2) Attendants at review meeting with client :

At least the respective personnel concerned from the process

engineering department, project department and instrumentation & control department shall attend the review meeting

Phase-3 P&ID for Approval (Issuance Step-II: P&ID Rev-0 and Conceptual UFD)

24

Trang 25

Phase for P&ID Preparation

Review Meeting with Client

(3) Method of review :

• Discussions shall be held on the basis of the client’s review list

• The requirements thus established on the basis of the results

of the abovementioned discussions shall be indicated in the P&ID so as to be followed up at the next revision issue of

P&ID

• Specially important matters shall be confirmed when

• preparing minutes of meeting

Phase-3 P&ID for Approval (Issuance Step-II: P&ID Rev-0 and Conceptual UFD)

25

Trang 26

Phase for P&ID Preparation

(2) Major and critical piping drawing

(3) Critical piping MTO (Material Take Off)

Phase-4 P&ID for Piping Layout (Issuance Step-III: P&ID Rev-1 and UFD Rev-0)

26

Trang 27

Phase for P&ID Preparation

Premise

(1) Prompt resolution of client’s comments

(2) Coincidence check with equipment data sheet

Trang 28

Phase for P&ID Preparation

Main Items to be Indicated

- Revision of piping size based on hydraulic design

- Piping size around CV and bypass line

- Revision of pump minimum flow line

Phase-4 P&ID for Piping Layout (Issuance Step-III: P&ID Rev-1 and UFD Rev-0)

28

Trang 29

Phase for P&ID Preparation

Main Items to be Indicated

(d) Instrumentation information

- LC/LG final arrangement

- DCS software alarm requirements

- PSV/RV/CV size

- Instrument draining and venting

- Analyzer sample conditioning and utility piping

- Auxiliary instruments (strainer, straightener, etc.)

(e) Vendor information

- To incorporate vendors’ information up to this stage

Phase-4 P&ID for Piping Layout (Issuance Step-III: P&ID Rev-1 and UFD Rev-0)

29

Trang 30

Phase for P&ID Preparation

Purpose

Smooth execution of construction work

Issue Schedule

6.0 ∼ 8.0 Month

Subsequent Downstream Work

(1) Piping FC (For Construction) drawing

(2) Production engineering

Phase-5 P&ID for Construction (Issuance Step-IV: P&ID Rev-2 and UFD Rev-1)

30

Trang 31

Phase for P&ID Preparation

Premise

(1) Minimization of HAZOP recommendation (by

brushing up the quality of P&ID at previous phase )

(2) Revision hereinafter is followed by NPIC

(3) Estimation of utility consumption of packaged

equipment and rotating equipment

(4) Estimation of auxiliary piping tie-in size and rating of rotating equipment

Phase-5 P&ID for Construction (Issuance Step-IV: P&ID Rev-2 and UFD Rev-1)

31

Trang 32

Phase for P&ID Preparation

Main Items to be Indicated

(a) General

- To follow up HAZOP recommendation

- To incorporate the results of detailed engineering so far as necessary for piping and instrumentation design

(b) Equipment information

- No specific additional information at this phase

(c) Piping information

- Piping size around PSV/RV, especially inlet and outlet piping size

- Piping tie-in with vendors’ scope

- Revision of utility piping size based on final utility requirements

Phase-5 P&ID for Construction (Issuance Step-IV: P&ID Rev-2 and UFD Rev-1)

32

Trang 33

Phase for P&ID Preparation

Main Items to be Indicated

(d) Instrumentation information

- Special instruments connection size and rating

- Auxiliary piping for instruments

(e) Vendor information

- To incorporate most of vendors’ information obtained up to this stage

- Auxiliary piping tie-in size and rating of rotating equipment will be informed at later stage however,

they shall be indicated together with estimated size.

Phase-5 P&ID for Construction (Issuance Step-IV: P&ID Rev-2 and UFD Rev-1)