Trang 1METHOD STATEMENT FOR EARTHWORK AND
CONCRETE WORK OF MANHOLES
(DOCUMENT CLASS: X)
Operation Centre JOB Code: Operation Centre Doc No.:
Trang 21 INTRODUCTION 3
2 SCOPE OF WORK 3
3 REFERENCES 3
4 ORGANIZATION CHART - RESPONSIBILITIES 5
5 EQUIPMENT 6
6 MATERIALS 6
7 RESOURCES 6
8 PROCEDURE 8
9 SAFETY 10
10 TRAFFIC MANAGEMENT PLAN 15
11 WASTE MANAGEMENT PLAN 15
12 APPENDIX #1 25
13 APPENDIX #2……… 42
Trang 4
3 REFERENCES
Earth Work Specification: 3550-8310-SP-0009
Specification for Concrete works: 3550-8310-SP-0005
Construction Specification for Concrete Work: S-000-1320-1001V
Scaffold Procedure: S-000-1654-0400V
Specification for The Foundation of Storage Tanks: 3550-8310-SP-f0006
HSSE Instructions to Sub-JGCSs: S-000-1654-0250V
Safety Transportation Management Plan: S-000-1654-0300V
HSE Instruction to JGCSs: 3550-8710-SP-0003
Drawing for construction issued from JGCS
Vinaconex E&C HSSE Management Plan VV3120-008-A-403
Vinaconex E&C Traffic Management Plan VV3120-008-A-406
Vinaconex E&C Waste Management Plan VV3120-008-A-404
Vinaconex E&C Emergency Response Plan VV3120-008-A-402
Construction Drawings for Manholes
Construction drawing for Pipes
Drainage Materials and workmanship 3550-8310-SP-0011
Standard pipe connections to manholes D-000-1316-1003V
Trang 54 ORGANIZATION CHART - RESPONSIBILITIES
Site Manager: Do Minh Chau
Directly in charge for daily schedule, mobilization of equipment, materials supply capacity.
Survey, daily schedule, location of work, equipment control, labor for each kind of works
HSSE
HSSE Manager: PN GiangHSSE Supervisor: LH Trung,
VN Hai,HD Bach, DT Ninh
Equipment HSSE control, Permit, access way, Traffic, Labor entry, HSSE training, HSSE at work place
- Labors for works
- Minor tool and equipment, sub- materials, form and
Const Equipment
Condition and number
of Equipment, fuels, drivers, transportation, traffic control, signal, service.
Trang 65 EQUIPMENT
Equipment Name, Capacity No
s
Year of Manuf.
Origin
2012-2014
China
16 Automatic Leveling machine:
NIKON
Trang 7- Prior to using any machineries/equipment at site, it will be inspected and certified by
qualified person
- Periodic Preventive Maintenance will be made by all equipments and machineries
- All operators and drivers are to be educated with valid driver’s license/operator’s license or permit from concerned government agency
- Only authorized drivers and operators are allowed to operate equipment and machinery
- Only authorized signalman will be assigned together with the driver or operator
Sub Concrete: mainly from batching plant of VINACONEX E&C installed on site (batching plant
of Viet Han, SAKURA, VIMECO, OIC or other approved ones by JGCS are standby option)
- Reinforcement: Shall be transported to workshop in the site (submitted to JGCS forapproval)
- Non shrinkage: Shall be submitted by JGCS
- Prior to working any work at site, all workers will be trained safety and certified by JGCS’HSE
- All workers must to have name card for travel on the site
- There are 2 teams for this task
Team 1 working at C200
Table 7.1: LIST OF MANPOWER FOR TEAM 1
Trang 81 Driver of excavator 1 2
Table 7.1: LIST OF MANPOWER FOR TEAM 2
Trang 910 General workers 6
Notes:
- Labour mobilisation schedule would be revised based on updated plan
- VINACONEX E&C will assign HSSE Supervisor and First Aiders regarding worker ratio, 1per 50 workers
- Management staff (see paragraph 4)
24.1 Process for Manhole construction (For manhole with depth of less than 2500mm – Precast
concrete):
Fabrication rebar, formwork and concrete work on the Fabrication yard (on the ground level)
Preparation fabrication yard
Trang 12 Concrete work
Trang 13 Curing of concrete
Excavate manholes located
(If slope higher than 1:0.5 use polythene sheet and sand bag)
Trang 14 Instalation crush stone level thick 20-25cm (if soil condition is very wet and soft make the temporary trench)
Trang 15 Casting lean concrete to design level
Trang 1624.2 Transportation and erection
24.2.1 General requirements
• Site checks before operating
Hard barricade and signage shall be set up around working area
Check for the safe entry and exit of the crane from the site
Check ground condition
Check where the crane is to be position to pick up, swing and deposit the load
Check all lifting gear to be used
Check whether site personnel have been informed as to the dangers of working in the vicinity
of any moving precast manhole and the crane
Check for power lines and correct distance for operation of crane
Check for location of overhead service lines (e.g Steam pipes) to ensure clear operation ofthe crane
Check for location of other facilities which may impact the lift
Check surrounding structures, including making allowance for rear end swing
Check for any obstructions
Ensure that the operating radius is clear of passageways and any pedestrian area, and if not,ensure adequate traffic controlling measures are put in place
Check for underground services, pipes, gas mains and tunnels or any weakness in the surfacewhich will not sustain the combined weight of the crane, the load and any gear to beemployed in the lifting process
Check for recently filled trenches
The correct weight of the load must be obtained by the operator prior to the lift This may be done
by weighbridge certificate, by engineer's certificate, or correct calculation by a competent person.The weight of the precast MH, CB and the gear must be checked with the relevant load chart toensure safe operation at all operating radius
The lifting are should be checked to ensure sufficient clearance if the load should drift
The position of the crane for lifting to ensure that sufficient area is provided for outriggers or
Trang 17stabilisers to be fully extended and packed.
The size of the load must be combined with the height to be lifted and the radius to ensure that theload will not become "boom-proud"
• The safe use of th e crane:
The crane should not be used during inclement weather, if such weather would make safe useimpossible
The wind must be taken into consideration to ensure that the load can be adequately controlled, andbulky loads, such as too much or too large precast MH, CB will not overload or overturn the cranebecause of wind pressure
The precast manhole must be kept as near to the ground as possible at all times
Traffic control plans will be put into place to ensure safe operation in traffic, and ensure that theprecast manhole is not lifted over or near pedestrians, traffic or neighbours property
If necessary, the work area will be cordoned off, especially the area of rear end swing
The crane will be kept level at all times when lifting precast MH and CB to ensure that side- pullwill not occur
Sufficient turns of wire on hook will be used to ensure that the load is properly supported inaccordance with the load charts and crane specification
If moving the crane while with holding the load is required, the load will be secured to the craneand a spotter used to make sure the operator is aware of all hazards
If boom extension is needed, then the correct sequence of boom extension must be used
The crane operator must not leave the crane driving station while the crane is under load
The crane will, at all times, be operated in accordance with manufacturer's specification
Fly jib installation, if required, will only be carried out by qualified, experienced personnel, anderected in accordance with manufacturer's specification, and correctly stowed at the end of the jobfor travel
Check the lifting gear carefully before using it in the lift, and such gear must be used within theirrated Safe Working Load rating, and in accordance with their design
• Dismantling:
When lifting operations are finished, the operator will leave the hooks clear of all obstructions
Trang 18The boom will be retracted and lowered in a safe manner, ensuring that the hook block(s) are raised
in conjunction to ensure that the hooks do not foul any object
When outriggers are out of sight, the supervisor will ensure that a lookout or observer will keeppeople away when
retracting the outriggers
Oncethecraneissecure
Trang 19Methodology of transportation, loading, unloading and installation
The following Chart describes the lifting work sequence:
• Step 1 Preparation for work
The crane, together with the associated operating crew will arrive on site at the specified
and agreed date and time
At the beginning of each day starts, tool box meeting is required to inform all people about
the activity shall be conducted
Guide all workers for safety rule must be followed during lifting activity
Assign barricade, guide line and signage in the necessary location to inform people about
dangers may happen
Any traffic management, ancillary pans, maps or temporary roadways etc are required to
be positioned or other means, prior to the crane or cranes manoeuvring into position, it will
be done under the instruction of the Supervisor
Preparation for works
Installation lifting devices
Lifting MH to the trailer
Transportation of MH
Unloading MH
Finish the work
Trang 20• Step 2: Installation lifting devices
Upon completion of the rigging procedure, the crane operator will carryout procedural
safety and checks again, implementing any specific operational requirements
The crane operator will then be instructed to hoist lifting tackle clear of any obstructions
and position the crane ready for the first required lift Any deliveiy/removal vehicles will
now be positioned adjacent to the crane as right position, ready for work to commence
Depending on the load of precast manhole (in this case the maximum load is the manhole
which have load around 10 ton], we can choose the cable for lifting It shall be check and
agree by supervisors and safety officer prior conducting work
• Step 3: Lifting precast manhole to the trailer
Flagman will issue instructions via hand signals or two-way radios to the crane operator to
position the crane over first required lift, flagman will plumb the boom head, directly over
the load or set short to allow for jib deflection where necessary
The flagman will instruct crane operator, the lower the hooks with lifting tackle to allow
trained rigger to attach lifting tackle to load
Once the load is clear of all obstructions, the flagman will give instructions to the crane
operator to manoeuvre the Precast manhole the right position on the trailer
The flagman will instruct the crane operator to lower the load to just above the landing
position and then instruct the operator to stop lowering, after that site supervisor will
confirm position and orientation of load prior to landing
Once the lifting tackle is clear of all obstructions the flagman will instruct the crane
operator to manoeuvre the crane ready for any further lifts that may be required and had
over to another flagman were required
• Step 4: Transport by trailer
The supervisor shall check again to make sure all precast MH and CB are in right position
and stable on the trailer Avoiding statement that precast MH, CB can be moved while
transporting it
Use chain to fix precast MH, CB on the trailer
The driver must have right certification and good experience for driving the trailer
Safety check for road travel must be carried out before transporting If there's any obstruct
object, remove it and make the ways always clean from dangers
• Step 5: Unloading the precast manhole
The Supervisor will then instruct the crane operator to lower all lifting tackle to the ground to
Trang 21allow removal from hook.
The crane operator will then instigate the removal of any lifting tackle stored on the crane andthen commence the de-rig procedure
All personnel assisting with de-rigging will be under the guidance of the crane operator at alltimes The de-rig procedure will be carried out as per crane manufacturers manual
The remaining members of the lifting crew will ensure that any ancillary mats or equipmentetc.are removed from site or placed in an appropriate position ready for collection prior tothem leaving site
The supervisor will inform the Site Manager or site representative of the completion of theoperation and address any issues that may be raised and inform of any equipment left on sitefor later collection
24.2.2 Transportation to erection site
Precast manhole will be transported from the storage yard to the erection site by trailers.Precast manhole will be fixed properly during transportation
Worker will be control the precast mahole by tag line
Install temporary bearing with wedge
During lifting and unloading arrange some worker to control the precast manhole to locatedposition as design,put it down slowly and carefully
Surveyor will be check final correct position and level for each precast manhole
Trang 23After install Manhole, Lifting hook will be cut and put motar (motar shall not be less than the
compress strength of panent concrete) in hole
8.2 Process for Manhole construction (For manhole with depth greater than 2500mm – In-situ concrete):
Trang 24Removal of formwork
Installation ofMiscellaneousSteels
THE SEQUENCE FOR EXECUTION OF MANHOLES
Trang 26-Using excavator excavating to design level
(If slope is higher than 1:0.5 use sand bag and plastic sheet to protect the slope)
b) Blinding concrete works
-Reinforced concrete foundation shall be placed upon blinding concrete whose strength classshall be C16/20, not less than 50mm thick, and laid over the ground immediately after
Trang 27excavation to provide a clean working surface Blinding concrete shall not be laid until existingground to receive blinding has been approved by the JGCS.
-Under yard paving, 0.25mm thick heavy duty polythene sheet may be used instead of concreteblinding Polythene sheet shall be laid in the longest lengths and widest widths available withoverlaps not less than 150mm at all joints and intersections Polythene sheet shall be laid on asurface free of hard spots or projections likely to cause a puncture
c) Rebar works
Fabrication of Reinforcement:
- All Steel reinforcement shall be deformed, high yield and shall have a minimum characteristicyield strength of 460 MPa complying with BS 4449 grade 460 type 2 or ASTM A615 grade 60(fy=420 MPa) and approved by JGCS for types and brand names (paragraph 3.7 ConstructionSpecification for Concrete Work: S-000-1320-1001V)
- After delivery reinforcement on site, inspection will be conducted by delivery slip, the certificateand checking invoice until conforming to the specifications Reinforcement will be laid on themanholes Cover sheet will be used for preventing from rust
Cover sheet
Storage of reinforcing bar s
- After cutting and bending the reinforcing bar, shapes, numbers and bending radius will bechecked for conforming to the drawings and specifications Reinforcing bar shall be cut according
to mechanical method and bended follows requirements of the drawings and specifications.(paragraph 14 Construction Specification for Concrete Work: S-000-1320-1001V)
- Reinforcement which has been bent to facilitate transportation in short trucks shall not be used
Trang 28Installation of reinforcing bar:
- Using concrete spacers to keep specified concrete cover for reinforcing bar The spacers aremade of precast concrete blocks having a compressive strength not less than that of theStructure concrete
- Area for storage of reinforcing bar shall be covered to be avoided from dust, raining water in
case casting concrete has not been started
DETAILS OF ANGLE BAR , ANCHOR
Trang 29-Formwork is made of steel or plywood with steel frame
- Store for form and scaffold shall be covered and form condition should be regularly maintainedafter each time of using
- When the formwork have been checked and accepted, using separation materials for formwork
to prevent adhesion between concrete and formwork, in addition, this shall make easydisassembly, flatness, evenness for structures
Trang 30- Form tie of steel rod will be applied at two level, the hole remained after removing of form tie will
be filled with cement mortar
Concrete mixing at batching plant and transportation:
- The batching plant will be ready for supply at the time of placing concrete
- Accurately scaling and measurement of concrete is required for concrete mixing Water andhumidity of sand and aggregate should be regularly checked and adjusted in order to get theslump as required
- Transporting concrete from batching plant to casting location by concrete mixer trucks Based
on concrete volume casted for each item and casting speed as well, JGCS shall arrange number
of concrete mixer trucks as required assuring the concrete’s uniformity and slump specified in theproject technical specification
- Water must not be added to the mix after the concrete has left the mixer
Casting and Compacting Concrete:
- Concrete will be cast with concrete pump truck
- The vibrators will be inserted into concrete vertically The intervals of the insertion of vibratorsare constant and suitable space in consideration of effective area of the vibration It is prohibited
to contact vibrators with reinforcing bar and move concrete by vibration Vibrators (needlevibrator) shall be inserted at such distances apart or applied in such a manner as will ensure thatthe concrete is satisfactorily and uniformly compacted Immersion vibrators shall penetrate thefull depth of the layer, and shall be withdrawn slowly to prevent the formation of voids When theunderlying layer is of fresh concrete, they shall enter and re-vibrate that layer to ensure thatsuccessive layers merge together Vibration shall be carried out in a manner which does notpromote segregation of the concrete Immersion vibrators shall be withdrawn slowly to preventthe formation of voids
- Compaction shall take place within 30 minutes from the time when agitation of the mix hasceased When ready mixed concrete is supplied in purpose-made agitators the time between theintroduction of cement to the mix and compaction shall not exceed 2 hours and shall not exceed
1 hour when air temperature exceeds 25°C (paragraph 9.2 of the Construction Specification forConcrete Work: S-000-1320-1001V)
- During concrete casting, it is required to regularly check and observe formwork and seal anyleakage, if any
Trang 31- Concrete shall be placed in layers that are approximately horizontal and not exceeding 450mm
in depth
- The cover seat will be prepared for preventing rain during concrete casting
- Fabrication of test cylinders and transportation to the laboratory shall be the responsibility ofsub-JGCS The rate of sampling for strength testing shall be one per 50 m3 of concrete Theminimum number of test cylinders to be prepared from each sample shall be six, three for testing
at age 7 days and three at 28 days
Trang 32
e) Finishing and curing works
Finishing and Curing Concrete:
- After concrete progresses hardening, concrete surface shall be finished by steel trowels so thatcoarse aggregates do not appear in the concrete surface
- Curing shall be carried out in anncodance with the requirement of BS 8110 Immediately afterfinishing or removal of formwork, the exposed surface of the concrete shall be protected duringhardening from the effects of sun, drying winds, cold, rain or running water Until after the initialset of the concrete the means of protection used shall not be supported from the concrete.During curing the concrete shall be protected from damage by shock, vibration, water, frost, orany agent likely to interfere with the process of setting and hardening Loads of any kind shall not
be placed on the concrete during the curing period without permission from EMPLOYER/JGCS
Removal Formwork of Structure:
- Vertical formwork shall be removed after 01 day Removal works shall be carefully carried out
so that no damage or defect occurred to the structure
- After removal, formwork shall be cleaned and maintained at site workshop
f) Connect pipes works
Trang 33DETAILS OF CONNECTION GRP PIPES
DETAILS OF CONNECTION RCP PIPES
Trang 34DETAILS OF BOX OUTS FOR PUDDLE FLANGE
BOX-OUT SIZE FOR RCP AS FOLLOW:
Trang 35BOX-OUT AND PUDDLE FLANGE SIZE FOR GRP AS FOLLOW:
Trang 36g) Backfilling works
Backfilling by excavated soil after casting of concrete of manholes
Using of roller and Rammer for compaction (less then 5T) in adjacent area to newly castedmanholes will be carried out minimum after 3 days or when the compressive strength of concretegain more than 70% of the design compressive strength Backfilling by layer less than 300mmun-compacted thickness
Construction tolerance for in-situ construction and placement to complied with paragraph 16 of
the Construction Specification for Concrete Work: S-000-1320-1001V
1.1 Manholes
Each manhole shall be tested for watertightness in the presence of the Engineer by filling with