1. Trang chủ
  2. » Kỹ Thuật - Công Nghệ

BIỆN PHÁP THI CÔNG MÁY BIẾN ÁP TIẾNG ANH

43 4 0

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Tiêu đề Biện Pháp Thi Công Máy Biến Áp
Định dạng
Số trang 43
Dung lượng 1,88 MB
File đính kèm BPTC MÁY BIẾN ÁP.rar (2 MB)

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Nội dung

METHOD STATEMENT OF TRANSFORMER – SW GEAR NỘI DUNG TABLE OF CONTENTS 51 AIM MỤC TIÊU 52 SCOPE OF WORKS PHẠM VI CÔNG VIỆC 53 REFERENCES THAM KHẢO 54 QUALITY CONTROL QUẢN LÝ CHẤT LƯỢNG 54 1 Purpose Scope Mục đích Phạm vi 54 2 Definition Định nghĩa 64 3 Process Flow Chart for the Work Plan Procedure Sơ đồ cho quy trình thực hiện công việc 74 4 Procedure Quy trình 74 5 Material Control Quản lý Vật tư 74 5 1 Purpose Mục đích 74 5 2 Scope Phạm vi 84 5 3 Responsibility Trách nhiệm 84.

Trang 1

METHOD STATEMENT

OF

TRANSFORMER – SW GEAR.

Trang 2

NỘI DUNG / TABLE OF CONTENTS

1 AIM / MỤC TIÊU 5

2. SCOPE OF WORKS / PHẠM VI CÔNG VIỆC 5

3 REFERENCES/ THAM KHẢO 5

4 QUALITY CONTROL/ QUẢN LÝ CHẤT LƯỢNG 5

4.1 PURPOSE/ SCOPE/ MỤC ĐÍCH/ PHẠM VI: 5

4.2 DEFINITION/ ĐỊNH NGHĨA 5

4.3 PROCESS FLOW CHART FOR THE WORK PLAN PROCEDURE/ SƠ ĐỒ CHO QUY TRÌNH THỰC HIỆN CÔNG VIỆC : 6

4.4 PROCEDURE/ QUY TRÌNH 7

4.5. MATERIAL CONTROL/ QUẢN LÝ V ẬT TƯ 7

4.5.1 Purpose/ Mục đích 7

4.5.2 Scope/ Phạm vi 7

4.5.3 Responsibility/ Trách nhiệm 8

4.5.4 GENERAL/ TỔNG QUAN 8

4.5.5 RECEIVING/ TIẾP NHẬN 9

4.5.6 STORAGE/ LƯU KHO 9

4.5.7 MARKING/ ĐÁNH DẤU 10

4.5.8 METHODS/ PHƯƠNG PHÁP 10

5 MATERIAL/ VẬT TƯ 10

6 PREPARATION/ CHUẨN BỊ 10

6.1 MACHINERIES & TOOL/ MÁY MÓC THIẾT BỊ & DỤNG CỤ: 10

6.2 SCAFFOLDING & LADDER/ GIÀN GIÁO & THANG : 11

6.3. RECEIVING, HANDLING AND STORAGE / TIẾP NHẬN , BỐC DỠ VÀ LỮU TRỮ 11

6.3.1 Receiving / Tiếp nhận: 11

6.3.2. Handling / Bốc dỡ 12

6.3.3 Moisture protection during storage / Bảo quản trong khi lưu trữ 12

7 INSTALLATION WORK/ CÔNG VIỆC LẮP ĐẶT 13

7.1 GENERAL / TỔNG QUÁT 13

7.1.1 Checking elements / Kiểm tra các cấu kiện 13

7.1.2 Correct installation sequence / Quy trình lắp đặt đúng 13

7.1.3 Joining elements Lắp ráp các cấu kiện 13

7.1.4 Checking the assembled elements Kiểm tra các kết cấu đã lắp ráp 13

7.1.5 Closing the junctions / Đậy các điểm đấu nối 13

7.2 INSTALLING A BUSBAR RUN / LẮP ĐẶT MÔ HÌNH THANH DẪN ĐIỆN 13

7.3 INSTALLATION RECOMMENDATION./ KHUYẾN CÁO LẮP ĐẶT 14

7.4 ATTACHING FIXING MATERIAL./ GẮN CÁC LINH KIỆN GHÉP NỐI 14

7.4 1 Overview / Tổng quan 14

7.4.2 Bracket for horizontal installation./ Giá treo cho kiểu lắp ngang 15

7.4.3 Spring brackets for vertical installation on walls./ Giá đỡ gắn tường kiểu đứng 19

7.4.4 Mounting the busbar trunking system on a bracket for vertical installation./ Gắn hệ thống thanh dẫn điện trên 1 giá đỡ kiểu đứng 20

7.4.5 Floor fixing for spring brackets./ Giá đỡ gắn sàn kiểu đứng 21

Trang 3

7.4.6 Fixing brackets with fixed point for vertical installation./ Các mối ghép cố định thẵng đứng 22

7.5. JOINING ELEMENTS LẮP RÁP CÁC CẤU KIỆN 24

7.5.1 Connecting elements by joining the ends together using the joining tool./ Lắp ráp các kết cấu bằng cách ghép nối các phần cuối thanh dẫn điện với nhau 24

7.5.2. Joining from above, below or the side, without joining tool./ ắp ráp từ phía trên, phía dưới hoặc phía hông, không dùng dụng cụ ghép 27

7.6. EXPANSION UNIT./ BỘ PHẬN GIÃN NỞ 29

7.7. FLANGED END./ ĐẦU NỐI 30

7.7.1. General./ Tổng quan 30

7.7.2 Installation./ Lắp đặt 30

7.7.3 Handling if multiple busbar runs are laid in parallel./ Xử lý khi đấu nối song song nhiều thanh dẫn điện 32

7.8. TRANSFORMER CONNECTION./ ĐẤU NỐI VỚI MÁY BIẾN ÁP 33

7.8.1 Transformer terminal connection element./ Kết cấu đấu nối với tram biến áp 33

7.8.2 Positioning the transformer terminal connection element above the transformer./ Định vị kết cấu đấu nối với trạm biến áp phía trên máy biến áp 33

7.8.3 Attaching the transformer terminal connection element at the installation location./ Chằng buộc kết cấu đấu nối trạm biến áp tại địa điểm lắp đặt 33

7.9. TAP OFF UNIT./ HỘP ĐẤU NỐI ĐIỆN 34

7.9.1 Tap off unit from 50A to 630A./ Các phụ tải từ 50A-630A 34

7.9.2 Tap off unit from 800A to 1250A./ Các phụ tải từ 800A đến 1250A 35

7.9.3. Lateral mounting of tap off units above 400A in horizontal layout./ Nối các phụ tải trên 400A theo mặt hông trên sơ đồ lắp ngang 36

8. INSPECTION FOR INSTALLATION WORKS / KIỂM TRA CÁC CÔNG VIỆC LẮP ĐẶT 37

9. TESTING AND COMMISSIONING / THỬ NGHIỆM VÀ VẬN HÀNH THỬ NGHIỆM 37

9.1 VISUAL AND MECHANICAL INSPECTION / KIỂM TRA TRỰC QUAN VÀ LIÊN KẾT CƠ KHÍ 37

9.2 ELECTRICAL TESTS / CÁC THỬ NGHIỆM ĐIỆN 37

10 SAFETY METHOD/ PHƯƠNG PHÁP AN TOÀN 38

10.1 GENERAL/ TỔNG QUAN 38

10.2 WORKING AT ELEVATED AREA/ LÀM VIỆC Ở KHU VỰC CAO: 39

10.3 WORKING WITH ELECTRICAL EQUIPMENTS/ LÀM VIỆC VỚI CÁC THIẾT BỊ ĐIỆN 39

11 COMPLETION STATUS / TÌNH TRẠNG HOÀN THÀNH 39

- Base on Construction drawings issued by Client & Consultant The Contractor shall provide the shop drawing with detail of Installation method for every item of works

Trang 4

as well as the relevant standard and codes.

- The Method Statement describes the necessary procedure to follow in order to ensure thatthe installation works are executed safely and in accordance with the Contract requirements, andthat all quality assurance/control activities are conducted in a systematic manner, withinspections and conformance verified and documented

WORKS SPECIFICATIONS

The following standards are applicable to this method statement and Tender Clarifications

- Plumbing, Drainage & Sanitary ware System MEP Specification: Division 22

- HVAC System MEP Specification: Division 23

- Low Voltage(LV) Electrical System MEP Specification: Division 26

- Extra Low Voltage(ELV) Electrical System MEP Specification: Division 27,28

RISK ASSESSMENT / JOB HAZARD ANALYSIS (JHA)

For the Risk Assessment please refer to the approved Environmental Management Plan(Table 1):

Trang 5

Control person

Safety Install anchor bolt Drills concrete,

Brick wall

Dust that produce during drilling work might spread out and effect vision while

at work

High

Make sure that all personal protection equipment (PPE) be provided on site before starting

of work such as helmet, safety glasses, glove, etc

HSE Staff

Safety Install Support& Cable

Ladder – Tray - Trunking

Working at heights exceeding

3 meter

workers may fall down High

Scaffold that use at site have to

be inspected by safety supervisorbefore use Defective scaffolds will not be allowed to use for works

HSE Staff

Safety Pulling cable

Working at heights exceeding

3 meter

workers may fall down High

Scaffold that use at site have to

be inspected by safety supervisorbefore use Defective scaffolds will not be allowed to use for works

HSE Staff

Safety Pulling cable Heavy and long

Make sure that all personal protection equipment (PPE) be provided on site before starting

of work such as helmet, safety glasses, glove, etc

HSE Staff

Safety Install conduit working at

heights exceeding

3 meters

workers may fall down High Make sure that all personal

protection equipment (PPE) be provided on site before starting

HSE Staff

Trang 6

Side

Assess the Situation Solution

Control person

of work such as helmet, safety glasses, glove, etc

Safety Install Panel Board drills concrete,

of work such as helmet, safety glasses, glove, etc

(Safety Manager)

Make sure that enough condition

be provided on site before starting of work such as lighting, protection equipment (PPE)

HSE Staff

Dust and

Mud

Dust generation from

loading and unloading/

transport of materials

Materials storage works

Reduction of local air quality, malodours and visual impairment

High

Cover the vehicle by tarpaulins, sprinkle water, enforce speed limit rules

HSE Staff

Noise Install work

Chipping, cutting,drills concrete, brick

Poor public industrial relations Complaints from legal authority

High Use cover wall, mufflers or

silencers to reduce noise HSE Staff

Noise Loading and unloading

of lorries

Material transportation

Poor public industrial relations Complaints from legal authority

High Arrange deliveries to suit the

area Minimize the drop height

(Safety Manager)

Water

pollution

Disposing of washout

from relate work

concrete around the site

Chipping, cutting,drills concrete, brick

Destruction of

sewerage works

High

Restrict use water in chipping,

cutting concrete, brick, tools cleaning within the site and

designate the area for the same

HSE Staff

Trang 7

Side

Assess the Situation Solution

Control person

into area recyclable

HSE Staff

Air

pollution

Dust from cutting,

grinding, grouting and

packing

Chipping, cutting,drills concrete

Reduction of local air quality, malodours and visual impairment

Air

pollution

Poor handling and

storage of materials such

as stockpiling sand

Material storage

works

Reduction of local air

quality, malodours and visual impairment

High Cover all dust generating

materials, sprinkle water HSE Staff

Cross contamination of land, air, ground and surface waters

High

Clean work area, move material and moved recyclable and waste packing materials into area recyblable

HSE Staff

Land

pollutio Install conduit

Chipping, cutting, drills concrete, brick

Cross contamination of land, air, ground and

surface waters

Medium

Cleaned area work, move material and moved recyclable

into area recyclable

into area recyclable

HSE Staff

Trang 8

- Risk assessment shall be carried out to ensure that potential hazards can be identified andsubsequently safety control measures are implemented to eliminate or to reduce the hazardsidentified:

- STEP 1: Break down the construction activities into various stages of work This taskshall be carried out as part of the pre-planning phase of work

- STEP 2: Identify the potential hazards associated with each phase of work and evaluateits risk occurrence based on the risk matrix

- STEP 3: Safety control measures shall be implemented to eliminate or reduce the risksidentified All reasonably practicable measures must be taken to eliminate any foreseeable risk toany person If the risk cannot be eliminated, safety measures must be taken to minimize the risk.Some measures to minimize the risks are listed in the figure below They are listed in decreasingorder of preference, i.e from most preferred to least preferred

Figure 1 Safety Hierarchy of Control

INSPECTION & TESTING PLAN (ITP)

Trang 9

GENERAL

- All required testing and inspection will be detailed in the Inspection and Testing PlanTable as follow The ITP will also detail all acceptance criteria plus approving body at each stage

of inspection and test being carried out

- Beyond the external inspection to be carried out with the Engineer, an ad-hoc internalinspection system will be adhered to ensure minimum reworks and minimize conditions of workrejections

Trang 10

Electrical Inspection and Test Plan Matrix (General)

Division Description

Factory Witness Testing/Inspecti on

Equipment/

Material Delivery Inspection

Installation Inspection

Commissionin

g Test / Operating &

Performance Tests

Endurance

Inspection

Test On Completion

All Control Document

Factory Witness Testing/Inspectio

n Procedure

Materilas &

Equipment approved

Method of Statement forInstallation

Method of Statement for Testing &

Commissioning

Method of Statement for Endurance Test

Test On Completion Procedure

Factory Witness Testing/Inspectio

n Checklist

Equipment/

Material Delivery Inspection Checklist

Field Inspection Checklist

Testing and CommissioningTest Report

Endurance Test Report

Tests On Completion Report

All Frequency *Refer to Testingand Training

Requirement

Once per Delivery

As per Works Program

Once per Area/

Floor/ Building

or System

Once per Completed System

Once per Completed System

Medium voltage cable

Low voltage cable

Trang 11

Equipment/

Material Delivery Inspection

Installation Inspection

Commissionin

g Test / Operating &

Performance Tests

Endurance Testing / Inspection

Test On Completion

Grounding / Lightning Protection

Trang 12

Method Statement, Material &

Equipment, Shop Drawing

Prepare Document by Engineers

Submit to Consultant

QC Check

Trang 14

2.B.11.1 INSTALLATION MAINFEEDER WORKS (CABLE LADDER - TRAY –

TRUNKING, CABLE RACK)

2.B.11.1.1 General Description

- This Method Statement only covers works relating to areas having cables supported onCable Ladders, Cable Trays& Trunking Works will be carried out based on constructionschedule and approved Shop Drawings The objective is to Safety and correctly installs inaccordance with the approved Safety Plan and the Specification requirements The CableLadder, Cable Tray and Trunking will be installed to their designated location as shown on theapproved Shop Drawings The works shall be coordinated with other construction activities onthe Site, as necessary and in accordance with the Plans, Drawings, Specification and allrelevant Standards Upon completion of the Works, the site will be cleaned as necessary toensure the smooth execution of other construction activities

- All of Indoor Cable Ladder, Cable Tray and Trunking in this project are PowederCoated type (except Warehouse)

- All of Outdoor Cable Ladder, Cable Tray and Trunking in this project are Hot deptgalvanized type (included Warehouse)

2.B.11.1.2 Site Planning & Preparation

The following activities will be conducted before starting the works:

- Scaffolds and “A” Ladder that are to be used on site will be inspected and deem safe bythe Contractor's Safety Supervisor before use Defective scaffolds will not be allowed to usefor the works Tagging will be provided by the contractors Guard rails will be provided whenworking at height exceeding 3 meters

- ‘A’ ladders when used against a wall shall not form an angle greater than 30 fromvertical All ‘A’ ladder when in used must be fully extended with the safety catch engaged

- Workers will be briefed on how to properly handle and pull cable following the correctsequencing of work execution

- The workers will be briefed about Safety manner

- After Cable support system is erected, it will be cleaned, inspected & approved beforestarting the works

- Confirm Anchor bolt / Insert layout is ready for installation

- Prepare the threaded rods (hot dipped galvanized) and cut to necessary length withspeed cutter Remove all sharp edges after cutting

- The workers at both side of Cable Duct, Cable Ladders, Tray & Trunking will becoordinated as necessary

Trang 15

- When Cable Ladder, Cable Tray & Trunking are to be cut, the ends will be checked andrepainted by same materials for painting

2.B.11.1.3 Work Methodology

2.B.11.1.3.1 Installation of cable tray/ trunking hang from concrete slab

Typical detail of installation of cable tray/ ladder on ceiling

- The installation of Anchor bolt/ Insert will be as per approved Shop Drawing

- Confirming Anchor bolt & Insert layout in position

- Cut the required length of galvanized threaded rod support, sharp edges of the rod will

be cleaned before installation

- Double nuts and washer will be install according to approved Method Statement

- Check the actual installation after installed the hanger / support

- Actual length of galvanized threaded rod for installation will be determined

- Ensure that the double nuts and washer properly tightened

- Ensure the both ends of the unistrut are cleaned and no sharp edges

- Install bracket support for cable tray/ ladder

- Install cable tray/ ladder on support

- Connect earth-link at expansion joint on cable tray/ ladder

2.B.11.1.3.2 Installation of cable tray/ trunking hang from roof purlin

- Provide the lifter (or scaffold for available area)

Trang 16

- Marking exactly the locations for fixing clamp as indicated in approved shop drawing

- Drill holes and install U-clamp, max distance beween clamps is 1.200mm

- Cut the required length of galvanized threaded rod support, sharp edges of the rod will

be cleaned before installation

- Double nuts and washer will be install according to approved Method Statement

- Check the actual installation after installed the hanger / support

- Actual length of galvanized threaded rod for installation will be determined

- Ensure that the double nuts and washer properly tightened

- Ensure the both ends of the unistrut are cleaned and no sharp edges

- Install bracket support for cable tray/ ladder

- Install cable tray/ ladder on support

- Connect earth-link at expansion joint on cable tray/ ladder

Trang 17

2.B.11.1.3.3 Installation of cable ladder on the wall and riser

Installation of cable tray/ ladder on the wall and riser

- Setting layout for Anchor bolt as per approved Shop Drawing

- Marking the concrete/brick wall before drilling as per approved Shop Drawing

- Blow out dust and fragments from the holes after drilled

- Used appropriate tools like hammer and setting tool for installing Anchor bolt orExpansion bolt

Trang 18

- Angular support will be installed after drilled the holes for Anchor bolt

- Installation of Cable Ladder/Tray will be follow

- Install cable tray/ ladder on support

- Connect earth-link at expansion joint on cable tray/ ladder

2.B.11.1.3.4 Installation of cable ladder to DB panel

- Setting layout for Anchor bolt as per approved Shop Drawing

- Marking the concrete/brick wall before drilling as per approved Shop Drawing

- Blow out dust and fragments from the holes after drilled

- Used appropriate tools like hammer and setting tool for installing Anchor bolt orExpansion bolt

- Angular support will be installed after drilled the holes for Anchor bolt

- Installation of Cable Ladder/Tray will be follow

- Install cable tray/ ladder on support

- Connect earth-link at expansion joint on cable tray/ ladder

- Installation of cover after finishing cable works

- Seal up the gap between opening of DB panel and ladder

2.B.11.2 INSTALLATION PANEL WORKS

Trang 19

2.B.11.2.1 General Description

- This method statement covers works relating to areas having panel boards installed onconcrete walls, brick walls, dry walls and floor slab Works are carried out basing onconstruction schedule and detailed shop drawings The works will be carried out in a safemanner in accordance with the approved safety plan and the Specification requirements Thepanel board on wall will be installed to their designated location as shown on the approvedshop drawings The works will be coordinated with other construction activities on the site, asnecessary and in accordance with the approved Shop Drawings, Specification and all relevantstandards Upon completion of the work, the site will be cleaned as necessary to ensure thesmooth execution of other construction activities

2.B.11.2.2 Site Planning & Preparation

The following activities will be conducted before starting the works:

- Scaffolds that are to be used on site will be inspected for safety by the Contractor'sSafety Supervisor, before use Defective scaffolds will not be allowed to be used for the works.Tagging will be provided by the respective contractors Guardrails will be provided whenworking at heights exceeding 3 meters

- Workers will be briefed on how to properly handle and install Panel board followingthe correct sequence of work execution

- The workers will be briefed about safety matters

- Location panel board will be checked, following the approved shop drawings at theareas where the panel board are ready to be installed

- The actual size and type of panel board required for installation shall be determined

- The starting point for the panel board installation will be checked and inspected based

on the approved shop drawings

- The workers will be coordinated as necessary

- If the opening of the panel board has sharp edge, the opening will be treated so as to notdamage the cables

- After panel board is installed, it will be cleaned and inspected

Trang 20

- The actual panel boards needed for installation shall be determined

- The cable routing will be checked to be clear from any obstruction

- The manpower for the activities with complete electrical hand & tool will be mobilized

- The safety officer-in-charge will check the area to ensure no potential dangers arepresent and everything is safe for the installation

- The Panel boards shall be completely enclosed, self supporting vertical structuresbolted together to form a rigid single sheet metal enclosure Boards shall be provided withfront and rear channels The end, top and rear shall be covered with removable screw-on-steelplates of approved thickness Panel boards shall include all protective devices and equipment

as necessary for interconnection, instrumentation and controls and terminal blocks withmechanical type solderless connectors for terminals

- Panel boards shall be factory bake finished, all as the approved Metal surfaces shall bechemically cleaned and treated Chemical treatment shall provide a bond between paint andmetal surfaces and help prevent entrance of moisture and formation of rust under the paintfilm Protection Index, color and other construction details will be as generally approved

- Panel boards shall be locked and accessible only to authorized staff

- The panel boards will be designed, installed and maintained in such way to be free ofmoisture and humidity

- Panel boards shall be completely assembled with all switchgear and wired at thefactory Thorough inspection shall be made before and after assembly to ensure correctness ofdesign and workmanship

- All cable entries shall be with cable glands or any other system fully reviewed andapproved by the Engineer, to provide secure fixings without stress on cable cores and preventthe intrusion of objects or rodents

- Busbar structure shall be arranged to permit future extension It shall be mounted oninsulator supports or high impact, non-tracking high quality insulation material and adequatelybraced to withstand the mechanical forces exerted during asymmetrical short circuit Bus barsshall be silver plated copper Branch circuit bushing shall connect directly to the bus structure.All bus work shall consist of sufficient copper to limit temperature up to 40°C ambienttemperature

- All ironmongery and other hardware shall have suitable protective finish as approved

- Anchor bolts, anti vibration bases and vibration isolators, all foundation pads, supports,hangers, fixtures and fixings materials shall be provided as necessary

- Engraved metal nameplates shall be provided for each device The letters or numerals

on the nameplate shall be a minimum of 5 mm in height, with light colored, enameledcharacters on a dark background The legend on the strips shall be composed as to clearly

Trang 21

indicate the name of the feeder and/or panel board and/or equipment served by the protectivedevices, etc All elements and functions will be clearly labeled to ease Operation andMaintenance and avoid any risk of confusion or misunderstanding

- Ventilating louvers shall be provided on the doors, removable panel boards and otherlocations where required, -to allow natural circulation of air and to prevent undue temperaturerise Louvers shall be fitted with screens to prevent entry of insects and vermin

- Cable terminal mounting bolts and cable clamps to appropriate cable size shall beprovided

- Panel boards, circuit breakers and disconnecting switches shall be mounted as indicated

on the Drawings or so that the height of the operating handle at its highest position will notexceed 1.8 m from the floor

- Panel boards shall be connected to earthing system for protection

2.B.11.2.3.2 Installation of MV Switchgear, MSB panel and floor standing LV panels

Tools and materials such as panel board, anchor, hammer, markers, electric drill, trolley, meter,hand tools, etc, will be prepared before starting the works

Making Position

- Marking of position for MV Switchgear, MSB and floor standing LV panels on floor

- Check floor level of MV Switchgear, MSB and floor standing LV panels room, checkthe door height & wide

- Remove any remaining packing of MV Switchgear, MSB and floor standing LV panels Handling/Loading of MV Switchgear, MSB and floor standing LV panels

- Upon arrival, park the Lorry Crane at the designated parking location

- Barricade the Lorry Crane surrounding area including the MV Switchgear, MSB andfloor standing LV panels storage location

- Position the Lorry Crane, set-up outrigger and Boom Lift and hook-up the slings withshackle to lifting ring on the MV Switchgear, MSB and floor standing LV panels Thequalified rigger shall check all the lifting point to ensure that all the lifting points are properlyhook and tightened

- Tag lines are to be tie on the lifting point of MV Switchgear, MSB and floor standing

LV panels hook to prevent the MV Switchgear, MSB and floor standing LV panels fromswaying

Moving the enclosure panel of MV Switchgear, MSB and floor standing LV panels

- Using hand-lift to move the MV Switchgear, MSB and floor standing LV panels to thelocation

- The steel plate to maintain at above the kerb of the door

Ngày đăng: 21/06/2022, 15:09

TỪ KHÓA LIÊN QUAN

w