Plan Drawing of Topographic Survey --- 157 Base Points : point that will be used as a base, GPS Point, Control Point, Construction Point can be a Base Point Control Points : point that
Trang 2IV Plan Drawing of Topographic Survey - 157
Base Point(s) : point that will be used as a base, GPS Point, Control Point,
Construction Point can be a Base Point
Control Point(s) : point that will be used for setting road centerline, pier centerline,
and Construction Point
Construction Point(s): point that will be used for construction works such as bored pile,
substructure, superstructure, bridge surface, and embankmentworks This point will be set out from Control Points
GPS03B, GPS04B, GPS06, GPS07, GPS08 and GPS09
Total Station : a surveying instrument that can measure azimuth angle and
distance
Trang 32) Setting Out Construction Points
3) Field Survey for Construction Work
4) Topographic Survey
The minimum surveying personnel per one team is as bellow:
3 Setting Out of Control Points
3.1 General
Control Points will be used as Base Points for setting out center of road, center of piers,center of structure, and Construction Points Control Points will be set out using GPS Pointsgiven by the Employer And GPS Points themselves are used as Control Points Refer toNetwork of Control Points (See Appendix I)
Control Points newly set will have data of coordinates (N, E) and elevation as well
3.2
Accuracy of Field Survey
Accuracy of the survey work applied shall be accordance with the general specificatios of the contract by the following table:
Construction Surveying and Staking Tolerances
Trang 4slope stake references (b
Note: (a) Center line points are point of curve (PC), point of tangent (PT) and point on curve (POC) (b) Take the cross sections normal to the centerline within ±1 degree (0.02 rad).
be proposed in the report of Control Point Network Survey, if necessary
Trang 5not to be submerged during rainy season
In addition, Control Points will be set on top of each pier after the erection work wasfinished Basically, the structure of Control Points is in accordance with Highway SurveyCodes 22TCN263-2000; however, 4 types of structure as below will be adopted consideringthe ground condition or surroundings
submerged
Trang 610 75
CERAMIC MARKER
200 300
Control Points (Type 4) on top of piers and on the surface of the structures will be set on thecenter of it or on parallel line of that center line Each of the Control Points will be drawn by
Trang 73.3.2 Procedure
Procedure for setting out on land is as follows
1 Reconnaissance, location selection for Control Points
2 Setting out stakes made of wood
3 Confirmation that the sight has no problem with using transit
4 Setting out points (casting concrete or stage erection by block as shown in fig 1)
5 Execute triangulation or traverse survey using Total Station
6 Decision of coordinates for each Control Point
7 Elevation survey
8 Decision of elevation for each Control Point
Procedure for setting out on pier is as follows
Points on pier will be on the centerline of structure
1 In case of the first Control Points setting on pier, or in case of no Control Points on pierare not available, new Control Points will be set out by using 2 original Control Points
2 In case that there is available Control Points on pier, new Control Points will be set byusing that Control Points After that, set the Total Station on the new Control Point, thedistance and angle of the Control Points on land will be used for checking and set thecenterline of structure as base line
In case that Control Points are set after completion of pier erection, it will be confirmed asfollows
by Steel Measuring Tape
far Control Point on centerline of structure, then Control Points among these 2Control Points will be confirmed whether they are on structure centerline or not.c) If the results of a) and b) is good enough, structure centerline will be drawn on thefront and top of nearest pier Right angle direction will be drawn on the top of
Trang 8b) Checking by field survey
Control Points will be checked at once per 6 months or at the time of Engineer’sinstruction by traverse survey and/or triangulation method The period is March andSeptember after rainy season ends The method of survey is same as setting ControlPoints and Control Points on bridge structure will be checked as well
Relaxation of foundation will be checked especially after rain season ends If there is aControl Point that cannot be utilized any more, new Control Point will be set out again
4 Setting Out of Construction Points
4.1 General
Construction Points are utilized for actual construction work such as bored pile, cofferdam,pile cap, pier, superstructure, embankment and work for roads and bridge surface.Construction Points will be set out based from Control Points
4.2 Accuracy of Field Survey
Accuracy for Construction Points is same as those of Control Points
4.3 Setting out Work
4.3.1 Method
Construction Points will be set out from Control Points including GPS Points First of all,Base Line will be set using Control Points and field survey for setting out ConstructionPoints will be executed based on the Base Line using Total Station
During the setting out work for Construction Points, checking will be done as follows.a) Confirmation will be done using other Base Line
Trang 9Location of Construction Points will be selected as the following for each works:
Stiff Ground, and the points where no heavy equipment working during constructionworks Offset points those are used for check piling work, excavation, cofferdam work,pile cap construction, pier erection, and road works will be set out
Bridge Surface Work
Construction Points will be set on the top of girder completed with checking fromControl Points on the ground and on pier
4.3.3 Checking
Construction Points will be checked when using Each Construction Points will be arranged
on a line; therefore, straightness will be checked from any Construction Points Ifdisplacement is found, the Construction Point will not be used, and new Construction Pointwill be set out again
Trang 105 Field Survey for Construction Works
In this section, methods of field survey are stated for each construction works as shown below
5.1 Bridge works
Trang 11Procedure of survey work for bored pile work is as follows.
PILE ARRANGEMENT
LC R-PIER L-PIER FRONT VIEW
PILE ARRANGEMENT
SIDE VIEW
1 : Setting out Construction Point 7cmx7cm, wooden stakes.
2 : Setting out Offset Stakes from 7cmx7cm,wooden stakes.
3 : Setting out Pile center from X 3cmx3cm, wooden stakes.
4 : Check by the Engineer.
5 : If it is no more available, re-set out from X.
Trang 122) Excavation
Procedure of survey work for excavation is as follows
PILE ARRANGEMENT
LC R-PIER L-PIER FRONT VIEW
PILE ARRANGEMENT
SIDE VIEW
1 : Setting out Offset Stakes from 7cmx7cm,wooden stakes.
2 : Setting out Excavation line from X 3cmx3cm, wooden stakes.
3 : Setting out Offset point from 7cmx7cm, wooden stakes.
Trang 133) Pile Cap
Procedure for execution of pile cap work is as follows
PILE ARRANGEMENT
LC R-PIER L-PIER FRONT VIEW
PLAN VIEW
SIDE VIEW
1 : Setting out Offset Stakes from O 7cmx7cm,wooden stakes.
2 : Marking out by setting Total Station at X.
3 : Marking Pile cap line from .
4 : Marking out Structural and cross-section centerline Offsetting from using steel measuring tape.
Wooden Stakes X will be removed after No 2 ends.
Trang 144) Pier (at Base)
Procedure for execution of pier column work is as follows
LC R-PIER L-PIER FRONT VIEW SIDE VIEW
PLAN VIEW
1 : Setting out Offset Stakes from O 7cmx7cm,wooden stakes.
2 : Marking out by setting Total Station at
3 : Marking out Structural and cross-section centerline setting Total Station at .
4 : Marking out pier line based on the line drawn by No 3.
5 : Offsetting pier line 30cm far from Pier line.
Wooden Stakes will be removed after No 2 ends.
Trang 155) Pier (at Top)
Procedure for execution of pier column work is as follows
LC R-PIER L-PIER FRONT VIEW
Trang 16Plan View
End Point of Girder
Side Line of Girder
Side Line of Girder
End Point of Girder
Position of Marking on Bridge Seat
Cross Section
Trang 175.2 Underpass works
5.2.1 Substructure
1) ExcavationProcedure of survey work for excavation is as follows
Trang 18Procedure of survey work for Bottom Slap is as follows.
Trang 19Set out design center of pier: Straightness and vertical will be check based on
the offset line of pier line maked out, cheking will execute using Plumb that will
be hanged from the top of column from
Trang 216 Topographic Survey
6.1 General
Topographic Survey will be executed for 3 purposes as follows
by excavation and/or Embankment
made with using cross-sectional drawing and longitudinal profile drawing
6.2 Positions to be surveyed
Two (2) kinds of field survey will be executed for topographic survey Those are cross-section
of road and bridge position and longitudinal profile of road and bridge position Positions to besurveyed are shown in Drawing below
Additional cross-sections is requested at significant breaks in topography and at changes
in the typical section (point of tangent (PT) and point middle curve (MC)) For eachcross-section, rod points shall be measured and recorded at changeable topography withmaximum 5m-interval between rod points
The width of cross section is area between approximately 20m offset line of both sides ofland acquition Points to be surveyed are as following drawing
PT
MC
PT
Trang 222) Longitudinal Profile of Road and Bridge Position
Considering the project area, through way center, frontage road, & ramp center line will
be surveyed Longitudinal profile at center line of box culvert and pipe culvert shall besurveyed also
Distance and elevation will be surveyed using Total Station
Before starting Topographic Survey, road and bridge center line shall be marked by stakes atsite Method of setting out, coordinate and location drawing of each center point are stated asfollows
6.5.1 Site Organization Chart
Fig 1 For Bridge Section Fig 2 For Embankment Area
Trang 236.5.2 Topographic Survey Sections
Topographic Survey Sections are proposed according to the method shown below
Site Manager
Project ManagerConstruction Manager
POSCO E&C Co., Ltd.
Trang 24appropriate position (as shown in Fig.2) In the case that Frontage road is straightline,parallel adjacent with to Throughway, shall be set only one cross-section (as shown inFig.3).
To carry out Topographic Survey, total station shall be set at any location After setting totalstation at certain location, coordinate of this location will be checked by 2 known ControlPoints Then, both boundary and other several points on certain Topographic Survey sectionwill be marked by stakes or bamboo poles and Topographic Survey section line will bemarked by some rope or measuring tape Along this marked line, coordinate and elevation of
Center of Throughway L.A.B
Topographic Survey Boundary
20m 20m
Fig 1 Topographic Survey Section Width (Throughway)
Center of Throughway L.A.B
Topographic Survey Boundary 20m
Fig 2 Topographic Survey Section Width (Throughway with Ramp Way)
L.A.B 20m Center of Ramp Way
L.A.B: Land Acquisition Border
Trang 256.5.3 Longitudinal Profiles
Longitudinal Profiles of road, bridge, underpass, box culvert and pipe culvert will be surveyed at the longitudinal center line of each structure Structures of which longitudinal profile will be surveyed are listed below
Underpass Box Culvert:
No Station Road Class
Trang 26Drainage Box Culverts:
No Station Function
Irrigation Pile Culverts:
No Station No Station No Station
N
o Station Function Km
Trang 275 Km 1+285 25 Km 8+620 45
Km 14+635 65 Km 20+100 Irrigation
6 Km 1+340 26 Km 8+799 46
Km 15+290 66 Km 20+273 Irrigation
7 Km 1+522 27 Km 8+860 47
Km 15+360 67 Km 20+460 Irrigation
8 Km 2+280 28 Km 9+488 48
Km 15+548 68 Km 20+550 Irrigation
9 Km 2+370 29 Km 9+743 49
Km 15+640 69 Km 20+722 Irrigation
10 Km 2+494 30 Km 9+805 50
Km 16+149 70 Km 20+790 Irrigation
11 Km 2+600 31 Km 10+010 51
Km 16+580 71 Km 20+936 Irrigation
12 Km 2+855 32 Km 10+190 52
Km 16+770 72 Km 21+374 Irrigation
13 Km 2+887 33 Km 10+485 53
Km 16+947 73 Km 22+565 Irrigation
14 Km 2+991 34 Km 10+880 54
Km 17+145 74 Km 22+765 Irrigation
15 Km 3+305 35 Km 11+193 55
Km 17+367 75 Km 23+228 Irrigation
16 Km 3+555 36 Km 11+640 56
Km 17+515 76 Km 23+648 Irrigation
17 Km 4+010 37 Km 11+827 57
Km 17+665 77 Km 24+655 Irrigation
18 Km 5+665 38 Km 11+925 58
Km 17+814 78 Km 25+435 Irrigation
19 Km 5+787 39 Km 12+290 59
Km 18+132 79 Km 25+750 Irrigation
Trang 28A2 Km 01+430 Drainage
D Km 01+010 Irrigation
Culverts at Interchange No.4:
No Station Function A1 Km 00+760 Drainage A1 Km 01+840 Drainage
Center points will be set out prior to Topographic Survey and used for this survey work
b) Accuracy of Field Survey
Accuracy for Center Points is same as those of Control Points
c) Setting out Work
Method
Center Points will be set out from Control Points including GPS Points First of all, BaseLine will be set using Control Points and field survey for setting out Center Points will beexecuted based on the Base Line using Total Station After coordinate of Center Point is
Trang 29Location of Center Points of Embankment and Bridges will be selected as the following foreach works:
Center Point coordinates are included in attached table of Appendix III And also According
to these coordinates, Center Points will be set out
6.6.5 Inspection
Topographic Survey shall be done in the presence of Inspector Proposed Inspection Sheet is
Topographic Section shall be recorded and sign by Inspector Coordinate and elevation ofsurveyed point shall be taken from total station in office and submitted with this Inspectionsheet for approval later
Trang 307 Method of Field Survey and Apparatus
7.1 Apparatus
Total Stations and Auto-Level will be nominated as equipments used for Field Survey work These equipment may change provided by the Sub-contractor when working
The Certificates of Survey Equipment are attached as Appendix VI
7.2 Calibration
Checking apparatus is executed once a month by the Contractor under the supervision ofthe Engineer In addition, checking apparatus is executed once a year by third party inorder to get calibration certificate to confirm the quality of apparatus The result includingchecking person and/or organization and date of checking will be recorded and submitted
to the Engineer.If the error is over the tolerance, the apparatus will be sent for repair
-Transit
3 points will be set on a line by 100m distance between each point Setting transit atthe center point, and the angle of 180°will be checked with turning over the sight -
Total Station
Setting of Total Station at the Base Point of GPS Point (GPS01, GPS02,… GPS09) oneControl Point coordinates will be checked based on a Base Line of GPS Point –Control Point on a known Bench mark
-Level
2 points will be set in line, and elevation survey will be executed from the middle point
of the 2 points and from near the one point Confirmation will be made by checking
Trang 314) The calculated result must be within the range of the following allowabletolerances.
not more than 8”
be < 1/70,000 in which S is length of side
7.4 Field Survey Using Level
The elevation transverse should be measured in both the forward and backward direction toform in one closed system The best distance from the level to the leveling staff is 75m, butthis distance could be extended to 100m if a good picture is provided The height of thesurvey ray should be at least 0.3m above the ground or any object
The difference of distance from the level to the leveling staff should not be more than 2mand accumulative distance differences within one section should not be more than 5m
7.5 Documents to be submitted
8 Survey Points to be Used
Those coordinates and elevations are shown below Before using these points, they shall bechecked by GPS