3 Racks installation3 Racks installation This chapter describes how to :Move the racks to their final locationsUnpack the racks Prepare the racks already in operationPosition the racks L
Trang 1ALCATEL BSS A9120 BSC with multipair cables
Installation Manual
Trang 2Status RELEASEDShort title INS
All rights reserved Passing on and copying of this document, useand communication of its contents not permitted without writtenauthorization from Alcatel/Evolium
Trang 3Contents
Preface 5
1 General Information 7
1.1 Hardware Description 8
1.1.1 General Information 8
1.1.2 Racks Configuration 9
1.1.3 Weight and Dimensions 11
1.2 Restrictions 11
1.3 Prerequisite 11
1.4 Initial State 11
1.5 Final State 12
1.6 Operating Principle 12
1.7 Time Schedule 13
1.8 Information Required 13
2 Preliminary Checks 15
2.1 Before Leaving for the Site 16
2.2 Before Starting (on Arrival at the Site) 16
3 Racks installation 17
3.1 Rack Delivery 18
3.2 Mechanical Assembling 19
3.2.1 Racks Positioning 19
3.2.2 Racks Assembling 21
3.2.3 Top Structures Fitting 22
3.2.4 Side Panels Fitting 23
4 Connecting DC Filters to the Racks 25
5 Option : Changing from 3–Wire to 2–Wire DC Power 27
6 Installing the Cable Tray 31
6.1 Normal Floor and Site Cable Tray Higher than 2.60 Meters 32
6.2 Normal Floor and Site Cable Tray Lower than 2.60 Meters 34
6.3 Raised Floor 35
7 Installing Power Cables 41
8 Inter-Rack Cabling (for Extension Racks) 49
9 PCM Cables Installation 53
9.1 Running Cables in the Cable Tray 54
9.2 Cable Routing at Back of Rack (Principle) 55
9.3 Fitting Cables in the First Half Cable Clamp 57
9.4 Connecting Cables to the Racks 59
9.5 Connecting Cables to the DDF 64
9.6 PCM Cable Testing 69
10 Connecting Communication Cables 71
11 Option: Installing Alarm Cables 75
12 Finishing Installation 79
12.1 Mechanical Assembly Finishing 80
12.2 Finishing 82
Trang 5Preface
Purpose This document describes how to install on site a A9120-BSC with mutipair
cables of ALCATEL 900/1800 subsystem
Audience
InstallersSite administratorsSupervisorsProject managersField service techniciansOccasional users
Assumed Knowledge
Basic knowledge of Alcatel BSS equipmentExperience of electrical mounting and cabling
Trang 7PrerequisiteInitial StateFinal StateTime ScheduleInformation Required
Trang 81.1 Hardware Description
1.1.1 General Information
Figure 1: Examples of site installation
Trang 91 General Information
1.1.2 Racks Configuration
Trang 10Figure 3: Example of extension rack B, C or D (front view)
The configuration and number of racks depend on the customer options,available links / rack are shown in the table below:
Trang 11— cable tray
— ground plate
— DDF for 2Mbits cables
If any of this equipment is not installed before the operation, contact theALCATEL person responsible for the installation and record it in the CCLdocument
1.4 Initial State
The racks and installation kits are packed and delivered on siteThe site is ready to receive the racks, according to the customer SPP-27document
Trang 121.5 Final State
The racks are ready for commissioning
The racks are not powered up
All the PCM cables between rack and site DDF must be installed for each rack
1.6 Operating Principle
Trang 131 General Information
1.7 Time Schedule
Basic tasks per rack — duration (minutes) 1st person 2nd person Total / 2 persons
(*1) transportation time to final location depending of the site (4 people aremandatory to transport the equipment manually)
Trang 162.1 Before Leaving for the Site
Check that prerequisites have been
satisfied
SeePrerequisite (Section 1.3)
Check availability of all Information
Required
SeeInformation Required (Section 1.8)
Check availability of documentation SeeDocuments Required (in appendix B); check the
edition and release of the documents
Check availability of tools SeeTools Required (in appendix B); refer to the “Tools
catalogue“ for checking the contentCheck calibration label when asked
Check availability of supplies SeeConsumable Supplies (in appendix B)
2.2 Before Starting (on Arrival at the Site)
Check applicable notifications and
Check that the safety instructions have
been applied
Refer to “General Wiring Handbook” to check that thesafety precautions have been taken in accordance withthe safety instructions
Read instructions in the event of anomaly Refer to “General Wiring Handbook” for instructions
Fill in premises inspection form Refer to “BSS site premises inspection, post handover” and
complete “Premise inspection form” (CEL)
Fill in completion check list Complete the header field of the “Completion Check List”
See “Tools catalogue“ and note measurementThe CCL is to be completed as each instruction is carriedout
Check the antistatic wrist strap Check that the resistance of the antistatic wrist strap is
greater then 1 Mohm and connect it to the rack’s earth
Check availability of Alcatel kits SeeInstallation Kits (in appendix B)
Trang 173 Racks installation
3 Racks installation
This chapter describes how to :Move the racks to their final locationsUnpack the racks
Prepare the racks already in operationPosition the racks
Level the racksAssemble the racks togetherAssemble the horizontal cable way
The extension rack must be assembled with operating racks
Before making mechanical installation or connection, ensure that the generalsafety instructions are applied (see General Wiring Handbook)
Trang 183.1 Rack Delivery
Figure 4: Crane Transportation or pallet transportation
Procedure 1 Check the number of packages.
2 Report any damages on the carrier’s delivery note.
3 Unpack the equipment.
4 Inspect the racks for cracks, scratches, damages to boards
5 Check the serial number
6 Complete the CCL
Figure 5: Unpacking the rack, then checking serial number
Trang 193 Racks installation
3.2 Mechanical Assembling
3.2.1 Racks Positioning
Procedure 1 According to the site documentation drawings, mark out the location of
the rack(s) on the ground
2 Move the racks to their final location.
Figure 6: Moving the rack
3 Position the racks in order A, B, C, D.
From the front of racks, the On/Off switches are visible
Figure 7: Front view example with 4 racks
Trang 20The racks are not attached to the ground.
If feets are not needed, remove only the levelling plate (part 1 and 2 in Figure).Parts 3 and 4 must be let into the frame
1 : Levelling plates (211 02622 AAAW)
2 : Rings (1AD 00802 0002)
3 : Level adjusting bolt (1AD 00204 0033)
4 : Nut (1AD 00197 0043)Figure 8: Leveling feet
Trang 213 Racks installation
3.2.2 Racks Assembling
Figure 9: Assembling the racks
Procedure 1 Assemble the racks together without tightening the screw (1 in Figure9)
2 Insert the spacers (detail) on the screws between the rack (3 in Figure).
3 Insert the bottom contact rails (2 in Figure).
4 Tighten slightly the screws.
5 Fit the bottom contact cover plates (using M6 self theading screws)
Trang 223.2.3 Top Structures Fitting
Figure 10: Top structure
1 Remove the rear cable clamp from top structure.
2 Fix the top structure to the rack (4 screws).
Trang 233 Racks installation
3.2.4 Side Panels Fitting
Procedure 1 Fix the 3 panel supports at right side of the last extension rack.
2 Fix the 2 side panel earthing brackets (1) at top of the last rack.
3 Screw the screws 1AD 00007 0146 to the side panel without tightening them.
4 Position the right side panel (2).
5 Tighten the fastening screws.
Trang 254 Connecting DC Filters to the Racks
4 Connecting DC Filters to the Racks
This chapter describes the procedure to connect the DC filters of the topstructure to the rack
Trang 26Cables represented in Figures 11 and 12 Reference
Figure 11: Top filter unit - Front view for 3-wire system
Figure 12: Top filter unit - Rear view for 3-wire system
Trang 275 Option : Changing from 3–Wire to 2–Wire DC Power
5 Option : Changing from 3–Wire to 2–Wire DC Power
This chapter describes the procedure to change from 3-wire to 2-wire powersystem
The racks are delivered in 3-wire power system, and optionally the equipmentcan be modified in 2-wire power system
Trang 28Procedure 1 Remove cable SG/EG - EG TAB filter (3BK 07838 AN , 1 in Figure13)
2 Remove BATRET - BATRET EMA filter 3BK 07836 AN, 2 in Figure13
3 Remove the filtered BATRET cable (3BK 07844 AP , 3 in Figure13and15)
4 Remove the two earth cables from the vertical frame (3BK 07839 AR , 4 in
Figure13and15)
5 Swap the positions of the small cables on the TRU (211 27978 AA , 5
in in Figure15and16)
6 Add BATRET EG TAB filter 3BK 07835 AN, E in Figure14
7. Install the 17 earth braid jumpers (211 03875 AA)from 02::17ZA03 to 02::18ZA03
from 02::37ZA03 to 02::38ZA03from 02::57ZA03 to 02::58ZA03from 03::02ZA03 to 03::03ZA03from 03::34ZA03 to 03::35ZA03from 04::02ZA03 to 04::03ZA03from 04::29ZA03 to 04::30ZA03from 04::61ZA03 to 04::62ZA03from 06::02ZA03 to 06::03ZA03from 06::34ZA03 to 06::35ZA03from 07::17ZA03 to 07::18ZA03from 07::22ZA03 to 07::23ZA03from 07::49ZA03 to 07::50ZA03from 07::54ZA03 to 07::55ZA03from 08::02ZA03 to 08::03ZA03from 08::41ZA03 to 08::42ZA03from 08::61ZA03 to 08::62ZA03
8. Install the small cable on the TRU (211 27978 AA , H in Figure16)
9. Install the earth cables from EG Tab Filter to the TRU (3BK 07843 AL, D in Figure14and Figure16)
10. Install the two earth cables to the vertical busbar (211 27975 AA , A and B
in Figure16)
Trang 295 Option : Changing from 3–Wire to 2–Wire DC Power
Figure 13: BEFORE - Top filter unit, front view for 3–wire system
Figure 14: AFTER - Top filter unit, front view for 2–wire system
Trang 30Figure 15: BEFORE - Top filter unit, rear view for 3–wire system
Figure 16: AFTER - Top filter unit, rear view for 2–wire system
Trang 316 Installing the Cable Tray
6 Installing the Cable Tray
:· normal floor and site cable tray lower than 2.60 meters· raised floorThis procedure applies to three standard cases:
normal floor and site cable tray higher than 2.60 metersnormal floor and site cable tray lower than 2.60 metersraised floor
All other cases are treated as specials and supplies have to be determined
on a site visit
Trang 326.1 Normal Floor and Site Cable Tray Higher than 2.60 Meters
1 : Normal floor
2 : Vertical cable tray
3 : Racktop cable trayFigure 17: Normal floor, site cable tray h > 2.60 m
Install the Cable Tray
Mountings on the Racks
1. Assemble the mountings ( 1 in Figure18) with the aluminium bars supplied( 2 in Figure18)
2 Mount all on the rack side panels ( see Figure18)
Figure 18: Cable tray support
Position the cable trays
Trang 336 Installing the Cable Tray
Figure 19: Top cable tray
Position the vertical
cable tray
5. Cut a length of cable tray ( 2 in Figure20) for the vertical connection withthe site cable tray ( 1 in Figure20)
6. Assemble using knuckles ( 3 Figure20)
7. Install two electrical interface earth braids between the cable trays Thesebraids should be positioned on the knuckles
Figure 20: Vertical cable tray
Trang 34Drill a hole in the site
cable tray
8. Make a 40 x 10 cm rectangular hole in the site cable tray, by the cable riser( 1 in Figure21)
Figure 21: Hole in the site cable tray
6.2 Normal Floor and Site Cable Tray Lower than 2.60 Meters
1 : Normal floor
2 : Site cable tray
A : Height of site cable trayFigure 22: Normal floor, site cable tray h < 2.60 m
Drill Holes in the Site
Cable Tray
1. Do not position the racktop cable tray mountings
2. Do not position the precut cable trays
3. On the site cable tray, make a 10 x 4 cm rectangular hole to run the powercables ( 1 in Figure23)
4. In the site cable tray, make a 70 x 4 cm rectangular hole to run the PCM andOMC-R cables ( 2 in Figure23)
5. Position the edge protection over the holes (use the corner protection of the
Trang 356 Installing the Cable Tray
Figure 23: Site cable tray
Position the Cable Tray
Mountings on the Rack
1. Assemble the mountings ( 1 in Figure25) with the aluminum bars supplied( 2 in Figure25)
2. Position these assemblies on the rack side panels without fastening them
NOTE : These mountings are not fastened but simply laid on the side panels.
Trang 36Figure 25: Cable tray support
Position the Cable Trays
on the Mountings
3. Fasten the precut cable trays to the two mountings ( 1 in Figure26)
4. Connect the earth braid ( 2 in Figure26) of the top structure to the cabletray
Figure 26: Top cable tray
Drill and Lay the Raised
Floor Tile for Running
the Cables
5. Cut a 52 cm length of angle section
6. Make a 52 x 6 cm rectangular hole in the raised floor tile
7. Fasten the angle section to the top of the tile using wood screws ( Figure27
, it will then be easier to fasten the cable tray)
Trang 376 Installing the Cable Tray
Figure 27: Drilling the tile
Position the Vertical
Cable Tray
8. Cut to length the cable tray for the vertical connection with the raisedfloor cable tray
9. Cut to length the angle section for separating the power cables
10. Fasten this angle section to the vertical cable tray
11. Assemble everything together using knuckles ( 3 in Figure28)
12. Install the earth braids for the electrical interface between the cable trays( 2 in Figure28)
Trang 38Figure 28: Vertical cable tray
Trang 396 Installing the Cable Tray
Put the Edge Protections 13. Position the edge protections ( 1 and 2 in Figure29)
Figure 29: Edge protection
Trang 417 Installing Power Cables
7 Installing Power Cables
The chapter describes the procedure to fit:
the earth cablr to the racksthe 48/60 Volts DC from the power cabinet to the racks
Verify that the circuit breakers are opened at the power cabinet
Check the fuse ratings (see SPP 27)Measure the voltages at the power cabinet , make sure the values are inthe specified range
Check that the rack breakers are OFF
Ensure that the rack is delivered in 3-wire system If it’s not the case, change itbefore apply this procedure
Trang 42Install the Power Bus
Cables in the Cable
3 Fasten the cables to the cable tray every 0.50 m using tie wraps.
Figure 30: Normal floor - Power supply cable running
Trang 437 Installing Power Cables
1 : Heat shrink sleeve
A : Length of spare cable (3 m)
B : Cable loop for over length (1 m)
Figure 32: The cable way is mounted to wait extension racks
Connect the Power
Cables to the Power
Cabinet
2 : BAT A or BAT B power cableFigure 33: Connecting power cable to the fuse holder
Trang 441 : Earth cable (ES/SG)
2 : 0 V cable (BATRET)
3 : -48 V cable (BAT A)
4 : -48 V cable (BAT B)
5 : Power cabinet signal ground
6 : Power cabinet electrical ground
Label the Cables
Figure 35: Power supply cable labeling
Mark the following text on cable (factory mounted clip) at fuse holder side:the number of the BSC on site:
BSC 01 for BSC number 01BSC 02 for BSC number 02
Trang 457 Installing Power Cables
the type of cable:
BAT A for the -48 VBAT B for the -48 VBAT RET for the O VES/SG for earth (green/yellow or black cable)
The power cabinet must be previously labeled by the customer
The number of the BSC is given in the site documentation; it does not depend
of the product generation
The ground black cable must be marked by yellow/green adhesive tape
Connect the Racks to
Power Bus
1 Remove the outer cable insulation (if the cable is double insulated)
2 Fit the cable clamps on power bus (to achieve good contact, do not remove
the conducting grease)
3 Tighten the nut correctly.
1 : Earth cable 3BK 07838 ANAA
2 : 0 V BATRET cable 3BK 07836 ANAA
3 : -48 V BAT A cable 3BK 07834 ANAA
4 : -48 V BAT B cable 3BK 07834 ANAAFigure 36: Connecting the external cable to the rack