All rights reserved Page 2Chapter 1 Preparation of OT Terminal Chapter 2 Preparation of Cold End Terminal Chapter 2 Preparation of Cold End Terminal...  Prepare the following tools: Po

Trang 1

01 August 2006

www.huawei.com

Internal

Training of Power

Cable Terminal

Preparation

Course No : EQA CM 001

Composer : Engineering Quality

Dept.

Trang 2

HUAWEI TECHNOLOGIES CO., LTD All rights reserved Page 2

Chapter 1 Preparation of OT Terminal

Chapter 2 Preparation of Cold End Terminal

Chapter 2 Preparation of Cold End Terminal

Trang 3

Prepare the following

tools: Power cable

crimper, power cable,

insulation tape,

paper knife, cable

cutter, and OT

terminal.

OT termin

al

Power cable crimpe

r

Trang 4

HUAWEI TECHNOLOGIES CO., LTD All rights reserved Page 4

Stripping

Step 1: Use the paper knife to

strip off the insulation skin of the

power cable (Note: The length of

exposed conductor must be one

to two millimeters longer than

the tube of the OT terminal.)

Trang 5

Step 2: Sheath the power

cable with the OT terminal

(Note: The length of exposed

conductor must be one to two

millimeters longer than the

tube of OT terminal.)

Trang 6

HUAWEI TECHNOLOGIES CO., LTD All rights reserved Page 6

Crimping

crimper to crimp the OT

terminal onto the power cable

(Note: Generally you need to

crimp twice to ensure that the

OT terminal is crimped reliably.)

Trang 7

Wrapping

Step 4: Wrap the well-crimped

OT terminal with insulation tape

Requirement: The lugs and naked

wires of the power cable and

ground cable must be wrapped

with tubes or insulation tapes

No copper wire can be exposed at

the lug or terminal Installation

order of the flat washer and

spring washer must be correct

(Note: The length of the insulation tape wrapped on the conductor cannot be too long Otherwise, the terminal cannot be in good contact upon installation.)

Trang 8

HUAWEI TECHNOLOGIES CO., LTD All rights reserved Page 8

End of Preparation of OT Terminal

Trang 9

Chapter 1 Preparation of OT Terminal

Chapter 2 Preparation of Cold End Terminal

Trang 10

HUAWEI TECHNOLOGIES CO., LTD All rights reserved Page 10

Tools

Prepare the following tools:

Power cable crimper, power

cable, insulation tape, paper

knife, cable cutter, and cold

end terminal.

cold end terminal

Trang 11

Stripping

Step 1: Use the paper knife

to strip off the insulation skin

(Note: When stripping the

insulation skin of the power

cable, you need to strip 12 to

15mm more of the external

water-proof layer than the

inner fire-proof layer.)

Trang 12

HUAWEI TECHNOLOGIES CO., LTD All rights reserved Page 12

Sheathing

Step 2: Sheath the power

cable with the cold end

terminal.

Trang 13

Crimping

Step 3: Use the power cable

crimper to crimp the cold end

terminal onto the power cable

and then use the cable cutter

to trim off the extruding

conductor of the power cable

on the cold end terminal

Trang 14

www.huawei.com Thank You