METHOD STATEMENT Noi Bai – Lao Cai Highway Project Package A1 Km 0 080 ~ 26+700 Traffic Control Plan POS TCP B1 EN TRAFFIC CONTROL PLAN Table of Contents 3I GENERAL, CONTENTS AND ORGANIZATION CHART 1[.]
Trang 1TRAFFIC CONTROL PLAN
Trang 2Table of Contents
I GENERAL, CONTENTS AND ORGANIZATION CHART ……… 3
1 General and Content……… ……… ….4
2 Oganization Chart……… ………4
II PROPOSED FOR GENERAL TRAFFIC CONTROL………… ……… …5
1 Work for Traffic Control 5
2 Materials for Traffic Control Devices 5
3 Maintanace of Equipment and Devices fot Traffic Control 6
4 Traffic Control During Non-Working Hours 6
5 Traffic Control During Night-time 6
6 Traffic Control Conserving Existing Traffic 6
7 Number of lanes for Traffic Control 7
8 Vertical Clearance 7
9 Line of Communication, Interaction & Communication Procedure……… 7
III SUBMISSION, APPROVAL AND CHANGE OF TRAFFIC CONTROL PLAN 8
IV CONTRACTOR'S TRAFFIC SUPERVISOR ……… ……… 9
V TRAFFIC CONTROL PLAN (TCP) FOR EACH STATION ……….……… 9
1 TRAFFIC CONTROL PLAN (TCP) FOR STATION NH2B BRIDGE AND INTERCHANGE #4, FROM KM 24+550 TO KM 26+700……… 10
2 TRAFFIC CONTROL PLAN (TCP) FOR STATION INTERCHANE#3, BA THIEN BRIDGE FROM KM 13+300 TO KM 14+700……… 13
3 TRAFFIC CONTROL PLAN (TCP) FOR STATION TAN LOI BRIDGE KM 10+695 TO KM 10+700……….………16
4 TRAFFIC CONTROL PLAN (TCP) FOR STATION TAM LONG - THIEN KE BRIDGE KM 19+ 120……… …… 18
5.TRAFFIC CONTROL PLAN (TCP) FOR STATION DAI DUONG, XUAN PHUONG, NGUYEN TAT THANH BRIDGES FROM KM 7+ 376 TO 7+ 854……… … 20
6 DRAWING OF BRIDGES AND SIGN BOARDS WILL INSTALL AT
CONSTRUCTION SITE (Attached)
VI THE LIST EXISTING ROADS INVESTIGATION: MAKING AND PICTURES
(Attached)
VII THE LIST OF BOX CULVERTS IN PAKAGE A1 ( Attached)
Trang 3
I GENERAL, CONTENTS AND ORGANIZATION CHART
1 General and Contents
This General Traffic Control Plan shall be read in order to describe clearer Contractor’splanning of traffic control during construction period and shall be read in conjunctionwith all the relevant tender documents Volume 2 – Section 01600 It shall be revised toallow for modifications based on actual physical site conditions during constructionstage
This Plan is prepared for the treatment of public traffic on exiting road that shall beaffected by the construction of the project and in order to maintain traffic safety as well
as avoiding excessive delay of public traffic on existing road of 19 bridges, 3interchanges and 1 underpass of Package A1 from Km 0-080 ~ 26+700
The Contractor shall be responsible for carrying out any necessary investigations andobtaining approvals, licenses, escorts and any other necessary facilities in order toenable extraordinary traffic to be moved on the roads in the Project area
Before the application of the measures for traffic maintenance and protection contained
in the “General Traffic Control Plan” described below, the Contractor shall investigateand clarify sufficiently the details and regulations established by local authorities andpertinent divisions of the Vietnam Road and Railroad Traffic Police Department The technical requirements specified in the Vietnamese Standards 22-TCN-237-01
“Road Signs and Signaling Regulations” or National Specifications QCKT / 01 / 2008 /BGTVT shall be applied as the specifications for the work items contained in thisSpecification Section
Traffic control devices and services shall be provided and maintained both inside andoutside the project limits as needed to facilitate traffic guidance should this benecessary such as temporary bridges, temporary roads and diversions All traffictemporary control devices and facilities shall be removed upon completion of theContract
Line communication shall be regular updating between all relation subdivision bymobile phone and daily report system Moreover, the intent of site meeting for trafficcoordination shall be clarified when necessary
All Sub-contractor shall follow Project’s General Traffic Control Plan
Inventory of the affected traffic are road section near site work area The detailedinventory of the affected traffic shall be mention in the specific traffic control plan foreach section in this project
Trang 41) Works for Traffic Control
2) Materials for Traffic Control Devices
3) Maintenance of Equipment and Devices for Traffic Control
4) Traffic Control during Non-Working Hours
5) Traffic Control during Nighttime
6) Traffic Control Conserving Existing Traffic
7) Number of Lanes for Traffic Control
8) Vertical Clearance
2 Organization Chart
The Organization Chart for General Traffic Control Plan will be as follows:
Traffic control works are responsibilities of all relation subdivisions Traffic Controlsupervisor who will be main responsible for all traffic control issues in the site Trafficcontrol supervisor have experience in traffic management and safety management.List key personnel of Traffic Supervisor, Traffic Control Team will submit to Engineerand Client immediately when employed
Traffic Control Team
Project Director
PARK YONG SOO
Construction Manager
LEE SANG DON
Site Engineer Traffic Supervisor
Site Manager
TRINH HUNG THO
NG NGOC BICH
Safety Environmental
LE DINH QUYEN
VU VAN THUY
Trang 5II PROPOSED FOR GENERAL TRAFFIC CONTROL
1 Work for Traffic Control
- Prior to the start of construction operations, based on his approved TrafficControl Plan, the Contractor shall furnish, erect and maintain (at prescribedpoints) warning and guide signs, barricades or barriers, temporary fences (2.0
m height), and other traffic control devices as established in the approvedTraffic Control Plan, the Vietnamese Standards, these specifications or directed
by the Engineer
- As necessary for proper control of traffic, or when/where directed by theEngineer, the Contractor shall furnish and station competent flagmen whosesole duties shall consist of directing the movement of traffic through or aroundthe Works
2 Materials for Traffic Control Devices
- Retro-reflective Material: Sign panels, barricades, cones, vertical panels,and flagged paddles shall have retro-reflective sheeting meeting theminimum requirements for retro-reflective material noted in SpecificationSection 08400 “Road Signs” of the Technical Specifications
- Sign Panels: Sign panels shall conform to Specification Section 08400
“Road Signs” of the Technical Specifications and shall be in orange colorwith black legend (or white with blue)
- Sign Posts: Sign posts shall be fabricated from untreated softwood Signsshall be capable of remaining in position during normal traffic flow andwind conditions
- Barricades: Barricades shall be constructed of wood
- Cones:
+ Cones shall be in accordance with the Vietnamese Standards for “RoadsSign and Signaling Regulations” (Article 91) with a minimum of 60 cm inheight and a broadened base and shall be capable of withstanding impactwithout damage to the cones or vehicles All cones shall be orange/whitecolored and highly visible both in daylight and darkness
+ Cones shall be capable of remaining bright and in position during
normal traffic flow and wind conditions in the area where they are used.Lamps for cones shall be suitable for the purpose
- Temporary Fence: Temporary fence shall be fabricated in panels withtimber framework and galvanized metal panels The panel face towards thetraffic shall be painted
Trang 6- Vertical Panels: Vertical panels shall be constructed of wood
3 Maintenance of Equipment and Devices for General Traffic Control
The equipment and devices provided to satisfy the requirements of thisSpecification Section shall be maintained and kept in good condition of operationall the time
Any equipment or devices that are lost, stolen, destroyed, or deemed unacceptablewhile their use is required on the Project, shall be replaced by at the Contractorexpense Devices for traffic control shall be operated only when necessary
4 Traffic Control during Non-Working Hours
During non-working hours and following the completion of a particularconstruction operation, all warning signs, except those necessary for the safety ofthe public, shall be removed or entirely covered with either metal or plywoodsheeting so that the sign panel will not be visible
5 Traffic Control during Night Time
- Nighttime operation shall be illuminated by a lighting system approved bythe Engineer
- The lighting system shall be positioned and operated to preclude glare
- Incandescent lights will not be permitted
- Retro-reflective sheeting on signs, barricades, and other devices shall bekept clean and in good condition The Contractor shall promptly correctstretches, rips, and tears in the sheeting Retro-reflective sheeting shall have
a maintained retro-reflection
- When applicable, street lighting shall be relocated as necessary to maintainthe same standards of lighting in the course of the Works until new lightingfacilities are put into operation
6 Traffic Control Conserving Existing Traffic
- When the construction is going to affect an existing road (feeder roads orothers) where traffic closing is not permissible, the Contractor shall keepthat open to traffic during the execution of the Works, provided that whenapproved by the Engineer the Contractor may bypass traffic over a detour
- The Contractor shall at all times keep roads and footpaths, affected by hisoperations, free from soil and material spillage and properly repaired at hisexpense if the road is damaged by those operations
- The Contractor shall keep the length of the Project construction areas insuch condition that traffic will be accommodated safely Traffic controldevices and services shall be provided and maintained both inside and
Trang 7outside the Project limits as needed to facilitate traffic guidance should this
be necessary
7 Number of lanes for Traffic Control
The existing number of traffic lanes of the roads that may be affected by theProject must be maintained at all times during the work execution and ifdiversions are provided these must be of the same traffic capacity as the originalroad
The detailed of Temporary road for each section shall be design and submit to the Engineer
8 Vertical Clearance
In general any temporary works placed over roads or diversions used by publictraffic should have a vertical clearance specified by the Vietnamese StandardsTCVN5729-97, TCVN4054-85, 22TCN210-92, TCVN5729-97 and22TCN210-92, as follows:
- Expressways and Highways Class I, II and III at least 4.75 m
- Highways Class IV, V and VI at least 4.50 m
- Rural Roads Class A at least 3.20 m
- Rural Roads Class B at least 2.70 m Where required by the Engineer, the Contractor shall erect and maintain suitableapproved check-gates, fitted with warning signs indicating the vertical clearance
9 Lines of Communication, Interaction & Communication Procedure:
The Communication Lines shall adapt with the actual and physical site condition and tosuit the actual construction work procedure and sequence that shall be carried out at site
It shall be read in order to describe clearer Contractor’s planning of traffic control duringconstruction period and each station However, it shall be subject to further revisionsbased on changes on actual physical site conditions during the construction stage
The Communication shall be made between the local traffic authorities and other related authorized agencies prior to the implementation of the traffic diversion
Traffic control plan approved by each authority shall be distributed to the each related authorities prior to the commencement
The Communication facilities and services shall be provided and maintained both insideand outside the project limits as needed to facilitate traffic guidance All traffic controldevices and facilities shall be removed upon completion of the Contract
Trang 89.1 The Communication Line Chart
The Communication Chart for the implementation of Traffic Control Plan shall be
as follows:
9-2 Related Authorities
The related authorities for the traffic diversion and traffic control are asfollows:
i The Employer - Ministry of Transport
ii The Employer - Project Management Unit iii The Vinh Phuc Transportation Office
iv The Engineer - : HAFICO & APECO,
v Local Police / Traffic Police
vi Highway Maintenance Boardvii Road Management Authorityviii Commune Committee
III SUBMISSION, APPROVAL AND CHANGE OF TRAFFIC CONTROL PLAN (TCP) FOR EACH STATION:
This General Traffic Control Plan used for entire Package A1: include 19 bridges, 3Interchanges, 1 under pass Each Traffic Control Plan, Detour Planning… put a
- PROJECT MANAGEMENT UNIT
- VINH PHUC TRANSPORT OFFICE
THE ENGINEER:HAFICO & APECO LOCAL POLICE/TRAFFIC POLICE HIGHWAY MAINTENANCE BOARD ROAD MANAGEMENT
AUTHORITY COMMUNE COMMITEE
SITE ENGINEER
IMPLEMENTING STAFF
FLAG MAN / TRAFFIC MAN MAINTENANCE WORKER
Trang 9station into practice will submit to Engineer at least One month before start work ofeach station include Inventory of the Affected traffic, existing Road Traffic Plan,Traffic Control Schedule for Each Station.
All the activities related to the Traffic Control shall comply with approved TCP andEngineer’s instruction on traffic control
If the Contractor proposes to change the approved TCP or TS, the Contractor willnotify the Engineer in writing at least seven (7) calendar days prior to any proposedchange Proposed changes are subject to the Engineer’s approval In case theEngineer makes any subsequent recommendation or instructions on the TCP inwriting, the Contractor will revise the TCP accordingly
IV CONTRACTOR’S TRAFFIC SUPERVISOR (TS)
The Contractor shall employ Traffic Supervisors (TS) who shall be under the SafetyDepartment throughout the construction period and these TS shall be entirelyconnected with the safety plan on the site The contractor shall ensure that these TS
is suitably qualified and experienced persons who will be supervise and monitor infull compliance with the Traffic Control Plan
The Contractor’s Traffic Supervisors shall maintain a daily logbook which shall be keep record
of daily traffic safety / control activities Photographs shall be considered as part of the record.
V TRAFFIC CONTROL PLAN (TCP) FOR EACH STATION
In this time, Contractor only submit TCP of Bridges, Interchanges in the land, where already
taken over and these stations will start construction in 2009 Others remain stations will submit to Engineer by January, 2010.
1 TRAFFIC CONTROL PLAN (TCP) FOR STATION NH2B BRIDGE AND INTERCHANGE #4, FROM KM 24+550 TO KM 26+700
2 TRAFFIC CONTROL PLAN (TCP) FOR STATION INTERCHANE#3, BA THIEN BRIDGE FROM KM 13+300 TO KM 14+700
3 TRAFFIC CONTROL PLAN (TCP) FOR STATION TAN LOI BRIDGE KM 10+695 TO KM 10+700
4 TRAFFIC CONTROL PLAN (TCP) FOR STATION TAM LONG - THIEN KE BRIDGE KM 19+ 120
5.TRAFFIC CONTROL PLAN (TCP) FOR STATION DAI DUONG, XUAN PHUONG, NGUYEN TAT THANH BRIDGES FROM KM 7+ 376 TO 7+ 854
6 DRAWING OF BRIDGES AND SIGN BOARDS WILL INSTALL AT CONSTRUCTION SITE
7 THE EXISTING ROADS INVESTIGATION: MAKING AND PICTURES
8 THE LIST OF BOX CULVERTS IN PAKAGE A1
Trang 101 TRAFFIC CONTROL PLAN (TCP) FOR STATION NH2B BRIDGE &
INTERCHANGE # 4 FROM KM 24+550 TO KM 26+700
A PROPOSED ROAD TRAFFIC MANAGEMENT
Overall traffic diversion is shown on the drawing No TCP-1 (Concept of TemporaryRoad) The concept of traffic control management for this project shall be based on twoparts:
- Road Plan of the Construction NH 2B Bridge
- Diversion in two (2) typical construction sites:
+ Embankment Works not along existing public road
1 Step 1: Temporary Road Plan at the NH 2B Bridge
Following to the tender documents, NH 2B Bridge shall be opened by the March 2011 Temporary access road for construction purpose shall be made along the through way from NH 2B ( Old) to NH 2B(New) , Tam Dao, Quang Ha, Dao Tu…as soon as after thecommencement of the works until opening of High way The Temporary road and the Frontage road is shown on the drawing No TCP-1and TCP- 2
Traffic control shall be done by proper devices such as sign, barricade, fence, etc.Those detail plans shall be designed and provided according to actual site condition.Flow Chart on “Sequence of Traffic Connection” is shown as follows:
FLOW CHART SEQUENSE OF TRAFFIC CONNECTION
NH 2B (OLD) AND NH 2B ( NEW)
Borrow Material (Embankment temp’ road
Works)
Tem’ road/ Up to Base
course
NH 2B BRIDGE Construction
Permanent Works
Temp’ road
open to NH 2B
(New)
Trang 112 Step 2: Frontage Road Planning at Interchange # 4 Construction Site ( Km 24+550 To
Km 26+700)
2.1 Embankment Works not along existing public road
There are no existing public road running along the embankment working area fromKm: 24+500 to Km: 26+ 700 Therefore, the temporary frontage road is built along thethrough way for the purpose of construction only
The Contractor shall arrange supervisors to assure for the safety duringconstruction, using, maintenance and protection
2.2 Interchange # 4 Works
During the construction of #4 interchange, the existing road shall be fully diverted asshown on the attached drawing No TCP-1~2 This Frontage road shall be maintainedthrough out construction period except the area affected to the permanent works In thisarea, proposed frontage road shall be modified according to the work
In order to minimize disruption to traffic flows, the Contractor shall enclose the sitewith temporary fence to provide a visual barrier between the work area and adjacenttraffic The movement of men, materials and plant into and out of the barrier area shall
be checked, controlled by flagman or security
Traffic Control Management
In order to comply with requirement of tight working schedule, the following process isbasically proposed as a working sequence All the existing traffic will be diverted to thetemporary road and frontage road through out construction period However, in areawhere the frontage road is crossing the working area, secondary diversion shall beapplied The area and period of this diversion is limited
Sign panels, barricades, cones, vertical panels and other traffic control devices shall beset to ensure safety of traffic at detour roads or at the intersection between existing roadand diversion roads Flagman shall be provided if required
Guide for traffic and regulate the facilities going and coming through the constructionarea shall be provided in conformity with the traffic line
Traffic shall also be instructed in proper manner to ensure construction progress of thesite and absolute safety for the vehicles and people
The following device and facilities shall be prepared to control the traffic in safetymanner and they shall be removed depending on the construction activities on site
a) Various kinds of site boarding shall be set to control the traffic and separatethe traffic road away the construction site
b) The flashing light and warning signs shall be installed to draw the attention
of public
c) Flagman will be provided at road intersection if required
Flow Chart on “Sequence of Construction” is shown as follows: