COLUMN ANCHOR METHOD plan Anchor cable Concrete beam Anchor on beam Angle L75 Concrete pipe TYPICAL COLUMN ERECTION METHOD Anchor cable Anchor cable PACKAGE CIVIL STRUCTURE WORKS SCALE:
Trang 12COLUMN ERECTION
TEMP COLUMN ANCHOR METHOD
plan
Anchor cable
Concrete beam
Anchor on beam
Angle L75
Concrete pipe
TYPICAL COLUMN ERECTION METHOD
Anchor cable
Anchor cable
PACKAGE
CIVIL STRUCTURE WORKS
SCALE: FIT DATE: REVISION:
CAM PHA TOWN, QUANG NINH PROVINCE
CONSTRUCTION & INVESTEMENT., JSC CONSTRUCTION CO., LTD
CHECKED BY
APPROVEDDRAWING BYVIETNAM
TYPICAL COLUM ERECTION METHOD STRUCTURE WORK
Trang 13FRAME ERECTION METHOD
SCAFFOLDING
ANCHOR CABLE SAFETY CABLE
PACKAGE
CIVIL STRUCTURE WORKS
SCALE: FIT DATE: REVISION:
CAM PHA TOWN, QUANG NINH PROVINCE
CONSTRUCTION & INVESTEMENT., JSC CONSTRUCTION CO., LTD
CHECKED BY
APPROVEDDRAWING BYVIETNAM
FRAM ERECTION METHOD STRUCTURE WORK
Trang 14CIVIL STRUCTURE WORKS
SCALE: FIT DATE: REVISION:
CAM PHA TOWN, QUANG NINH PROVINCE
CONSTRUCTION & INVESTEMENT., JSC CONSTRUCTION CO., LTD
CHECKED BY
APPROVEDDRAWING BY
VIETNAM
ROOF ERECTION METHOD STRUCTURE WORK
Trang 15ROOF SHEET
ROOF SHEET ERECTION METHOD
PACKAGE
CIVIL STRUCTURE WORKS
SCALE: FIT DATE: REVISION:
CAM PHA TOWN, QUANG NINH PROVINCE
CONSTRUCTION & INVESTEMENT., JSC CONSTRUCTION CO., LTD
CHECKED BY
APPROVEDDRAWING BY
VIETNAM
ROOF ERECTION METHOD STRUCTURE WORK
Trang 16- THE MASONY SHALL BE LOCATED DURING THE CONSTRUCTION WITH THE OPENING FOR THE PIPECS OF WATER
SUPLLY&DRAINAGE, ELECTRIC, AIR CONDITION SYSTEMS.
- THE LOCATING OF OPENINGS, ANCHORING BOLTS SHALL BE IN COMPLIANCE WITH THE DESIGN BEFORE LAYING THE
BRICK THE BRICK SHALL BE WATER OR MOISTURIZED BEFORE THE CONSTRUCTION.
- THE INTERSECTION OF THE MASONY SHOULD BE WATERED AND CLEANED.
- THE BRICKS SHALL BE LAID IN THE HORIZONTAL DIRECTION WITH MORTAR JOINTS THE THICKNESS OF JOINTS SHALL NOT
BE GREATER THAN 10mm.
- THE PULLING OPENING POINTS SHALL BE MET WITH TECHNICAL SPECIFICATIONS OF DIMENSION AND
LOCATIONS FOR ACCURACY.
- NO BROKEN BRICKS SHALL BE USED FOR THE CONSTRUCTION OF HORIZONTAL BLOCKS.
- IN ORDER TO ENSURE THE FLATNESS OF THE WALL, THE LINES AND SQUARE RULER SHALL BE USED FOR
THE CONSTRUCTION OF BOTH WALL SIDES.
PACKAGE
CIVIL STRUCTURE WORKS
SCALE: FIT DATE: REVISION:
CAM PHA TOWN, QUANG NINH PROVINCE
CONSTRUCTION & INVESTEMENT., JSC CONSTRUCTION CO., LTD
CHECKED BY
APPROVEDDRAWING BY
VIETNAM
BRICK WORK METHOD FINISHING WORK
Trang 17- THE PULLING OPENING SHALL BE MET WITH TECHNICAL SPECIFICATIONS AND LOCATION FOR ACCURACY
- NO BROKEN BRICKS SHALL BE USED FOR THE CONSTRUCTION OF HORIZONTAL BLOCKS.
- IN ORDER TO ENSURE THE FLATNESS OF THE WALLS, THE LINES AND SQUARE RULER SHALL BE USED FOR THE CONSTRUCTION OF BOTH WALL SIDES.
- THE LOCATING OF OPENINGS, ANCHORING BOLTS SHALL BE IN COMPLIANCE WITH THE DESIGN BEFORE LAYING THE BRICKS THE BRICKS SHALL BE WATER OR MOISTURIZED BEFORE THE CONSTRUCTION
- THE BRICK SHALL BE WATER OR MOISTURIZED BEFORE THE CONSTRUCTION.
- THE INTERSECTION OF THE MASONRY SHOULD BE WATERED AND CLEANED.
- THE BRICK SHALL BE LAID IN THE HORIZONTAL DIRECTION WITH MORTAR WITH MORTAR IN JOINTS THE THICKNESS OF JOINTS SHALL NOT BE THAN GREATER THAN 10MM.
PACKAGE
CIVIL STRUCTURE WORKS
SCALE: FIT DATE: REVISION:
CAM PHA TOWN, QUANG NINH PROVINCE
CONSTRUCTION & INVESTEMENT., JSC CONSTRUCTION CO., LTD
CHECKED BY
APPROVEDDRAWING BY
VIETNAM
BRICK WORK METHOD FINISHING WORK
Trang 18CIVIL STRUCTURE WORKS
SCALE: FIT DATE: REVISION:
CAM PHA TOWN, QUANG NINH PROVINCE
CONSTRUCTION & INVESTEMENT., JSC CONSTRUCTION CO., LTD
CHECKED BY
APPROVEDDRAWING BYVIETNAM
COLUMN LOCATING FINISHING WORK
Trang 19PRECAUTION FOR USING ELEVATOR
- MATERIAL IS TRANSPORTED VERTICALLY BY ELEVATOR AND HORIZONTALLY BY CART.
AND LIFTING FLOOR' POSITION MUS BE AT GROUND.
- REQUIRING SWITCH OFF ELECTRIC WHEN NOT USING.
- NOT USING ELEVATOR TO TRANSPORT WORKERS.
- WHEN OPERATING, WORKERS NOT WALKING BELOW THE LIFTING FLOOR.
- ONLY OPERATOR IS PERMITTED TO CONTROL.
- MATERIAL IS MEASURED BY DEDICATED POT.
- MORATR PROCESSING IS INSPECTED BY SITE ENGINEER.
- THE WALL'S SURFACE MUST MEET TECHNICAL REQUIRES
- USING ALUMINIUM RULE TO CHECK THE WALL'S SURFACE
USING ELEVATOR PRECAUTION OF MORTAR POT
CEMENT CEMENT CEMENT
PACKAGE
CIVIL STRUCTURE WORKS
SCALE: FIT DATE: REVISION:
CAM PHA TOWN, QUANG NINH PROVINCE
CONSTRUCTION & INVESTEMENT., JSC CONSTRUCTION CO., LTD
CHECKED BY
APPROVEDDRAWING BY
VIETNAM
MOTAR PROCESSING SERVING FOR FINISHING WORK FINISHING WORK
Trang 20T IL
IN G L E
COLUMN PLASTERING
NOTES:
- THE LOCATION MARKS OR MORTARING THICKNESS-CONTROLLING MARKS SHALL BE
MADE BEFORE PLASTERING.
- THE DUST, MOSS, OIL STAINS OF STRUCTURE SHALL BE REMOVED AS WELL AS THE LEVELING THE
CONCAVENESS OR CONVEXITY OF THE SURFACE SHALL BE DONE BEFORE PLASTERING.
- FOR THE WATER PROOFING AND ADHESION EFFICIENCY BETWEEN LAYERS, THE CEMENT MORTARING
SHALL BE USED FOR SOME WORKS WITH HIGH MOITURE SUCH AS TOILETS, WASHING ROOM
NO CLASHES OR VIBRATION AS WELL AS THE SUDDEN HEAT OR WATER SHALL BE MADE TO THE NEW
THE GRADIENT AND DIRECETION OF THE PAVING WORK SHALL BE CHEKED BY POURING WATER
THE PAVING WORK SHALL NOT BE HIT WITH CRASHES WHEN THE JOINTS HAVE NOT BEEN WEDGED YET.
THE CEMENT MORTAR SHALL BE PUT INTO THE INSERTIONS OF PAVING PARTS AND BASE SHOES.
PACKAGE
CIVIL STRUCTURE WORKS
SCALE: FIT DATE: REVISION:
CAM PHA TOWN, QUANG NINH PROVINCE
CONSTRUCTION & INVESTEMENT., JSC CONSTRUCTION CO., LTD
CHECKED BY
APPROVEDDRAWING BY
VIETNAM
FINISHING WORK - PLASTERING PAVING AND VERNEERING FINISHING WORK
Trang 21edge detail
ZONE 3, MONG DUONG EWARD
PACKAGE
CIVIL STRUCTURE WORKS
SCALE: FIT DATE: REVISION:
CAM PHA TOWN, QUANG NINH PROVINCE
CONSTRUCTION & INVESTEMENT., JSC CONSTRUCTION CO., LTD
CHECKED BY
APPROVEDDRAWING BY
VIETNAM
WC VERNEERING METHOD FINISHING WORK
Trang 22fire extinguisher
labour safety and environment protection
truck shall be cleaned before going out truck shall be covered
do not obstruct other vehicles working at site
safety measure shall be applied
vehicles shall be inspected before working
minimising the noise at site
cooking proposed places
do not use inflammable element at site
PACKAGE
CIVIL STRUCTURE WORKS
SCALE: FIT DATE: REVISION:
CAM PHA TOWN, QUANG NINH PROVINCE
CONSTRUCTION & INVESTEMENT., JSC CONSTRUCTION CO., LTD
CHECKED BY
APPROVEDDRAWING BYVIETNAM
LABOR SAFETY AND SAFETY WORK
ENVIRONMENT PROTECTION
Trang 23safety engineer
no te
bo ok
labour safety and environment protection
welding with welder's goggles minimising the noise at site
do not scatter water
do not scatter material at internal roads usual industral cleaning
don't suspend electric line on twig don't put electric line on ground
the operator shall inspect the safety elements of electricity component before working
do not operate without labour protection such as: shoes, helmet, insulated gloves
lock
placing in dryplace
control panel control panel
PACKAGE
CIVIL STRUCTURE WORKS
SCALE: FIT DATE: REVISION:
CAM PHA TOWN, QUANG NINH PROVINCE
CONSTRUCTION & INVESTEMENT., JSC CONSTRUCTION CO., LTD
CHECKED BY
APPROVEDDRAWING BYVIETNAM
LABOR SATEFY AND ENVIRONMENT PROTECTION SAFETY WORK
Trang 24filling sand
CONSTRUCTION SEQUENCES OF EMBANKMENT
CONSTRUCTION OF EMBANKMENT K95
- Materials shall be transported and stockpiled
- Initial compaction by steel roller 8-10T
- Tight compaction by vibrating roller 12-25T
as directed by Contractor's site inspector
- During compaction duration, material moisture shall be regularly controlled.
and taking measures for moisture maintenance at optimum rate
- Continue filling to designed level and waiting for settlement (if any)
- Settlement monitoring (soft soil treatment section)s
- At end of settlement period, additional filling for settlement
- Finish compaction for to surface as designed
directed by Contractor's site inspector
- Tight compaction by vibrating roller 12-25T
- Initial compaction by steel roller 8-10T
-Materials shall be levelled in layer of 15-20cm by motor grader
Filling soil K98 Vibrating roller 12- 25T
- Surface finish compaction by steel roller 8-10T
Steel roller 8-10T
- Materials shall be transported by dump truck and stockpiled as
Bulldozer
Steel roller 8-10T
- Materials shall be leveled in each layer of not more than 20-25cm
- Moisture checking should be regularly controlled during compaction
- and taking measures for moisture maintenance at optimum rate
by bulldozer in combinattion with motor grader.
PACKAGE
CIVIL STRUCTURE WORKS
SCALE: FIT DATE: REVISION:
CAM PHA TOWN, QUANG NINH PROVINCE
CONSTRUCTION & INVESTEMENT., JSC CONSTRUCTION CO., LTD
CHECKED BY
APPROVEDDRAWING BY
VIETNAM
CONSTRUCTION SEQUENCES INFRASTRUCTURE WORK
OF EMBANKMENT
Trang 25CONSTRUCTION SEQUENCE FOR FOUNDATION
CONSTRUCTION OF SUBASE AGGREGATE COURSE
Paver
Dump truck 12T
Aggregate material shall be spreaded by specialized paver
- Thickness of each layer shall be 10-15cm
- Innitial compaction by steel roller 10-12T
- Tight compaction by vibrating roller 12-25T then compact by tired roller 25T
- Finish compaction by steel roller 10-12T
- Moisture shall be regularly checked during compaction period
steel roller 10-12T roller 25T steel roller 12-25T Steel roller 10-12T Paver Dump truck 12T
CONSTRUCTION OF BASE AGGREGATE COURSE ( motor grader as accepted by Engineer)
- Aggregate material shall be spreaded by specialized paver
- Thickness of each layer shall be 15cm
- Innitial compaction by steel roller 10-12T - Moisture shall be regularly checked during compaction period
- Finish compaction by steel roller 10-12T
- Tight compaction by vibrating roller 12-25T then compact by tired roller 25T
PACKAGE
CIVIL STRUCTURE WORKS
SCALE: FIT DATE: REVISION:
CAM PHA TOWN, QUANG NINH PROVINCE
CONSTRUCTION & INVESTEMENT., JSC CONSTRUCTION CO., LTD
CHECKED BY
APPROVEDDRAWING BYVIETNAM
INFRASTRUCTURE WORK
CONSTRUCTION SEQUENCES
OF FOUNDATION
Trang 26asphalt / AC paver
- Spreading the asphalt concrete by specialized Paver
- Spreading temperature of asphalt concrete shall be 120 - 150oC
- initial compaction by steel roller 6-8T
- compaction by tired roller 16-25T
- Finish compaction by steel roller 10-12T
CONSTRUCTION OF AC BINDER COURSES
- Cleaning of foundation surface by air compressor
CONSTRUCTION SEQUENCE FOR PAVEMENT
- Spraying of prime coat in accordance with technical Specifications
CONSTRUCTION OF PRIME COAT
- Waiting for 24 hours for bitum penetration then construct the AC binder course
PACKAGE
CIVIL STRUCTURE WORKS
SCALE: FIT DATE: REVISION:
CAM PHA TOWN, QUANG NINH PROVINCE
CONSTRUCTION & INVESTEMENT., JSC CONSTRUCTION CO., LTD
CHECKED BY
APPROVEDDRAWING BYVIETNAM
INFRASTRUCTURE WORK
CONSTRUCTION SEQUENCES
OF PAVEMENT
Trang 27- Cleaning of surface by air compressor - Spreading temperature of AC shall be 120 - 150 oC
- Spreading of tack coat in accordance with technical Specification
- spreading of AC surface course by specialized AC paver
CONSTRUCTION OF ASPHALT SURFACE COURSE
- Finish compaction by steel roller 10-12T
- Tight compaction by tired roller 16-25T
- Initial compaction by steel roller 6-8T
Dump truck 12T Steel roller 6-8T
- Làm sạch mặt đường bằng máy nén khí
- Rải lớp bê tông asphalt hoặc bê tông tạo nhám bằng máy rải chuyên dụng
- Tưới lớp nhựa dính bám 0.5 kg/m2 bằng xe tưới nhựa chuyên dụng
Thi công lớp Bê tông nhựa tạo nhám
Lu sơ cấp, lu chặt và lu hoàn thiện
- Nhiệt độ của bê tông khi rải từ 120 - 150 oC
CONSTRUCTION SEQUENCE FOR ASPHALT LAYER
- Waiting until the tack coat is dried then construct
PACKAGE
CIVIL STRUCTURE WORKS
SCALE: FIT DATE: REVISION:
CAM PHA TOWN, QUANG NINH PROVINCE
CONSTRUCTION & INVESTEMENT., JSC CONSTRUCTION CO., LTD
CHECKED BY
APPROVEDDRAWING BY
Trang 28Step 2
Backfilling soil
R.C pipe culvert
Step 4:
- Treat conection, water-proofing.
- Granular drainage material backfill.
- Installing the pipe culvert by excavator.
- Finishing.
- Cradle and pipe culvert will be cast in factory
and transported to site by specialized vehicles
- Excavation of foundation pit by excavator and
- Construction of blinding stone layer.
- Installing the cradle by Excavator.
Step 2:
Bulldozer
Step 4
Excavator Step 3:
1:1
SECTION 2-2
DIRECTION
SECTION 1-1(AFTER TRIM MANUAL AND COMPACTION)
INSTALLED SEWAY PILE GL=3.55m
W R
PACKAGE
CIVIL STRUCTURE WORKS
SCALE: FIT DATE: REVISION:
CAM PHA TOWN, QUANG NINH PROVINCE
CONSTRUCTION & INVESTEMENT., JSC CONSTRUCTION CO., LTD
CHECKED BY
APPROVEDDRAWING BYVIETNAM
CONSTRUCTION OF SEWAY SYSTEM STRUCTURE WORK
Trang 292 - House for staff (153 m2)
3 - Firt aid and medical facilities (14 m2)
4 - Kitchen and dining room for staff (54 m2)
5 - Toilet for staff (15M2)
6 - Guard house (3 m2)
7 - Rebar yard (126 m2)
8 - Formwork yard (77 m2)
10 - Camps for labor (2x300 m2)
11 - Kitchen and dining room for labor (2x140 m2)
12 - Toilet for labor (2x72m2)
8 - Fabrication yard (500 m2)
ZONE 3, MONG DUONG EWARD
PACKAGE
CIVIL STRUCTURE WORKS
SCALE: FIT DATE: REVISION:
CAM PHA TOWN, QUANG NINH PROVINCE
CONSTRUCTION & INVESTEMENT., JSC CONSTRUCTION CO., LTD
CHECKED BY
APPROVEDDRAWING BY
Trang 302 - House for staff (153 m2)
3 - Firt aid and medical facilities (14 m2)
4 - Kitchen and dining room for staff (54 m2)
5 - Toilet for staff (15M2)
6 - Guard house (3 m2)
7 - Rebar yard (182 m2)
8 - Formwork yard (111 m2)
10 - Camps for labor (2x340 m2)
11 - Kitchen and dining room for labor (2x160 m2)
12 - Toilet for labor (2x72m2)
8 - Fabrication yard (500 m2)
64000
ZONE 3, MONG DUONG EWARD
PACKAGE
CIVIL STRUCTURE WORKS
SCALE: FIT DATE: REVISION:
CAM PHA TOWN, QUANG NINH PROVINCE
CONSTRUCTION & INVESTEMENT., JSC CONSTRUCTION CO., LTD
CHECKED BY
APPROVEDDRAWING BY
Trang 312 - House for staff (153 m2)
3 - Firt aid and medical facilities (14 m2)
4 - Kitchen and dining room for staff (54 m2)
5 - Toilet for staff (15M2)
10 - Camps for labor (2x300 m2)
11 - Kitchen and dining room for labor (2x140 m2)
12 - Toilet for labor (2x72m2)
PACKAGE
CIVIL STRUCTURE WORKS
SCALE: FIT DATE: REVISION:
CAM PHA TOWN, QUANG NINH PROVINCE
CONSTRUCTION & INVESTEMENT., JSC CONSTRUCTION CO., LTD
CHECKED BY
APPROVEDDRAWING BY