Method statement and Job Safe Analysis for concrete slab 1. Purpose : The purpose of this document is to describe the method for concrete slab and to details out the step to be taken to meet EHS and technical requirements for concrete slab. 2. Scope of work : This method statement covers the works which related to concrete slab work at site (workshop floor).This is also describes details of EHS requirement, equipment, manpower. 3. Responsibilities : It is overall responsibility of project manager to organize resources to perform concrete slab work activities as per project specification in with schedule and safety requirements. EHS Manager will ensure coordination with Site Manager and Site Supervisor that all measure taken shall be maintained until completion of job.
Trang 1METHOD STATEMENT FOR ROOF AND WALL PANEL
INSTALLATION
Kim Min Wook
METHOD STATEMENT FOR ROOF AND WALL PANEL
INSTALLATION
Kim Min Wook
METHOD STATEMENT FOR ROOF AND WALL PANEL
INSTALLATION
Kim Min Wook
Trang 21 PURPOSE 3
2 REFERENCE DOCUMENTS 3
3 SCOPE 3
4 REPONSIBILITIES 3
4.1.1 Project Manager: 3
4.1.2 Site Manager 4
4.1.3 Erection engineer 5
4.2.4 Erector 5
4.2.6 HSSE Manager 6
4.2.7 HSSE Supervisor 7
4.2.8 QC inspector 7
4.2.9 Temporary building and facilities 8
4.2.10 Insurance 8
5 EXECUTTION SEQUENCE 9
5.1 Unloading 9
5.2 Checking 9
5.3 Materials arrangement 10
6 PANEL INSTALLATION 11
7 HEALTH AND SAFETY REQUIREMENTS 16
7.1 Health and safety training 16
7.2 Equipment and tools used in the erection activity 16
7.2.2 Hand tools 17
7.2.3 Horizontal Fall Arrest System 17
7.2.4 Full body harness required 19
7.3 OTHERS 19
8 JOB SAFETY ANALYSIS 19
Contents 1 PURPOSE 3
2 REFERENCE DOCUMENTS 3
3 SCOPE 3
4 REPONSIBILITIES 3
4.1.1 Project Manager: 3
4.1.2 Site Manager 4
4.1.3 Erection engineer 5
4.2.4 Erector 5
4.2.6 HSSE Manager 6
4.2.7 HSSE Supervisor 7
4.2.8 QC inspector 7
4.2.9 Temporary building and facilities 8
4.2.10 Insurance 8
5 EXECUTTION SEQUENCE 9
5.1 Unloading 9
5.2 Checking 9
5.3 Materials arrangement 10
6 PANEL INSTALLATION 11
7 HEALTH AND SAFETY REQUIREMENTS 16
7.1 Health and safety training 16
7.2 Equipment and tools used in the erection activity 16
7.2.2 Hand tools 17
7.2.3 Horizontal Fall Arrest System 17
7.2.4 Full body harness required 19
7.3 OTHERS 19
8 JOB SAFETY ANALYSIS 19
Contents 1 PURPOSE 3
2 REFERENCE DOCUMENTS 3
3 SCOPE 3
4 REPONSIBILITIES 3
4.1.1 Project Manager: 3
4.1.2 Site Manager 4
4.1.3 Erection engineer 5
4.2.4 Erector 5
4.2.6 HSSE Manager 6
4.2.7 HSSE Supervisor 7
4.2.8 QC inspector 7
4.2.9 Temporary building and facilities 8
4.2.10 Insurance 8
5 EXECUTTION SEQUENCE 9
5.1 Unloading 9
5.2 Checking 9
5.3 Materials arrangement 10
6 PANEL INSTALLATION 11
7 HEALTH AND SAFETY REQUIREMENTS 16
7.1 Health and safety training 16
7.2 Equipment and tools used in the erection activity 16
7.2.2 Hand tools 17
7.2.3 Horizontal Fall Arrest System 17
7.2.4 Full body harness required 19
7.3 OTHERS 19
8 JOB SAFETY ANALYSIS 19
Trang 31 PURPOSE
This method statement covers the construction works for the Fruit of the loom new factory anddeals with the panel of workshop The method statement was prepared in accordance to theSpecification and Drawings as well as the relevant standard and codes
The method statement describes the necessary procedure to follow in order to ensure thatpanel installation works is executed safely and in accordance with the Contract requirements,and that all quality assurance/control activities are conducted in a systematic manner, withinspections and conformance verified and documented
2 REFERENCE DOCUMENTS
DW-SDW-0002.1 Shop drawing for panel workshop
DW-S-0004 Specification for Steel Structure – Erection
3 SCOPE
Works will be carried out based on the construction program and the approved shopdrawings The works will be carried out in a safe manner in accordance with the approved safetyplan and the Specification requirements Panel will be installed to their designated location asshown on the approved shop drawings The works will be coordinated with other constructionactivities on the Site, as necessary and in accordance with the plans, Drawings, Specificationand all relevant standards Upon completion of the Works, the site will be cleaned as necessary
to ensure the smooth execution of other construction activities
4 RESPONSIBILITIES
Acting as the main technical adviser on a construction site for FOTL, crafts people andoperatives
Manage project on time and under budget
Ensuring that all materials used and work performed are as per specifications;
Overseeing the selection and requisition of materials and plant;
Agreeing a price for materials, and making cost-effective solutions and proposals for theintended project;
Managing, monitoring and interpreting the contract design documents supplied by theengineer/ architect;
Liaising with engineers and their representatives(architects, engineers and surveyors),including attending regular meetings to keep them informed of progress;
Daily management of the site, including supervising and monitoring the site labor force andthe work of FOTL;
Planning the work and efficiently organizing the plant and site facilities in order to meetagreed deadlines;
1 PURPOSE
This method statement covers the construction works for the Fruit of the loom new factory anddeals with the panel of workshop The method statement was prepared in accordance to theSpecification and Drawings as well as the relevant standard and codes
The method statement describes the necessary procedure to follow in order to ensure thatpanel installation works is executed safely and in accordance with the Contract requirements,and that all quality assurance/control activities are conducted in a systematic manner, withinspections and conformance verified and documented
2 REFERENCE DOCUMENTS
DW-SDW-0002.1 Shop drawing for panel workshop
DW-S-0004 Specification for Steel Structure – Erection
3 SCOPE
Works will be carried out based on the construction program and the approved shopdrawings The works will be carried out in a safe manner in accordance with the approved safetyplan and the Specification requirements Panel will be installed to their designated location asshown on the approved shop drawings The works will be coordinated with other constructionactivities on the Site, as necessary and in accordance with the plans, Drawings, Specificationand all relevant standards Upon completion of the Works, the site will be cleaned as necessary
to ensure the smooth execution of other construction activities
4 RESPONSIBILITIES
Acting as the main technical adviser on a construction site for FOTL, crafts people andoperatives
Manage project on time and under budget
Ensuring that all materials used and work performed are as per specifications;
Overseeing the selection and requisition of materials and plant;
Agreeing a price for materials, and making cost-effective solutions and proposals for theintended project;
Managing, monitoring and interpreting the contract design documents supplied by theengineer/ architect;
Liaising with engineers and their representatives(architects, engineers and surveyors),including attending regular meetings to keep them informed of progress;
Daily management of the site, including supervising and monitoring the site labor force andthe work of FOTL;
Planning the work and efficiently organizing the plant and site facilities in order to meetagreed deadlines;
1 PURPOSE
This method statement covers the construction works for the Fruit of the loom new factory anddeals with the panel of workshop The method statement was prepared in accordance to theSpecification and Drawings as well as the relevant standard and codes
The method statement describes the necessary procedure to follow in order to ensure thatpanel installation works is executed safely and in accordance with the Contract requirements,and that all quality assurance/control activities are conducted in a systematic manner, withinspections and conformance verified and documented
2 REFERENCE DOCUMENTS
DW-SDW-0002.1 Shop drawing for panel workshop
DW-S-0004 Specification for Steel Structure – Erection
3 SCOPE
Works will be carried out based on the construction program and the approved shopdrawings The works will be carried out in a safe manner in accordance with the approved safetyplan and the Specification requirements Panel will be installed to their designated location asshown on the approved shop drawings The works will be coordinated with other constructionactivities on the Site, as necessary and in accordance with the plans, Drawings, Specificationand all relevant standards Upon completion of the Works, the site will be cleaned as necessary
to ensure the smooth execution of other construction activities
4 RESPONSIBILITIES
Acting as the main technical adviser on a construction site for FOTL, crafts people andoperatives
Manage project on time and under budget
Ensuring that all materials used and work performed are as per specifications;
Overseeing the selection and requisition of materials and plant;
Agreeing a price for materials, and making cost-effective solutions and proposals for theintended project;
Managing, monitoring and interpreting the contract design documents supplied by theengineer/ architect;
Liaising with engineers and their representatives(architects, engineers and surveyors),including attending regular meetings to keep them informed of progress;
Daily management of the site, including supervising and monitoring the site labor force andthe work of FOTL;
Planning the work and efficiently organizing the plant and site facilities in order to meetagreed deadlines;
Trang 4 Overseeing quality control, HSE matters on site;
Preparing regular reports as required;
Resolving any unexpected technical difficulties and other problems that may arise
The site manager has overall management and control of the building site and shouldensure that:
The building construction is in accordance with the project schedule
A traffic management plan is developed and implemented(which includes safeaccess/egress points and delivery areas)
A marking plan has been submitted
A delivery schedule submitted by the fabricator is agreed upon
The activities of all contractors are being coordinated and supervised
The ground surface or supporting structure is suitable for plant (such as EWP, mobilescaffolds and cranes) to operate safely
Holding-down bolts, cast in concrete footing, pedestals or slabs, are within tolerance
Shop drawings (prepared by the shop detailer)
Have a signed statement from the structural design engineer that the shop drawingscomply with the structural design
The erection engineer provides clear advice on how to achieve stability for each stage
of the structure’s erection
Weather conditions are continually monitored, particularly potentially hazardous situationslike high or strong winds and electrical storms, and that a contingency plan has beendeveloped for severe weather
At least one of the erection crew or another person who remains on site throughout
erection should hold a current qualification as a level 2 first aider
A safe work method statement has been developed and work is under taken in
accordance with the SWMS
Site manager must also provide to contractors a detailed site plan, which
Includes information on:
Overseeing quality control, HSE matters on site;
Preparing regular reports as required;
Resolving any unexpected technical difficulties and other problems that may arise
The site manager has overall management and control of the building site and shouldensure that:
The building construction is in accordance with the project schedule
A traffic management plan is developed and implemented(which includes safeaccess/egress points and delivery areas)
A marking plan has been submitted
A delivery schedule submitted by the fabricator is agreed upon
The activities of all contractors are being coordinated and supervised
The ground surface or supporting structure is suitable for plant (such as EWP, mobilescaffolds and cranes) to operate safely
Holding-down bolts, cast in concrete footing, pedestals or slabs, are within tolerance
Shop drawings (prepared by the shop detailer)
Have a signed statement from the structural design engineer that the shop drawingscomply with the structural design
The erection engineer provides clear advice on how to achieve stability for each stage
of the structure’s erection
Weather conditions are continually monitored, particularly potentially hazardous situationslike high or strong winds and electrical storms, and that a contingency plan has beendeveloped for severe weather
At least one of the erection crew or another person who remains on site throughout
erection should hold a current qualification as a level 2 first aider
A safe work method statement has been developed and work is under taken in
accordance with the SWMS
Site manager must also provide to contractors a detailed site plan, which
Includes information on:
Overseeing quality control, HSE matters on site;
Preparing regular reports as required;
Resolving any unexpected technical difficulties and other problems that may arise
The site manager has overall management and control of the building site and shouldensure that:
The building construction is in accordance with the project schedule
A traffic management plan is developed and implemented(which includes safeaccess/egress points and delivery areas)
A marking plan has been submitted
A delivery schedule submitted by the fabricator is agreed upon
The activities of all contractors are being coordinated and supervised
The ground surface or supporting structure is suitable for plant (such as EWP, mobilescaffolds and cranes) to operate safely
Holding-down bolts, cast in concrete footing, pedestals or slabs, are within tolerance
Shop drawings (prepared by the shop detailer)
Have a signed statement from the structural design engineer that the shop drawingscomply with the structural design
The erection engineer provides clear advice on how to achieve stability for each stage
of the structure’s erection
Weather conditions are continually monitored, particularly potentially hazardous situationslike high or strong winds and electrical storms, and that a contingency plan has beendeveloped for severe weather
At least one of the erection crew or another person who remains on site throughout
erection should hold a current qualification as a level 2 first aider
A safe work method statement has been developed and work is under taken in
accordance with the SWMS
Site manager must also provide to contractors a detailed site plan, which
Includes information on:
Trang 5 The site manager should ensure that the accuracy of each contractor’s work is within thetolerance of the level or position nominated by the erection engineer or relevant standard.Any modifications to the building layout also need to be checked by site manager forapproval by the erection engineer.
The erection engineer approves the sequential erection procedure which includes how thestructure is stabilized at each stage and signs any modifications, and is required to provideguidance to the builder and erection crew on matters including:
Joints and additional erection cleats
Structural design criteria affecting construction
Temporary bracing
Lifting points
Loads and conditions likely to be experienced during the lifting and erection
Any wind load limit actions on the integrity of the structure as it is being erected
according to the signed-off sequential erection procedure
Wind load on the braced members
A point positions (as they affect erection sequences)
Accessibility of connections
Fixings for working platforms, hand rails etc
Preferred method of connecting steel members
Preferred type and number of cranes to erect members of particular size and shape, andfor vertical and horizontal bracing requirements
Instructions on how to stabilize the structure at each stage of erection which involves:
- Verifying the adequacy of the base connections (steel to foundations)
- Checking stability under construction load conditions
Capacity to withstand accidental vehicle impact
4.2.4 Erector
The erector ensures that:
the structure is erected in accordance with the sequential erection procedure
an SWMS is developed in consultation with the erection crew
work proceeds in accordance with the SWMS
Confirms with the builder’s representative that the ground or supporting surface issuitable for mobile plant to safely operate
Pre-assembly of members and the movement and location of heavy members areconsidered prior to installation
Weather conditions are continually monitored, and in particular, potentially hazardous
The site manager should ensure that the accuracy of each contractor’s work is within thetolerance of the level or position nominated by the erection engineer or relevant standard.Any modifications to the building layout also need to be checked by site manager forapproval by the erection engineer
The erection engineer approves the sequential erection procedure which includes how thestructure is stabilized at each stage and signs any modifications, and is required to provideguidance to the builder and erection crew on matters including:
Joints and additional erection cleats
Structural design criteria affecting construction
Temporary bracing
Lifting points
Loads and conditions likely to be experienced during the lifting and erection
Any wind load limit actions on the integrity of the structure as it is being erected
according to the signed-off sequential erection procedure
Wind load on the braced members
A point positions (as they affect erection sequences)
Accessibility of connections
Fixings for working platforms, hand rails etc
Preferred method of connecting steel members
Preferred type and number of cranes to erect members of particular size and shape, andfor vertical and horizontal bracing requirements
Instructions on how to stabilize the structure at each stage of erection which involves:
- Verifying the adequacy of the base connections (steel to foundations)
- Checking stability under construction load conditions
Capacity to withstand accidental vehicle impact
4.2.4 Erector
The erector ensures that:
the structure is erected in accordance with the sequential erection procedure
an SWMS is developed in consultation with the erection crew
work proceeds in accordance with the SWMS
Confirms with the builder’s representative that the ground or supporting surface issuitable for mobile plant to safely operate
Pre-assembly of members and the movement and location of heavy members areconsidered prior to installation
Weather conditions are continually monitored, and in particular, potentially hazardous
The site manager should ensure that the accuracy of each contractor’s work is within thetolerance of the level or position nominated by the erection engineer or relevant standard.Any modifications to the building layout also need to be checked by site manager forapproval by the erection engineer
The erection engineer approves the sequential erection procedure which includes how thestructure is stabilized at each stage and signs any modifications, and is required to provideguidance to the builder and erection crew on matters including:
Joints and additional erection cleats
Structural design criteria affecting construction
Temporary bracing
Lifting points
Loads and conditions likely to be experienced during the lifting and erection
Any wind load limit actions on the integrity of the structure as it is being erected
according to the signed-off sequential erection procedure
Wind load on the braced members
A point positions (as they affect erection sequences)
Accessibility of connections
Fixings for working platforms, hand rails etc
Preferred method of connecting steel members
Preferred type and number of cranes to erect members of particular size and shape, andfor vertical and horizontal bracing requirements
Instructions on how to stabilize the structure at each stage of erection which involves:
- Verifying the adequacy of the base connections (steel to foundations)
- Checking stability under construction load conditions
Capacity to withstand accidental vehicle impact
4.2.4 Erector
The erector ensures that:
the structure is erected in accordance with the sequential erection procedure
an SWMS is developed in consultation with the erection crew
work proceeds in accordance with the SWMS
Confirms with the builder’s representative that the ground or supporting surface issuitable for mobile plant to safely operate
Pre-assembly of members and the movement and location of heavy members areconsidered prior to installation
Weather conditions are continually monitored, and in particular, potentially hazardous
Trang 6situations like high or strong winds and electrical storms for which a contingency planshould be developed and implemented
4.2.5 Erection crew
An erection crew consists of:
an experienced structural steel supervisor
rigger
digger
Flagman
Crane operator
The erection supervisor is responsible for directing and coordinating the agreed
sequential erection procedure They should hold a high risk work license for rigging ineither the Intermediate Rigging or Advanced Rigging classes
The crane operator must hold a license to perform high risk work appropriate for the type
of crane and, in the case of a slewing mobile crane, the crane’s capacity (WLL) (or beunder the direct supervision of the holder of the appropriate license)
The size and make-up of the remainder of the erection crew will vary depending uponthe nature of the site and the particular circum stances All members of the crew musthold the basic rigging license as a minimum Anyone who is being trained, in order toobtain a license, must be directly supervised to ensure that the work is carried outsafely
4.2.6 HSSE Manager
Main responsibilities are to:
Assist in implementation of and reporting on compliance with HSSE management plan
Advise Management on preventing injury to personnel and damage to plant andequipment
Public HSE issues especially Traffic Management & construction interface with publicareas
Further improvement in existing sound working methods
Legal requirements affecting HSE
Provision and use of protective clothing and equipment
Potential hazards on new contacts before work starts and on the site HSE organization
Feedback on new policy or procedures adopted
Methods of safe working arising from new developments
Carry on out site surveys, in association with the Section Manager, Engineer orSupervisor, to see that only safe methods or working are in operation; that all regulationsare being observed;
Determine that cause of any accident or dangerous occurrence and recommend means ofpreventing reoccurrence;
situations like high or strong winds and electrical storms for which a contingency planshould be developed and implemented
4.2.5 Erection crew
An erection crew consists of:
an experienced structural steel supervisor
rigger
digger
Flagman
Crane operator
The erection supervisor is responsible for directing and coordinating the agreed
sequential erection procedure They should hold a high risk work license for rigging ineither the Intermediate Rigging or Advanced Rigging classes
The crane operator must hold a license to perform high risk work appropriate for the type
of crane and, in the case of a slewing mobile crane, the crane’s capacity (WLL) (or beunder the direct supervision of the holder of the appropriate license)
The size and make-up of the remainder of the erection crew will vary depending uponthe nature of the site and the particular circum stances All members of the crew musthold the basic rigging license as a minimum Anyone who is being trained, in order toobtain a license, must be directly supervised to ensure that the work is carried outsafely
4.2.6 HSSE Manager
Main responsibilities are to:
Assist in implementation of and reporting on compliance with HSSE management plan
Advise Management on preventing injury to personnel and damage to plant andequipment
Public HSE issues especially Traffic Management & construction interface with publicareas
Further improvement in existing sound working methods
Legal requirements affecting HSE
Provision and use of protective clothing and equipment
Potential hazards on new contacts before work starts and on the site HSE organization
Feedback on new policy or procedures adopted
Methods of safe working arising from new developments
Carry on out site surveys, in association with the Section Manager, Engineer orSupervisor, to see that only safe methods or working are in operation; that all regulationsare being observed;
Determine that cause of any accident or dangerous occurrence and recommend means ofpreventing reoccurrence;
situations like high or strong winds and electrical storms for which a contingency planshould be developed and implemented
4.2.5 Erection crew
An erection crew consists of:
an experienced structural steel supervisor
rigger
digger
Flagman
Crane operator
The erection supervisor is responsible for directing and coordinating the agreed
sequential erection procedure They should hold a high risk work license for rigging ineither the Intermediate Rigging or Advanced Rigging classes
The crane operator must hold a license to perform high risk work appropriate for the type
of crane and, in the case of a slewing mobile crane, the crane’s capacity (WLL) (or beunder the direct supervision of the holder of the appropriate license)
The size and make-up of the remainder of the erection crew will vary depending uponthe nature of the site and the particular circum stances All members of the crew musthold the basic rigging license as a minimum Anyone who is being trained, in order toobtain a license, must be directly supervised to ensure that the work is carried outsafely
4.2.6 HSSE Manager
Main responsibilities are to:
Assist in implementation of and reporting on compliance with HSSE management plan
Advise Management on preventing injury to personnel and damage to plant andequipment
Public HSE issues especially Traffic Management & construction interface with publicareas
Further improvement in existing sound working methods
Legal requirements affecting HSE
Provision and use of protective clothing and equipment
Potential hazards on new contacts before work starts and on the site HSE organization
Feedback on new policy or procedures adopted
Methods of safe working arising from new developments
Carry on out site surveys, in association with the Section Manager, Engineer orSupervisor, to see that only safe methods or working are in operation; that all regulationsare being observed;
Determine that cause of any accident or dangerous occurrence and recommend means ofpreventing reoccurrence;
Trang 7 Supervise the recording and analysis of information on injuries, damage and loss, assessaccident trends and review overall HSE performances;
Assist with training for all levels of engineers on safety;
Promote awareness of injury prevention and damage control to all levels of engineers;
Keep contact with officials and professional bodies;
Maintain records of certification of operatives and plant
4.2.7 HSSE Supervisor
Attend pre-job START meetings and Provide HSSE input as required
HSE Staff to worker 1:50
ISOS Approved First Aider / worker 1:50
His role and responsibilities are to:
Assist the HSSE Management
Ensure the HSE Supervisors are carrying out their tasks in an efficient manner as directed
Patrol the Site as frequently as possible, and inspect current activities and workingconditions
Advise the Construction Manager and Discipline Supervisor of any unsafe conditions orviolations and remedial action required including immediate stoppage of activity
Attend Site Inspection and Audits as required
Attend HSSE Meetings as required
Report daily to HSSEM on any HSE issues
Chair and document weekly QC meetings with the superintendent and provide writtenminutes as described in project specific contract documents
Provide written daily QC reports that reinforce activities that are being constructed inconformance with each specific project's established standard and constructively confrontsnon-conformances to produce the desired outcome in a timely manner
Conduct preparatory, initial and follow-up meetings to establish an understanding of thestandards of care desired for each definable feature of work Verify that checklists are
Supervise the recording and analysis of information on injuries, damage and loss, assessaccident trends and review overall HSE performances;
Assist with training for all levels of engineers on safety;
Promote awareness of injury prevention and damage control to all levels of engineers;
Keep contact with officials and professional bodies;
Maintain records of certification of operatives and plant
4.2.7 HSSE Supervisor
Attend pre-job START meetings and Provide HSSE input as required
HSE Staff to worker 1:50
ISOS Approved First Aider / worker 1:50
His role and responsibilities are to:
Assist the HSSE Management
Ensure the HSE Supervisors are carrying out their tasks in an efficient manner as directed
Patrol the Site as frequently as possible, and inspect current activities and workingconditions
Advise the Construction Manager and Discipline Supervisor of any unsafe conditions orviolations and remedial action required including immediate stoppage of activity
Attend Site Inspection and Audits as required
Attend HSSE Meetings as required
Report daily to HSSEM on any HSE issues
Chair and document weekly QC meetings with the superintendent and provide writtenminutes as described in project specific contract documents
Provide written daily QC reports that reinforce activities that are being constructed inconformance with each specific project's established standard and constructively confrontsnon-conformances to produce the desired outcome in a timely manner
Conduct preparatory, initial and follow-up meetings to establish an understanding of thestandards of care desired for each definable feature of work Verify that checklists are
Supervise the recording and analysis of information on injuries, damage and loss, assessaccident trends and review overall HSE performances;
Assist with training for all levels of engineers on safety;
Promote awareness of injury prevention and damage control to all levels of engineers;
Keep contact with officials and professional bodies;
Maintain records of certification of operatives and plant
4.2.7 HSSE Supervisor
Attend pre-job START meetings and Provide HSSE input as required
HSE Staff to worker 1:50
ISOS Approved First Aider / worker 1:50
His role and responsibilities are to:
Assist the HSSE Management
Ensure the HSE Supervisors are carrying out their tasks in an efficient manner as directed
Patrol the Site as frequently as possible, and inspect current activities and workingconditions
Advise the Construction Manager and Discipline Supervisor of any unsafe conditions orviolations and remedial action required including immediate stoppage of activity
Attend Site Inspection and Audits as required
Attend HSSE Meetings as required
Report daily to HSSEM on any HSE issues
Chair and document weekly QC meetings with the superintendent and provide writtenminutes as described in project specific contract documents
Provide written daily QC reports that reinforce activities that are being constructed inconformance with each specific project's established standard and constructively confrontsnon-conformances to produce the desired outcome in a timely manner
Conduct preparatory, initial and follow-up meetings to establish an understanding of thestandards of care desired for each definable feature of work Verify that checklists are
Trang 8being used and signed off prior to the placement of concrete, steel and other similar items
of work
Verify and document that all materials received for the project are in conformance with theapproved submittal, are handled and stored appropriately and are acceptable for use inthe project
Conduct preconstruction meetings with new and existing superintendent at least two daysprior to the start of each new phase of the work to discuss issues that affect quality.Document these meetings in the daily QC report and preparatory phase report
Schedule, document the results of, and maintain a log of all code and independentinspections that are required Clearly document, correct and re-inspect all non-conformances prior to covering up work
Conduct periodic follow-up inspections to verify that work is proceeding with the contractdocuments and the approved submittals (Desired results come from what is inspected,not what is expected.)
Coordinate and document the testing and commissioning of building systems
Document and distribute pre-punch lists, punch lists and the completion of these lists
Document final inspections, certificates of occupancy and acceptance of the works andvarious phases thereof
Maintain the project "as-built" drawings on a daily basis
The construction Plan shall consider all physical, environmental and social conditionsprevalent at the work site handover
All temporary buildings and facilities shall be tidy and clean, and be subject to inspection
by the safety and security groups
Temporary buildings not contain any explosives without specific written approval from theHSE manager
4.2.10 Insurance
FOTL shall be responsible for own worker Compensation Vehicle and third party liabilitiesaccording to the statutory regulations of the other insurances as designated in thecontract
The copies of the insurance certification shall be submitted prior to starting work
Documentation
The following reports, information and documentation shall be timely submitted to HSSEoffice
Weekly and Monthly Manpower reports
Safety Training Reports
Personnel Data and required information
being used and signed off prior to the placement of concrete, steel and other similar items
of work
Verify and document that all materials received for the project are in conformance with theapproved submittal, are handled and stored appropriately and are acceptable for use inthe project
Conduct preconstruction meetings with new and existing superintendent at least two daysprior to the start of each new phase of the work to discuss issues that affect quality.Document these meetings in the daily QC report and preparatory phase report
Schedule, document the results of, and maintain a log of all code and independentinspections that are required Clearly document, correct and re-inspect all non-conformances prior to covering up work
Conduct periodic follow-up inspections to verify that work is proceeding with the contractdocuments and the approved submittals (Desired results come from what is inspected,not what is expected.)
Coordinate and document the testing and commissioning of building systems
Document and distribute pre-punch lists, punch lists and the completion of these lists
Document final inspections, certificates of occupancy and acceptance of the works andvarious phases thereof
Maintain the project "as-built" drawings on a daily basis
The construction Plan shall consider all physical, environmental and social conditionsprevalent at the work site handover
All temporary buildings and facilities shall be tidy and clean, and be subject to inspection
by the safety and security groups
Temporary buildings not contain any explosives without specific written approval from theHSE manager
4.2.10 Insurance
FOTL shall be responsible for own worker Compensation Vehicle and third party liabilitiesaccording to the statutory regulations of the other insurances as designated in thecontract
The copies of the insurance certification shall be submitted prior to starting work
Documentation
The following reports, information and documentation shall be timely submitted to HSSEoffice
Weekly and Monthly Manpower reports
Safety Training Reports
Personnel Data and required information
being used and signed off prior to the placement of concrete, steel and other similar items
of work
Verify and document that all materials received for the project are in conformance with theapproved submittal, are handled and stored appropriately and are acceptable for use inthe project
Conduct preconstruction meetings with new and existing superintendent at least two daysprior to the start of each new phase of the work to discuss issues that affect quality.Document these meetings in the daily QC report and preparatory phase report
Schedule, document the results of, and maintain a log of all code and independentinspections that are required Clearly document, correct and re-inspect all non-conformances prior to covering up work
Conduct periodic follow-up inspections to verify that work is proceeding with the contractdocuments and the approved submittals (Desired results come from what is inspected,not what is expected.)
Coordinate and document the testing and commissioning of building systems
Document and distribute pre-punch lists, punch lists and the completion of these lists
Document final inspections, certificates of occupancy and acceptance of the works andvarious phases thereof
Maintain the project "as-built" drawings on a daily basis
The construction Plan shall consider all physical, environmental and social conditionsprevalent at the work site handover
All temporary buildings and facilities shall be tidy and clean, and be subject to inspection
by the safety and security groups
Temporary buildings not contain any explosives without specific written approval from theHSE manager
4.2.10 Insurance
FOTL shall be responsible for own worker Compensation Vehicle and third party liabilitiesaccording to the statutory regulations of the other insurances as designated in thecontract
The copies of the insurance certification shall be submitted prior to starting work
Documentation
The following reports, information and documentation shall be timely submitted to HSSEoffice
Weekly and Monthly Manpower reports
Safety Training Reports
Personnel Data and required information
Trang 9 List of Engineers / Workers
Construction Equipment Log books
Equipment Inspection & Maintenance Records
Accident / Incident / Near-Miss Report
Hazardous Material Storage and Handling records
Material Safety Data Sheet (MSDS)
Work Permit Record
Housekeeping and Waste Disposal records
Monthly Safety Report
Insurance Certificates
5 EXECUTTION SEQUENCE
5.1 Unloading
Materials were shipped to job site separately or on the skid put in container
They are unloaded by crane of worker manually up to the material properties
The average load of trucks carried materials is about 40 ton, this load is also the safetyworking load of crane 20 ton Therefore, the temporary road in the job site must be preparedproperly for crane and trucks working
Before unloading materials out of trucks or containers, it is required to take pictures of realmaterial status delivered to jobsite
5.2 Checking
List of Engineers / Workers
Construction Equipment Log books
Equipment Inspection & Maintenance Records
Accident / Incident / Near-Miss Report
Hazardous Material Storage and Handling records
Material Safety Data Sheet (MSDS)
Work Permit Record
Housekeeping and Waste Disposal records
Monthly Safety Report
Insurance Certificates
5 EXECUTTION SEQUENCE
5.1 Unloading
Materials were shipped to job site separately or on the skid put in container
They are unloaded by crane of worker manually up to the material properties
The average load of trucks carried materials is about 40 ton, this load is also the safetyworking load of crane 20 ton Therefore, the temporary road in the job site must be preparedproperly for crane and trucks working
Before unloading materials out of trucks or containers, it is required to take pictures of realmaterial status delivered to jobsite
5.2 Checking
List of Engineers / Workers
Construction Equipment Log books
Equipment Inspection & Maintenance Records
Accident / Incident / Near-Miss Report
Hazardous Material Storage and Handling records
Material Safety Data Sheet (MSDS)
Work Permit Record
Housekeeping and Waste Disposal records
Monthly Safety Report
Insurance Certificates
5 EXECUTTION SEQUENCE
5.1 Unloading
Materials were shipped to job site separately or on the skid put in container
They are unloaded by crane of worker manually up to the material properties
The average load of trucks carried materials is about 40 ton, this load is also the safetyworking load of crane 20 ton Therefore, the temporary road in the job site must be preparedproperly for crane and trucks working
Before unloading materials out of trucks or containers, it is required to take pictures of realmaterial status delivered to jobsite
5.2 Checking
Trang 10(1) Quantities, dimensions of the panel, including bolts together with the associatedfastener and gratings with fasteners which are delivered to FOTL, shall be checked inaccordance with the drawings, packing list, and applicable documents.
(2) If panel are found to have any defects, bends or distortions from the required shapeafter transportation, they shall be corrected and repaired
(3) Damaged panel shall be reported in writing to HBP’s engineer
5.3 Materials arrangement
To avoid materials being moved so much on jobsite that might cause unexpected
damages of paint, shapes, when material delved to job site, they must be unloaded and
arranged closed to the designed erection point Up to the materials shall be stacked in
locations according to the building/areas, should be near to the lifting position adjacent tothe area to be erected This is to facilitate the sorting and delivery during the erection Theconditions of each job site, the material arrangement plan may different but in generally,
materials will be arranges as following principle to ease moving, combination and erectionafter
Leave 01 end open for erection machinethough out erection period
(1) Quantities, dimensions of the panel, including bolts together with the associatedfastener and gratings with fasteners which are delivered to FOTL, shall be checked inaccordance with the drawings, packing list, and applicable documents
(2) If panel are found to have any defects, bends or distortions from the required shapeafter transportation, they shall be corrected and repaired
(3) Damaged panel shall be reported in writing to HBP’s engineer
5.3 Materials arrangement
To avoid materials being moved so much on jobsite that might cause unexpected
damages of paint, shapes, when material delved to job site, they must be unloaded and
arranged closed to the designed erection point Up to the materials shall be stacked in
locations according to the building/areas, should be near to the lifting position adjacent tothe area to be erected This is to facilitate the sorting and delivery during the erection Theconditions of each job site, the material arrangement plan may different but in generally,
materials will be arranges as following principle to ease moving, combination and erectionafter
Leave 01 end open for erection machinethough out erection period
(1) Quantities, dimensions of the panel, including bolts together with the associatedfastener and gratings with fasteners which are delivered to FOTL, shall be checked inaccordance with the drawings, packing list, and applicable documents
(2) If panel are found to have any defects, bends or distortions from the required shapeafter transportation, they shall be corrected and repaired
(3) Damaged panel shall be reported in writing to HBP’s engineer
5.3 Materials arrangement
To avoid materials being moved so much on jobsite that might cause unexpected
damages of paint, shapes, when material delved to job site, they must be unloaded and
arranged closed to the designed erection point Up to the materials shall be stacked in
locations according to the building/areas, should be near to the lifting position adjacent tothe area to be erected This is to facilitate the sorting and delivery during the erection Theconditions of each job site, the material arrangement plan may different but in generally,
materials will be arranges as following principle to ease moving, combination and erectionafter
Leave 01 end open for erection machinethough out erection period
Trang 116 PANEL INSTALLATION
6.1 ROOFING
6.1.1 Preparation
Before sheeting, all the tasks below must be completed:
- The Period Completion Report of mainframes must be approved and signed off byHBP’Engineer
- All column base plates must be filled grouting strong enough for support loading
- Frames must be completed painting touch up and checked
- Safety net was installed below right after completion of all purlins
6.1.2 Complete Sag rod
- After installation of safety net, workers will push the chanels, which put across
purlins along purlins for sag rod installation
- PPE will be attached to purlins for safety
6.1.3 Lifting roof sheet:
Roof sheet will be lifted on to the roof by crane or
manually by workers.
6.1 ROOFING
6.1.1 Preparation
Before sheeting, all the tasks below must be completed:
- The Period Completion Report of mainframes must be approved and signed off byHBP’Engineer
- All column base plates must be filled grouting strong enough for support loading
- Frames must be completed painting touch up and checked
- Safety net was installed below right after completion of all purlins
6.1.2 Complete Sag rod
- After installation of safety net, workers will push the chanels, which put across
purlins along purlins for sag rod installation
- PPE will be attached to purlins for safety
6.1.3 Lifting roof sheet:
Roof sheet will be lifted on to the roof by crane or
manually by workers.
6.1 ROOFING
6.1.1 Preparation
Before sheeting, all the tasks below must be completed:
- The Period Completion Report of mainframes must be approved and signed off byHBP’Engineer
- All column base plates must be filled grouting strong enough for support loading
- Frames must be completed painting touch up and checked
- Safety net was installed below right after completion of all purlins
6.1.2 Complete Sag rod
- After installation of safety net, workers will push the chanels, which put across
purlins along purlins for sag rod installation
- PPE will be attached to purlins for safety
6.1.3 Lifting roof sheet:
Roof sheet will be lifted on to the roof by crane or
manually by workers.
Trang 12(a) Lifting by crane
- Roof sheets will be piled up to set of 10 sheets then being tied together by soft
ropes at space maximum =4m
- With roof sheet length <25m , 01 crane was applied
- With roof sheet length >25m , 02 cranes was applied
- The spreader bars will be applied for lifting purpose
- The lifted roof sheets will be arranged to adjacent bays, pilled, and tied carefully topurlins until being installed
(b) Lifting manually by workers
- Roof sheet will be moved to right
position and pulled sheet by sheet
on to the roof by workers sitting on
the rafter with PPE attached to
static lines
- Roof sheets lifted on to the roof will
be arranged to adjacent bays, pilled
<400 0
<400 0
<400 0
<400 0
<400 0
<400 0
<400 0
Lif e lin e
B
(a) Lifting by crane
- Roof sheets will be piled up to set of 10 sheets then being tied together by soft
ropes at space maximum =4m
- With roof sheet length <25m , 01 crane was applied
- With roof sheet length >25m , 02 cranes was applied
- The spreader bars will be applied for lifting purpose
- The lifted roof sheets will be arranged to adjacent bays, pilled, and tied carefully topurlins until being installed
(b) Lifting manually by workers
- Roof sheet will be moved to right
position and pulled sheet by sheet
on to the roof by workers sitting on
the rafter with PPE attached to
static lines
- Roof sheets lifted on to the roof will
be arranged to adjacent bays, pilled
<400 0
<400 0
<400 0
<400 0
<400 0
<400 0
<400 0
Lif e lin e
B
(a) Lifting by crane
- Roof sheets will be piled up to set of 10 sheets then being tied together by soft
ropes at space maximum =4m
- With roof sheet length <25m , 01 crane was applied
- With roof sheet length >25m , 02 cranes was applied
- The spreader bars will be applied for lifting purpose
- The lifted roof sheets will be arranged to adjacent bays, pilled, and tied carefully topurlins until being installed
(b) Lifting manually by workers
- Roof sheet will be moved to right
position and pulled sheet by sheet
on to the roof by workers sitting on
the rafter with PPE attached to
static lines
- Roof sheets lifted on to the roof will
be arranged to adjacent bays, pilled
<400 0
<400 0
<400 0
<400 0
<400 0
<400 0
<400 0
Lif e lin e
B
Trang 13and tied safely to purlins before
installation
6.1.4 Install roof sheets
- Roof sheets which are waiting for installation will be tied to purlins by ropes
- Before install roof sheet, safety net was installed for safety reason
- Roof sheet must be installed by only 01 way from predetermined end gable of the
building ,this end gable should be closed to the rolling machine of position of fabricatedroof sheet to avoid moving too much , this might cause damages to them
- Roof sheet will be installed one by one manually by workers
- Roof sheet will be attached to purlins by screws while KSS600 by clips and seamingafter completing checking
- All the accessories related to installation sheeting and the order of installation will becomplied as sketch below
B : Kirby peak panel
Steel line Sidewall
6.1.4 Install roof sheets
- Roof sheets which are waiting for installation will be tied to purlins by ropes
- Before install roof sheet, safety net was installed for safety reason
- Roof sheet must be installed by only 01 way from predetermined end gable of the
building ,this end gable should be closed to the rolling machine of position of fabricatedroof sheet to avoid moving too much , this might cause damages to them
- Roof sheet will be installed one by one manually by workers
- Roof sheet will be attached to purlins by screws while KSS600 by clips and seamingafter completing checking
- All the accessories related to installation sheeting and the order of installation will becomplied as sketch below
B : Kirby peak panel
Steel line Sidewall
6.1.4 Install roof sheets
- Roof sheets which are waiting for installation will be tied to purlins by ropes
- Before install roof sheet, safety net was installed for safety reason
- Roof sheet must be installed by only 01 way from predetermined end gable of the
building ,this end gable should be closed to the rolling machine of position of fabricatedroof sheet to avoid moving too much , this might cause damages to them
- Roof sheet will be installed one by one manually by workers
- Roof sheet will be attached to purlins by screws while KSS600 by clips and seamingafter completing checking
- All the accessories related to installation sheeting and the order of installation will becomplied as sketch below
B : Kirby peak panel
Steel line Sidewall