1. Trang chủ
  2. » Kỹ Thuật - Công Nghệ

A9120 BSC installation manual HUAWEI EQUIPMENT INSTALLATION

90 353 0

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 90
Dung lượng 4,43 MB

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Nội dung

3 Racks installation3 Racks installation This chapter describes how to :Move the racks to their final locationsUnpack the racks Prepare the racks already in operationPosition the racks L

Trang 1

ALCATEL BSS A9120 BSC with multipair cables

Installation Manual

Trang 2

Status RELEASEDShort title INS

All rights reserved Passing on and copying of this document, useand communication of its contents not permitted without writtenauthorization from Alcatel/Evolium

Trang 3

Contents

Preface 5

1 General Information 7

1.1 Hardware Description 8

1.1.1 General Information 8

1.1.2 Racks Configuration 9

1.1.3 Weight and Dimensions 11

1.2 Restrictions 11

1.3 Prerequisite 11

1.4 Initial State 11

1.5 Final State 12

1.6 Operating Principle 12

1.7 Time Schedule 13

1.8 Information Required 13

2 Preliminary Checks 15

2.1 Before Leaving for the Site 16

2.2 Before Starting (on Arrival at the Site) 16

3 Racks installation 17

3.1 Rack Delivery 18

3.2 Mechanical Assembling 19

3.2.1 Racks Positioning 19

3.2.2 Racks Assembling 21

3.2.3 Top Structures Fitting 22

3.2.4 Side Panels Fitting 23

4 Connecting DC Filters to the Racks 25

5 Option : Changing from 3–Wire to 2–Wire DC Power 27

6 Installing the Cable Tray 31

6.1 Normal Floor and Site Cable Tray Higher than 2.60 Meters 32

6.2 Normal Floor and Site Cable Tray Lower than 2.60 Meters 34

6.3 Raised Floor 35

7 Installing Power Cables 41

8 Inter-Rack Cabling (for Extension Racks) 49

9 PCM Cables Installation 53

9.1 Running Cables in the Cable Tray 54

9.2 Cable Routing at Back of Rack (Principle) 55

9.3 Fitting Cables in the First Half Cable Clamp 57

9.4 Connecting Cables to the Racks 59

9.5 Connecting Cables to the DDF 64

9.6 PCM Cable Testing 69

10 Connecting Communication Cables 71

11 Option: Installing Alarm Cables 75

12 Finishing Installation 79

12.1 Mechanical Assembly Finishing 80

12.2 Finishing 82

Trang 5

Preface

Purpose This document describes how to install on site a A9120-BSC with mutipair

cables of ALCATEL 900/1800 subsystem

Audience

InstallersSite administratorsSupervisorsProject managersField service techniciansOccasional users

Assumed Knowledge

Basic knowledge of Alcatel BSS equipmentExperience of electrical mounting and cabling

Trang 7

PrerequisiteInitial StateFinal StateTime ScheduleInformation Required

Trang 8

1.1 Hardware Description

1.1.1 General Information

Figure 1: Examples of site installation

Trang 9

1 General Information

1.1.2 Racks Configuration

Trang 10

Figure 3: Example of extension rack B, C or D (front view)

The configuration and number of racks depend on the customer options,available links / rack are shown in the table below:

Trang 11

— cable tray

— ground plate

— DDF for 2Mbits cables

If any of this equipment is not installed before the operation, contact theALCATEL person responsible for the installation and record it in the CCLdocument

1.4 Initial State

The racks and installation kits are packed and delivered on siteThe site is ready to receive the racks, according to the customer SPP-27document

Trang 12

1.5 Final State

The racks are ready for commissioning

The racks are not powered up

All the PCM cables between rack and site DDF must be installed for each rack

1.6 Operating Principle

Trang 13

1 General Information

1.7 Time Schedule

Basic tasks per rack — duration (minutes) 1st person 2nd person Total / 2 persons

(*1) transportation time to final location depending of the site (4 people aremandatory to transport the equipment manually)

Trang 16

2.1 Before Leaving for the Site

Check that prerequisites have been

satisfied

SeePrerequisite (Section 1.3)

Check availability of all Information

Required

SeeInformation Required (Section 1.8)

Check availability of documentation SeeDocuments Required (in appendix B); check the

edition and release of the documents

Check availability of tools SeeTools Required (in appendix B); refer to the “Tools

catalogue“ for checking the contentCheck calibration label when asked

Check availability of supplies SeeConsumable Supplies (in appendix B)

2.2 Before Starting (on Arrival at the Site)

Check applicable notifications and

Check that the safety instructions have

been applied

Refer to “General Wiring Handbook” to check that thesafety precautions have been taken in accordance withthe safety instructions

Read instructions in the event of anomaly Refer to “General Wiring Handbook” for instructions

Fill in premises inspection form Refer to “BSS site premises inspection, post handover” and

complete “Premise inspection form” (CEL)

Fill in completion check list Complete the header field of the “Completion Check List”

See “Tools catalogue“ and note measurementThe CCL is to be completed as each instruction is carriedout

Check the antistatic wrist strap Check that the resistance of the antistatic wrist strap is

greater then 1 Mohm and connect it to the rack’s earth

Check availability of Alcatel kits SeeInstallation Kits (in appendix B)

Trang 17

3 Racks installation

3 Racks installation

This chapter describes how to :Move the racks to their final locationsUnpack the racks

Prepare the racks already in operationPosition the racks

Level the racksAssemble the racks togetherAssemble the horizontal cable way

The extension rack must be assembled with operating racks

Before making mechanical installation or connection, ensure that the generalsafety instructions are applied (see General Wiring Handbook)

Trang 18

3.1 Rack Delivery

Figure 4: Crane Transportation or pallet transportation

Procedure 1 Check the number of packages.

2 Report any damages on the carrier’s delivery note.

3 Unpack the equipment.

4 Inspect the racks for cracks, scratches, damages to boards

5 Check the serial number

6 Complete the CCL

Figure 5: Unpacking the rack, then checking serial number

Trang 19

3 Racks installation

3.2 Mechanical Assembling

3.2.1 Racks Positioning

Procedure 1 According to the site documentation drawings, mark out the location of

the rack(s) on the ground

2 Move the racks to their final location.

Figure 6: Moving the rack

3 Position the racks in order A, B, C, D.

From the front of racks, the On/Off switches are visible

Figure 7: Front view example with 4 racks

Trang 20

The racks are not attached to the ground.

If feets are not needed, remove only the levelling plate (part 1 and 2 in Figure).Parts 3 and 4 must be let into the frame

1 : Levelling plates (211 02622 AAAW)

2 : Rings (1AD 00802 0002)

3 : Level adjusting bolt (1AD 00204 0033)

4 : Nut (1AD 00197 0043)Figure 8: Leveling feet

Trang 21

3 Racks installation

3.2.2 Racks Assembling

Figure 9: Assembling the racks

Procedure 1 Assemble the racks together without tightening the screw (1 in Figure9)

2 Insert the spacers (detail) on the screws between the rack (3 in Figure).

3 Insert the bottom contact rails (2 in Figure).

4 Tighten slightly the screws.

5 Fit the bottom contact cover plates (using M6 self theading screws)

Trang 22

3.2.3 Top Structures Fitting

Figure 10: Top structure

1 Remove the rear cable clamp from top structure.

2 Fix the top structure to the rack (4 screws).

Trang 23

3 Racks installation

3.2.4 Side Panels Fitting

Procedure 1 Fix the 3 panel supports at right side of the last extension rack.

2 Fix the 2 side panel earthing brackets (1) at top of the last rack.

3 Screw the screws 1AD 00007 0146 to the side panel without tightening them.

4 Position the right side panel (2).

5 Tighten the fastening screws.

Trang 25

4 Connecting DC Filters to the Racks

4 Connecting DC Filters to the Racks

This chapter describes the procedure to connect the DC filters of the topstructure to the rack

Trang 26

Cables represented in Figures 11 and 12 Reference

Figure 11: Top filter unit - Front view for 3-wire system

Figure 12: Top filter unit - Rear view for 3-wire system

Trang 27

5 Option : Changing from 3–Wire to 2–Wire DC Power

5 Option : Changing from 3–Wire to 2–Wire DC Power

This chapter describes the procedure to change from 3-wire to 2-wire powersystem

The racks are delivered in 3-wire power system, and optionally the equipmentcan be modified in 2-wire power system

Trang 28

Procedure 1 Remove cable SG/EG - EG TAB filter (3BK 07838 AN , 1 in Figure13)

2 Remove BATRET - BATRET EMA filter 3BK 07836 AN, 2 in Figure13

3 Remove the filtered BATRET cable (3BK 07844 AP , 3 in Figure13and15)

4 Remove the two earth cables from the vertical frame (3BK 07839 AR , 4 in

Figure13and15)

5 Swap the positions of the small cables on the TRU (211 27978 AA , 5

in in Figure15and16)

6 Add BATRET EG TAB filter 3BK 07835 AN, E in Figure14

7. Install the 17 earth braid jumpers (211 03875 AA)from 02::17ZA03 to 02::18ZA03

from 02::37ZA03 to 02::38ZA03from 02::57ZA03 to 02::58ZA03from 03::02ZA03 to 03::03ZA03from 03::34ZA03 to 03::35ZA03from 04::02ZA03 to 04::03ZA03from 04::29ZA03 to 04::30ZA03from 04::61ZA03 to 04::62ZA03from 06::02ZA03 to 06::03ZA03from 06::34ZA03 to 06::35ZA03from 07::17ZA03 to 07::18ZA03from 07::22ZA03 to 07::23ZA03from 07::49ZA03 to 07::50ZA03from 07::54ZA03 to 07::55ZA03from 08::02ZA03 to 08::03ZA03from 08::41ZA03 to 08::42ZA03from 08::61ZA03 to 08::62ZA03

8. Install the small cable on the TRU (211 27978 AA , H in Figure16)

9. Install the earth cables from EG Tab Filter to the TRU (3BK 07843 AL, D in Figure14and Figure16)

10. Install the two earth cables to the vertical busbar (211 27975 AA , A and B

in Figure16)

Trang 29

5 Option : Changing from 3–Wire to 2–Wire DC Power

Figure 13: BEFORE - Top filter unit, front view for 3–wire system

Figure 14: AFTER - Top filter unit, front view for 2–wire system

Trang 30

Figure 15: BEFORE - Top filter unit, rear view for 3–wire system

Figure 16: AFTER - Top filter unit, rear view for 2–wire system

Trang 31

6 Installing the Cable Tray

6 Installing the Cable Tray

:· normal floor and site cable tray lower than 2.60 meters· raised floorThis procedure applies to three standard cases:

normal floor and site cable tray higher than 2.60 metersnormal floor and site cable tray lower than 2.60 metersraised floor

All other cases are treated as specials and supplies have to be determined

on a site visit

Trang 32

6.1 Normal Floor and Site Cable Tray Higher than 2.60 Meters

1 : Normal floor

2 : Vertical cable tray

3 : Racktop cable trayFigure 17: Normal floor, site cable tray h > 2.60 m

Install the Cable Tray

Mountings on the Racks

1. Assemble the mountings ( 1 in Figure18) with the aluminium bars supplied( 2 in Figure18)

2 Mount all on the rack side panels ( see Figure18)

Figure 18: Cable tray support

Position the cable trays

Trang 33

6 Installing the Cable Tray

Figure 19: Top cable tray

Position the vertical

cable tray

5. Cut a length of cable tray ( 2 in Figure20) for the vertical connection withthe site cable tray ( 1 in Figure20)

6. Assemble using knuckles ( 3 Figure20)

7. Install two electrical interface earth braids between the cable trays Thesebraids should be positioned on the knuckles

Figure 20: Vertical cable tray

Trang 34

Drill a hole in the site

cable tray

8. Make a 40 x 10 cm rectangular hole in the site cable tray, by the cable riser( 1 in Figure21)

Figure 21: Hole in the site cable tray

6.2 Normal Floor and Site Cable Tray Lower than 2.60 Meters

1 : Normal floor

2 : Site cable tray

A : Height of site cable trayFigure 22: Normal floor, site cable tray h < 2.60 m

Drill Holes in the Site

Cable Tray

1. Do not position the racktop cable tray mountings

2. Do not position the precut cable trays

3. On the site cable tray, make a 10 x 4 cm rectangular hole to run the powercables ( 1 in Figure23)

4. In the site cable tray, make a 70 x 4 cm rectangular hole to run the PCM andOMC-R cables ( 2 in Figure23)

5. Position the edge protection over the holes (use the corner protection of the

Trang 35

6 Installing the Cable Tray

Figure 23: Site cable tray

Position the Cable Tray

Mountings on the Rack

1. Assemble the mountings ( 1 in Figure25) with the aluminum bars supplied( 2 in Figure25)

2. Position these assemblies on the rack side panels without fastening them

NOTE : These mountings are not fastened but simply laid on the side panels.

Trang 36

Figure 25: Cable tray support

Position the Cable Trays

on the Mountings

3. Fasten the precut cable trays to the two mountings ( 1 in Figure26)

4. Connect the earth braid ( 2 in Figure26) of the top structure to the cabletray

Figure 26: Top cable tray

Drill and Lay the Raised

Floor Tile for Running

the Cables

5. Cut a 52 cm length of angle section

6. Make a 52 x 6 cm rectangular hole in the raised floor tile

7. Fasten the angle section to the top of the tile using wood screws ( Figure27

, it will then be easier to fasten the cable tray)

Trang 37

6 Installing the Cable Tray

Figure 27: Drilling the tile

Position the Vertical

Cable Tray

8. Cut to length the cable tray for the vertical connection with the raisedfloor cable tray

9. Cut to length the angle section for separating the power cables

10. Fasten this angle section to the vertical cable tray

11. Assemble everything together using knuckles ( 3 in Figure28)

12. Install the earth braids for the electrical interface between the cable trays( 2 in Figure28)

Trang 38

Figure 28: Vertical cable tray

Trang 39

6 Installing the Cable Tray

Put the Edge Protections 13. Position the edge protections ( 1 and 2 in Figure29)

Figure 29: Edge protection

Trang 41

7 Installing Power Cables

7 Installing Power Cables

The chapter describes the procedure to fit:

the earth cablr to the racksthe 48/60 Volts DC from the power cabinet to the racks

Verify that the circuit breakers are opened at the power cabinet

Check the fuse ratings (see SPP 27)Measure the voltages at the power cabinet , make sure the values are inthe specified range

Check that the rack breakers are OFF

Ensure that the rack is delivered in 3-wire system If it’s not the case, change itbefore apply this procedure

Trang 42

Install the Power Bus

Cables in the Cable

3 Fasten the cables to the cable tray every 0.50 m using tie wraps.

Figure 30: Normal floor - Power supply cable running

Trang 43

7 Installing Power Cables

1 : Heat shrink sleeve

A : Length of spare cable (3 m)

B : Cable loop for over length (1 m)

Figure 32: The cable way is mounted to wait extension racks

Connect the Power

Cables to the Power

Cabinet

2 : BAT A or BAT B power cableFigure 33: Connecting power cable to the fuse holder

Trang 44

1 : Earth cable (ES/SG)

2 : 0 V cable (BATRET)

3 : -48 V cable (BAT A)

4 : -48 V cable (BAT B)

5 : Power cabinet signal ground

6 : Power cabinet electrical ground

Label the Cables

Figure 35: Power supply cable labeling

Mark the following text on cable (factory mounted clip) at fuse holder side:the number of the BSC on site:

BSC 01 for BSC number 01BSC 02 for BSC number 02

Trang 45

7 Installing Power Cables

the type of cable:

BAT A for the -48 VBAT B for the -48 VBAT RET for the O VES/SG for earth (green/yellow or black cable)

The power cabinet must be previously labeled by the customer

The number of the BSC is given in the site documentation; it does not depend

of the product generation

The ground black cable must be marked by yellow/green adhesive tape

Connect the Racks to

Power Bus

1 Remove the outer cable insulation (if the cable is double insulated)

2 Fit the cable clamps on power bus (to achieve good contact, do not remove

the conducting grease)

3 Tighten the nut correctly.

1 : Earth cable 3BK 07838 ANAA

2 : 0 V BATRET cable 3BK 07836 ANAA

3 : -48 V BAT A cable 3BK 07834 ANAA

4 : -48 V BAT B cable 3BK 07834 ANAAFigure 36: Connecting the external cable to the rack

Ngày đăng: 28/06/2017, 15:15

TỪ KHÓA LIÊN QUAN

w