Trang 1FLOOR LEVELING PROCESS with S485 LASER SCREED
Quang Ngai, Vietnam
October 22 to 29, 2019
www.anconbeton.com
Trang 2FLOOR LEVELING PROCESS
Trang 3ROOF AND SIDE PROTECTION ARE INSTALLED
• Photo 1: Roof and side protection installed for protection from direct sunlight, rain,
and wind getting into the concrete floor during casting This will prevent rapid
evaporation of water from the concrete surface
• Photo 2: If walls are not in place, erect scaffolding cover (blue sheet) locked down
and at least 2 meters high to prevent rain water and wind blowing in during finishing
process
Photo 1 Photo 2
Trang 4FORMWORK SET UP
• Photo 1: Slab on grade
• Photo 2: slab on piles
Trang 5SET UP OF S485
1.) Obtain finish floor level by setting laser guided transmitter
2.) Transmitter will transfer the designed elevation
3.) Laser Receiver are set to the s485 for rough (quick pass) and screeding (smooth)
Trang 6SET UP OF LASER TRANSMITTER FOR S485
1.) Obtain finish floor level by setting laser guided transmitter
2.) Transmitter will transfer the designed elevation
Trang 7SET UP GRADE ROD
1 Set Grade Rod to bench mark
2 Read numbers on grade rod
3 Set matching numbers on machine receive poles
4 Screed test pass and adjust
Trang 8SET UP PUMP LINES WITH LINE PUMP
casting
Trang 9SET UP PUMP LINES WITH LINE PUMP (CONT’D)
This concrete is discharged in 4 meter strips wide
Trang 10WITH STEEL FIBER CONCRETE SLAB
Trang 111 1
VIBRATION
Vibrator must be inserted immediately after placing
Vibrator must be inserted vertically to reduce the air entrance
Trang 12MANUAL ROUGH LEVELING JUST ABOVE GRADE
Trang 131 3
ROUGH LEVELING BY ‘QUICK PASS’ FUNCTION
The s485 can pull the concrete to a rough level through a function called
“Quick Pass”
Trang 14FINE LEVEL TO DESIRED FFL
Trang 151 5
USE GRADE ROD TO CHECK LEVEL
Trang 16FINE LEVEL OF SCREEDED CONCRETE
1. After first pass of fine level, s485 will move parallel to the first pass
area
joint
Trang 171 7
HAND SCREED TOOLS FOR EDGING
Trang 18HAND TOOLS-MESH ROLLER
Mesh Roller is to embed steel fibers and to bring up some cement paste up to surface to cover.Mesh Roller can also be used to push down coarse aggregates at the surface of concrete
Trang 191 9
HAND TOOLS-CHANNEL FLOAT
After Mesh Roller has pass through, apply channel float to fill surface and improve flatness.Overlap each pass by 50%
Trang 20HAND TOOLS-CHECK ROD
For higher tolerance floor apply check rod when concrete is still plastic
Overlap each pass by 50%
Trang 212 1
RESULT OF A GOOD LEVEL FLOOR