Trang 1SUNWAH PEARL
PROJECT 装修实施策划报告
http://cscec-sea.com
中国建筑(东南亚)有限公司
编制:李墩安
Trang 2目 录
CONTENTS
01
03 04 05 06
project brief
construction method
construction schedule construction resource quality&HSE management
Trang 3project brief 1
Trang 5项目简介 PROJECT PROFILE
Trang 7project organization chart
2
Trang 9Main construction method
3
Trang 104、塔吊附墙方案/Anchorage Of Tower Crane
5、装修策划/Finishing Work Plan
6、临水临电方案 Temporary Hydraulic & Electric plan
Trang 11SITE OFFICE Set up the office on the SAIGON PEARL side Move the office to the 3F(refer to the site drawing)
WORKERS QUARTERS Subcontractors to solve the dorm problems.
TOWER CRANE Four tower cranes are arranged(2 pcs 6018,2 pcs D5522)Refer to the master plan
ROAD Local roads use precast slab, cast concrete, and the original road combination consideration.
TEMPORARY BUILDING PLAN
Trang 121.MASTER PLAN
MASTER LIAN
Trang 131.MASTERIAL PLAN
SITE OFFICE LAYOUT ON 3F OFFICE &MATERIAL STORE LAYOUT ON B1F
Trang 14EQUIPMENT LIST
Trang 15MIXING STATION CAPACITY CALCULATION
Trang 162.INTEGRATED SELF CLIMB SCAFFOLD
INTEGRATED SELF CLIMB SCAFFOLD
Trang 172.INTEGRATED SELF CLIMB SCAFFOLD
Tower 1 SCAFFOLD LAYOUT
3D DISPLAY
FLAP PROTECTION
Trang 18The concrete strength of the wall
structure attached to the hanging wall
must reach or exceed 10MPa before
lifting The strength of the second
layer from top to bottom reaches
15MPa, and the strength of the third
layer reaches 20MPa
According to the actual situation of
the site, the leveling frame can be
installed at 7F first, and the rest part
can be assembled on the ground and
then use tower crane to install.
The position of 8F does not need to be embedded in advance From 9F, the screw hole
of the attached wall fixed guide seat is reserved From 10F, the screw hole of the
upper hanging wall is reserved.Consider piercing the aluminum mold.
8F
10F 9F
11F 12F
2.INTEGRATED SELF CLIMB SCAFFOLD
Trang 19<1>Level Frame Build
<3>a.Synchronous Installion of upright
tube and horizontal truss
<2>Installation of bottom operation
b.Install guide rail support and the
2th&3th safety nets
c.Splicicing of upright tubes
<5>Installation of lateral net
<6>a.Connection between guide rail
link and operatingplatform
b.Fasten the attached wall fixed
guide seat and guide rail
2.INTEGRATED SELF CLIMB SCAFFOLD
Trang 20<7>a.Underslung truss mounting
b.Underslung point mounting
c.Installation of hanging seat
on chain block
<8>a.Bottom connection plate
and seal flap installion
b.Kick board installation
<9>.Install the operating
platforms of 4 th &5 th
Floors and lateral guide net
<10>.Insert the installation synchronously
for piece,seal flap,kick board and guide seat
,adjustable positioning device,etc.
<11>.Install intelligent lifting
system
2.INTEGRATED SELF CLIMB SCAFFOLD
Trang 21waste, low carbon emission reduction, and convenient support system.
Trang 22Aluminum formwork standard
Concrete standard
3.ALUMINUM FORMWORK
Trang 23THE THICKNESS OF THE WALL CHANGE
key
L26-32 L20-L26 L14-L20 L7-L14
L32-38 L38-44 L44-TOP
500 600 +300 500 400 450
500 +300 500/ 400 300 400
550 +300 500/ 450 350
400 +300 500/ 350 250 350
400+300 500/ 300 250 300
350 +300 500/ 250 250 300
300 +300 500/ 250 250
250
Trang 24ALUMINUM FORMWORK RE-DESIGN
There is a small section of masonry between the column and the exterior wall, which is design into concrete
Trang 25A small portion of the exterior wall bulges out of the masonry and deepens into concrete
ALUMINUM FORMWORK RE-DESIGN
Trang 26SCHEDULE TO TYPICAL FLOOR
Trang 27ALUMINUM FORMWORK ACCEPTANCE STANDARD
1 Acceptance error range:
Wall column: vertical [0,4]mm, Flatness [0,4]mm,
Inside and outside corners [-3,3]mm Section size [-3,+5]mm;
Floor thickness [-3,+5]mm Door opening size [-5,+5]mm:
Door opening flatness [0,3]mm Ceiling level [0,+5]mm
Ground level: [0,4]mm Beam side verticality [0,+2]mm;
Beam positioning deviation [0,+2]mm Founder] [0, + 5 mm
The clear height of [8] mm Cumulative deviation degree of control
Line [0,+2]mm
Trang 284 Anchorage Of Tower Crane
Tower 3&4 ANCHORAGE SECTION
TC3 and TC4 anchor at 8F、16F、23F、30F、38F、 45F。 TC1 and TC2anchor at 6F、11F、17F、22F
、 27F、32F、40F,additional TC1 anchor at 44F、 47F。
Trang 295.FINISH WORK PLAN
1#KERB LAYOUT
KERB DETAIL
Trang 31BALCONY,HANDRAIL AND WATER DRIP
The balcony is not closed, the drip line install when plastering
Trang 32WATER DRIP
Water Drip Detail
Trang 33JZM 350 MIXER-8
FORKLIFT(3t)-30台
MORTAR PUMP2-3立方米/h
Trang 34BRICK WORK
THE RATIO OF BRICK WORK
BRICK WORK DETAIL
THE OPENNING DETAIL
Trang 35BRICK WORK LAYOUT
BRICK WORK LAYOUT
TEMPORARY TOILET
Trang 36FINISH WORK PLAN
Masonry model SAMPLE FLOOR(T1—8F)
Trang 37WATER STOP METHOD
"Dry area" includes elevator hall
and indoor rooms
•Plagging position: The reserved
hole of kitchen flue,survey hole
,formwork transfer hole, Water and
electricity well reserve hole, the
wind well.
The drainage position:Elevator
shaft, balcony drain hole, toilet
drain hole, kitchen drain pipe.
The "wet area" is fire stairs and external walls
•Plagging position:Rest platform kerb, tube side seal
•The drainage position:Exterior walls, stair platforms.
•Divide the floor into two areas: dry area and wet area; "Dry area"
includes elevator hall and indoor rooms; The "wet area" is fire stairs and external walls; The closure and drainage method is adopted in the dry area and the drainage system is adopted in the wet area.
Trang 38WATER STOP METHOD
Trang 39WATER STOP METHOD
Trang 40Hydraulic & Electric Temporary
GF TEMPORARY ELECTRIC LAYOUT GF TEMPORARY HYDRAULIC LAYOUT
Trang 41Hydraulic & Electric Temporary
Trang 454
Trang 47STRUCTURE SCHEDULE
Trang 48FINISHING SCHEDULE
Trang 49MEP SCHEDULE
Trang 51CONSTRUCTION RESOURCE
六
Trang 52分包资源及进场计划 1
Trang 53分包资源及进场计划 2
Trang 54分包资源及进场计划 3
Trang 55劳动力控制表
Trang 57周转材料投入表
Trang 60QUALITY&HSE MANAGEMENT
七
Trang 62MANAGEMENT GOALS
Trang 63样板引路
Trang 64墙柱表面垂直度偏差 板表面平整度偏差
Trang 65新华项目实测实量章
新华项目实测实量章
Trang 672 体系管理 编制CI布置标准化策划
现场办公区、临建、加工防护棚、设备、警示标语、临边洞口防护、楼层垃圾输送、塔吊施工电梯防护、安全通道防护
越籍主管及资料员 2017.8.11
9 过程管理 安全周检查、安全周例会 业主、监理、项目安全、工程在现场进行安全检查 每周五下午2:00
安全经理、越籍主管经理、工程部负责人、技术部负责人
Trang 6816 过程管理 分包管理制度
对分包劳工、管理人员的不安全行为、工作中的不安全状态进行教育、发出勒令整改、停工等指令,对于未能按要求进行整改、重大违章、违规等操作进行处罚。
Trang 70PERIOD PLAN
请各位领导 提出宝贵意见
谢谢!