GIẢI PHÁP CỐP PHA1.. CỘT, VÁCH / LÕI THANG : CỐP PHA VÁN CẦU THANG BỘ : CỐP PHA VÁN TẦNG ĐIỂN HÌNH TẦNG KHÔNG ĐIỂN HÌNH 1 BIỆN PHÁP CỐP PHA... 1 BIỆN PHÁP CỐP PHA GIẢI PHÁP CỐP PHA CH
Trang 15 GIẢI PHÁP CỐP PHA
1. MÓNG / TẦNG HẦM
ĐÀI MÓNG, DẦM MÓNG : CỐP PHA VÁN
CỘT, VÁCH / LÕI THANG : CỐP PHA VÁN
CẦU THANG BỘ : CỐP PHA VÁN
2. TẦNG KHÔNG ĐIỂN HÌNH
CỘT, VÁCH / LÕI THANG : CỐP PHA VÁN
CẦU THANG BỘ : CỐP PHA VÁN
3. TẦNG ĐIỂN HÌNH
. CỘT, VÁCH / LÕI THANG : CỐP PHA VÁN
CẦU THANG BỘ : CỐP PHA VÁN
TẦNG ĐIỂN HÌNH
TẦNG KHÔNG ĐIỂN HÌNH
1 BIỆN PHÁP CỐP PHA
Trang 25 GIẢI PHÁP CỐP PHA CHO MÓNG, TẦNG HẦM
MẶT BẰNG TẦNG HẦM 2
1 BIỆN PHÁP CỐP PHA
3 LÕI THANG : CỐP PHA VÁN
CẦU THANG BỘ : CỐP PHA VÁN
DẦM, SÀN : CỐP PHA VÁN
5
4
CỘT, VÁCH : CỐP PHA VÁN 2
ĐÀI MÓNG, DẦM MÓNG : CỐP PHA VÁN 1
Trang 35 GIẢI PHÁP CỐP PHA CHO TẦNG KHÔNG ĐIỂN HÌNH
MẶT BẰNG TẦNG 2
1 BIỆN PHÁP CỐP PHA
3 LÕI THANG : CỐP PHA VÁN
CẦU THANG BỘ : CỐP PHA VÁN
DẦM, SÀN : CỐP PHA VÁN
5
4
CỘT, VÁCH : CỐP PHA VÁN 2
ĐÀI MÓNG, DẦM MÓNG : CỐP PHA VÁN 1
Trang 45 1 BIỆN PHÁP CỐP PHA GIẢI PHÁP CỐP PHA CHO TẦNG ĐIỂN HÌNH
MẶT BẰNG TẦNG ĐIỂN HÌNH
3 LÕI THANG : CỐP PHA VÁN
CẦU THANG BỘ : CỐP PHA VÁN
DẦM, SÀN : CỐP PHA VÁN
5
4
CỘT, VÁCH : CỐP PHA VÁN 2
ĐÀI MÓNG, DẦM MÓNG : CỐP PHA VÁN 1
Trang 55 1 BIỆN PHÁP CỐP PHA GIẢI PHÁP CỐP PHA CHO CỘT, VÁCH / LÕI THANG
1 ĐÀI MÓNG, DẦM MÓNG: CỐP PHA VÁN
Trang 65 1 BIỆN PHÁP CỐP PHA GIẢI PHÁP CỐP PHA CHO CỘT, VÁCH / LÕI THANG
2 CỘT, VÁCH: CỐP PHA VÁN
Trang 75 1 BIỆN PHÁP CỐP PHA GIẢI PHÁP CỐP PHA CHO CỘT, VÁCH / LÕI THANG
3 LÕI THANG: CỐP PHA VÁN
Trang 8DẦM, SÀN: CỐP PHA NHÔM
4
Trang 95 CẦU THANG BỘ: CỐP PHA NHÔM
Trang 105 1 BIỆN PHÁP BAO CHE, AN TOÀN GIÀN GIÁO BAO CHE BÊN NGOÀI
MẶT CẮT GIÀN GIÁO BAO CHE BÊN NGOÀI PHỐI CẢNH GIÀN GIÁO BAO CHE BÊN NGOÀI