GIẢI PHÁP CỐP PHATẦNG ĐIỂN HÌNH TẦNG KHÔNG ĐIỂN HÌNH 1 BIỆN PHÁP CỐP PHA 1... 1 BIỆN PHÁP CỐP PHA GIẢI PHÁP CỐP PHA CHO CỘT, VÁCH / LÕI THANG 1 ĐÀI MÓNG, DẦM MÓNG: CỐP PHA VÁN... 1 BIỆN
Trang 15 GIẢI PHÁP CỐP PHA
TẦNG ĐIỂN HÌNH
TẦNG KHÔNG ĐIỂN HÌNH
1 BIỆN PHÁP CỐP PHA
1 MÓNG / TẦNG HẦM
ĐÀI MÓNG, DẦM MÓNG : CỐP PHA VÁN
CỘT, VÁCH / LÕI THANG : CỐP PHA VÁN
DẦM, SÀN : CỐP PHA VÁN
CẦU THANG BỘ : CỐP PHA VÁN
2 TẦNG KHÔNG ĐIỂN HÌNH
CỘT, VÁCH / LÕI THANG : CỐP PHA VÁN
DẦM, SÀN : CỐP PHA VÁN
CẦU THANG BỘ : CỐP PHA VÁN
3 TẦNG ĐIỂN HÌNH
CỘT, VÁCH / LÕI THANG : CỐP PHA NHÔM
DẦM, SÀN : CỐP PHA NHÔM
CẦU THANG BỘ : CỐP PHA NHÔM
Trang 2COFICO Copyright © 2017
MẶT BẰNG TẦNG HẦM
1 BIỆN PHÁP CỐP PHA
3 LÕI THANG : CỐP PHA VÁN
CẦU THANG BỘ : CỐP PHA VÁN
DẦM, SÀN : CỐP PHA VÁN
5
4
CỘT, VÁCH : CỐP PHA VÁN 2
ĐÀI MÓNG, DẦM MÓNG : CỐP PHA VÁN 1
CỘT TRÒN : CỐP PHA THÉP 6
Trang 35 GIẢI PHÁP CỐP PHA CHO TẦNG KHÔNG ĐIỂN HÌNH
MẶT BẰNG TẦNG KHÔNG ĐIỂN HÌNH
1 BIỆN PHÁP CỐP PHA
CỘT TRÒN : CỐP PHA THÉP 6
3 LÕI THANG : CỐP PHA VÁN
CẦU THANG BỘ : CỐP PHA VÁN
DẦM, SÀN : CỐP PHA VÁN
5
4
CỘT, VÁCH : CỐP PHA VÁN 2
ĐÀI MÓNG, DẦM MÓNG : CỐP PHA VÁN 1
Trang 4COFICO Copyright © 2017
5 1 BIỆN PHÁP CỐP PHA GIẢI PHÁP CỐP PHA CHO CỘT, VÁCH / LÕI THANG
1 ĐÀI MÓNG, DẦM MÓNG: CỐP PHA VÁN
Trang 55 1 BIỆN PHÁP CỐP PHA GIẢI PHÁP CỐP PHA CHO CỘT, VÁCH / LÕI THANG
3
2 CỘT, VÁCH: CỐP PHA VÁN
LÕI THANG: CỐP PHA VÁN
Trang 6COFICO Copyright © 2017
5.
DẦM SÀN: CỐP PHA VÁN
1 BIỆN PHÁP CỐP PHA GIẢI PHÁP CỐP PHA CHO DẦM SÀN VÀ CẦU THANG BỘ
5
4
CẦU THANG BỘ: CỐP PHA VÁN
Trang 75 1 BIỆN PHÁP CỐP PHA GIẢI PHÁP CỐP PHA CHO CỘT TRÒN
6 CỘT TRÒN: CỐP PHA THÉP
Trang 8COFICO Copyright © 2017
5 1 BIỆN PHÁP CỐP PHA GIẢI PHÁP CỐP PHA CHO DẦM CHUYỂN
6 CỘT TRÒN: CỐP PHA THÉP
Trang 95 1 BIỆN PHÁP CỐP PHA GIẢI PHÁP CỐP PHA CHO TẦNG ĐIỂN HÌNH
2 LÕI THANG : CỐP PHA NHÔM
CẦU THANG BỘ : CỐP PHA NHÔM
3
CỘT, VÁCH : CỐP PHA NHÔM 1
Trang 10COFICO Copyright © 2017
5 1 BIỆN PHÁP CỐP PHA GIẢI PHÁP CỐP PHA CHO CỘT, VÁCH / LÕI THANG
2
1 CỘT, VÁCH: CỐP PHA NHÔM
LÕI THANG: CỐP PHA NHÔM
Trang 11DẦM, SÀN: CỐP PHA NHÔM
1 BIỆN PHÁP CỐP PHA GIẢI PHÁP CỐP PHA CHO DẦM, SÀN
3
Trang 12COFICO Copyright © 2017
5.
4 CẦU THANG BỘ: CỐP PHA NHÔM
1 BIỆN PHÁP CỐP PHA GIẢI PHÁP CỐP PHA CHO CẦU THANG BỘ
Trang 135 MẠCH NGỪNG THI CÔNG: CỐP PHA NHÔM
1 BIỆN PHÁP CỐP PHA GIẢI PHÁP CỐP PHA CHO MẠCH NGỪNG THI CÔNG
MẶT CẮT TRÌNH TỰ THI CÔNG MẠCH NGỪNG
MẶT BẰNG ĐỊNH VỊ MẠCH NGỪNG THI CÔNG
Trang 14COFICO Copyright © 2017
5 1 BIỆN PHÁP BAO CHE, AN TOÀN GIÀN GIÁO BAO CHE BÊN NGOÀI
MẶT CẮT GIÀN GIÁO BAO CHE BÊN NGOÀI PHỐI CẢNH GIÀN GIÁO BAO CHE BÊN NGOÀI