1 FORMWORK METHOD FORMWORK FOR COLUMN, WALL / CORE WALL1 COLUMN, WALL: PLYWOOD FORMWORK... CORE WALL: PLYWOOD FORMWORK 1 FORMWORK METHOD FORMWORK FOR COLUMN, WALL / CORE WALL 2... 1 FOR
Trang 1COFICO Copyright © 2017
1 FOUNDATION / BASEMENTS (B4 – B1)
FORMWORK
FORMWORK
COLUMN, WALL / CORE WALL : PLWOOOD FORMWORK
FORMWORK
FORMWORK
2 NON-TYPICAL FLOORS (1F – 2F / M&E – RF)
COLUMN, WALL / CORE WALL : PLYWOOD FORMWORK
FORMWORK
FORMWORK
3 TYPICAL FLOORS (3F – 23F)
COLUMN, WALL / CORE WALL : ALUMINIUM FORMWORK
FORMWORK
TYPICAL FLOORS
(3F – 23F)
NON-TYPICAL FLOORS (1F – 2F / M&E – RF)
FOUNDATION / BASEMENTS
(B4 – B1)
Trang 25 1 FORMWORK METHOD FORMWORK PLAN FOR FOUNDATION
GROUND BEAM : PLYWOOD FORMWORK 2
FOUNDATION : PLYWOOD FORMWORK 1
FOUNDATION LAYOUT PLAN
Trang 35 1 FORMWORK METHOD FORMWORK FOR COLUMN, WALL / CORE WALL
2
1 FOUNDATION : PLYWOOD FORMWORK
GROUND BEAM : PLYWOOD FORMWORK
Trang 45 1 FORMWORK METHOD FORMWORK PLAN FOR BASEMENTS (B4 – B1)
2 CORE WALL : PLYWOOD FORMWORK
STAIR : PLYWOOD FORMWORK
3
COLUMN, WALL: PLYWOOD FORMWORK 1
BASEMENT LAYOUT PLAN
Trang 55 1 FORMWORK METHOD FORMWORK PLAN FOR NON-TYPICAL FLOORS
2 CORE WALL : PLYWOOD FORMWORK
STAIR : PLYWOOD FORMWORK
3
COLUMN, WALL: PLYWOOD FORMWORK 1
LEVEL 1 LAYOUT PLAN
Trang 65 1 FORMWORK METHOD FORMWORK FOR COLUMN, WALL / CORE WALL
1 COLUMN, WALL: PLYWOOD FORMWORK
Trang 7CORE WALL: PLYWOOD FORMWORK
1 FORMWORK METHOD FORMWORK FOR COLUMN, WALL / CORE WALL
2
Trang 8BEAM, SLAB: PLYWOOD FORMWORK
1 FORMWORK METHOD FORMWORK FOR BEAM, SLAB & STAIR
3
Trang 9STAIR: PLYWOOD FORMWORK
1 FORMWORK METHOD FORMWORK FOR BEAM, SLAB & STAIR
4
Trang 105 1 FORMWORK METHOD FORMWORK PLAN FOR TYPICAL FLOORS
2 CORE WALL : ALUMINIUM FORMWORK
STAIR : ALUMINIUM FORMWORK
3
COLUMN, WALL: ALUMINIUM FORMWORK 1
TYPICAL FLOOR LAYOUT PLAN
Trang 115 1 FORMWORK METHOD FORMWORK FOR COLUMN, WALL / CORE WALL
2
1 COLUMN, WALL: ALUMINIUM FORMWORK
CORE WALL: ALUMINIUM FORMWORK
Trang 12OPTION 1 BEAM, SLAB: ALUMINIUM FORMWORK
3
Trang 134 STAIR: PLYWOOD FORMWORK
Trang 145 1 SAFETY PROTECTION SYSTEM EXTERNAL SCAFFOLDING