Construction Methodology for Transfer Beams – System support... Formwork Methodology for Transfer Beams – Sequences... Construction Methodology – Step 2: Testing load to system support..
Trang 1VIETTEL OPERATION & TRADE CENTER
BIM
Trang 2Block B – 4 star Hotel
Transfer beam area
Trang 3Transfer beam 3 .00m x 3.70m
Trang 4Viettel Operation & Trade Center Project Item: Block B – 4 Star Hotel,
24 floors and 03 basements
Main scope : Structural works
& Finish works M&E, not yet nominated
Total height : 93.90 m
Commencement : 02/01/2013
Expected completion : 23/09/2014
Trang 5F HC
F HC
F HC P&D HVAC
SE OA
KE TE KE CW CHW
FS SP
P&D
P&D ELE
P&D P&D
R S
T U
V W
Trang 6Construction Methodology for Transfer Beams – System support
Trang 7Formwork Methodology for Transfer Beams – Sequences
Trang 8Formwork Methodology for Transfer Beams – Sequences
Trang 9Construction Methodology – Step 1: Erecting system support
Trang 10Construction Methodology – Step 2: Testing load to system support
Trang 11Construction Methodology – Step 3: Installing rebars
Trang 12Construction Methodology – Step 4: Installing post tension cable
Trang 13Construction Methodology – Step 4: Installing post tension cable
Trang 14Construction Methodology – Step 5: Installing cooling system & temperature sensor
Trang 15Construction Methodology – Step 6: Finishing beam side formwork for 1st casting
Trang 16Construction Methodology – Step 7: 1st Casting
Trang 17Construction Methodology – Step 8: Curing the 1st Casting
Trang 18Construction Methodology – Step 9: Finishing beam side formwork for 2nd casting
Trang 19Construction Methodology – Step 10.1: 2nd casting
Trang 20Construction Methodology – Step 10.2: Checking temperature after concreting
Trang 21Construction Methodology – Step 11: Post tension
Trang 22Construction Methodology – Step 12: Dismantling support + formwork and Finishing
Trang 23With practical experiences, we are considering how BIM to support us IMPROVING ???