TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILTTENDER DỰ THẦU CHỦ ĐẦU TƯ - OWNER : NHÀ THẦU - CONTRACTOR: CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS ĐỊA CHỈ : 766/19-21
Trang 1CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
Minh
CHỦ ĐẦU TƯ - OWNER:
HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ĐỊA CHỈ-ADDRESS
NHÀ THẦU - CONTRACTOR:
BÀ HUỲNH THỊ KIM DUNG
BIỆN PHÁP THI CÔNG
Trang 2HIỆU CHỈNH / REVISION
STT/NO NGÀY/DATE NỘI DUNG/CONTENTS 01
02 03 04
TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
TENDER - ĐẤU THẦU
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
DANH MỤC BẢN VẼ
DANH MỤC BẢN VẼ
SỐ HIỆU BẢN VẼ TÊN BẢN VẼ
MS-2008 GIAI ĐOẠN 8 MS-2008a MẶT CẮT GIAI ĐOẠN 8 MS-2009 GIAI ĐOẠN 9
MS-2009a MẶT CẮT GIAI ĐOẠN 9 MS-2010 GIAI ĐOẠN 10
MS-2010a MẶT CẮT GIAI ĐOẠN 10 MS-2011 GIAI ĐOẠN 11
MS-2011a MẶT CẮT GIAI ĐOẠN 11 MS-2012 GIAI ĐOẠN 12
MS-2012a MẶT CẮT GIAI ĐOẠN 12 MS-2013 GIAI ĐOẠN 13
MS-2013a MẶT CẮT GIAI ĐOẠN 13 MS-2014 GIAI ĐOẠN 14
MS-2014a MẶT CẮT GIAI ĐOẠN 14 MS-2015 GIAI ĐOẠN 15
MS-2015a MẶT CẮT GIAI ĐOẠN 15 MS-2016 GIAI ĐOẠN16
MS-2016a MẶT CẮT GIAI ĐOẠN 16 MS-2017 GIAI ĐOẠN 17
MS-2017a MẶT CẮT GIAI ĐOẠN 17 MS-3000 BIỆN PHÁP THI CÔNG PHẦN THÂN MS-3001 GIAI ĐOẠN 1
MS-3002 GIAI ĐOẠN 2 MS-3003 GIAI ĐOẠN 3 MS-3004 GIAI ĐOẠN 4 MS-3005 GIAI ĐOẠN 5 MS-4000 BIỆN PHÁP THI CÔNG CỘT ĐIỂN HÌNH MS-5000 BIỆN PHÁP THI CÔNG DẦM SÀN ĐIỂN HÌNH
Trang 3NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG
ASCONS
ĐỊA CHỈ: 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
CHỦ ĐẦU TƯ -OWNER:
DỰ ÁN - PROJECT
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI BÀ
TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
BÀ HUỲNH THỊ KIM DUNG
ĐỊA CHỈ: 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
TỔ CHỨC THI CÔNG
Trang 4HIỆU CHỈNH / REVISION
STT/NO NGÀY/DATE NỘI DUNG/CONTENTS 01
02 03 04
TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
TENDER - ĐẤU THẦU
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
VỊ TRÍ DỰ ÁN
VỊ TRÍ DỰ ÁN
147-147bis HAI BÀ TRƯNG, PHƯỜNG 6, QUẬN 3, TP.HCM
QUY MÔ:
Trang 5TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
PROJECT PACKAGE NO NGÀY GIAO - ISSUE DATE TỶ LỆ - SCALE
1/100
TENDER - ĐẤU THẦU
Rev00
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
22/05/2021 9:24:14 AM
MẶT BẰNG TỔNG THỂ DỰ ÁN
MS-1002
MẶT BẰNG TỔNG THỂ DỰ ÁN
Trang 6CỔNG CHÍNH 1
HÀNG RÀO TẠM 2
CẨU THÁP 4
SÀN THAO TÁC 5
LAN CAN AN TOÀN 7
BÃI GIA CÔNG THÉP 8
HIỆU CHỈNH / REVISION
STT/NO NGÀY/DATE NỘI DUNG/CONTENTS 01
02 03 04
TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
TENDER - ĐẤU THẦU
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
MẶT BẰNG TỔ CHỨC THI CÔNG MẶT BẰNG TỔ CHỨC THI CÔNG
1
2
3 2
2 2
7
Trang 7CỔNG CHÍNH 1
HÀNG RÀO TẠM 2
TRẠM ĐIỆN TẠM PHỤC VỤ THI CÔNG 3
CẨU THÁP 4
SÀN THAO TÁC 5
HỆ SHORING 6
LAN CAN AN TOÀN 7
BÃI GIA CÔNG THÉP 8
ĐÈN CHIẾU SÁNG PHỤC VỤ THI CÔNG 9
TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
PROJECT PACKAGE NO NGÀY GIAO - ISSUE DATE TỶ LỆ - SCALE
1/100
TENDER - ĐẤU THẦU
Rev00
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
2 2
9
9
9
9
Trang 8CỔNG CHÍNH 1
HÀNG RÀO TẠM 2
CẨU THÁP 4
SÀN THAO TÁC 5
LAN CAN AN TOÀN 7
BÃI GIA CÔNG THÉP 8
HIỆU CHỈNH / REVISION
STT/NO NGÀY/DATE NỘI DUNG/CONTENTS 01
02 03 04
TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
TENDER - ĐẤU THẦU
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
MẶT ĐỨNG CỔNG CHÍNH MẶT ĐỨNG CỔNG CHÍNH
1 4
3
Trang 9SÀN THAO TÁC 5
HỆ SHORING 6
LAN CAN AN TOÀN 7
BÃI GIA CÔNG THÉP 8
ĐÈN CHIẾU SÁNG PHỤC VỤ THI CÔNG 9
TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
PROJECT PACKAGE NO NGÀY GIAO - ISSUE DATE TỶ LỆ - SCALE
1/100
TENDER - ĐẤU THẦU
Rev00
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
Trang 10CỔNG CHÍNH 1
HÀNG RÀO TẠM 2
CẨU THÁP 4
SÀN THAO TÁC 5
LAN CAN AN TOÀN 7
BÃI GIA CÔNG THÉP 8
HIỆU CHỈNH / REVISION
STT/NO NGÀY/DATE NỘI DUNG/CONTENTS 01
02 03 04
TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
TENDER - ĐẤU THẦU
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
3D VIEW 1 3D VIEW 1
5
7
7 6
6
6 7
8
2
2
9 9
9
Trang 11TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
PROJECT PACKAGE NO NGÀY GIAO - ISSUE DATE TỶ LỆ - SCALE
1/100
TENDER - ĐẤU THẦU
Rev00
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
22/05/2021 9:24:19 AM
MẶT BẰNG BỐ TRÍ ĐIỆN NƯỚC TẠM
MS-1008
MẶT BẰNG BỐ TRÍ ĐIỆN NƯỚC TẠM
ĐIỆN TẠM PHỤC VỤ THI CÔNG
NƯỚC TẠM PHỤC VỤ THI CÔNG
TỦ ĐIỆN TẠM
Trang 12HIỆU CHỈNH / REVISION
STT/NO NGÀY/DATE NỘI DUNG/CONTENTS 01
02 03 04
TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
TENDER - ĐẤU THẦU
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
MẶT BẰNG HỆ SHORING LỚP 1
MẶT BẰNG HỆ SHORING LỚP 1
SHORING LỚP 1 (H400) Ở CAO ĐỘ -1.400 KINGPOST H400, ĐỈNH KINGPOST Ở CAO ĐỘ -0.850
SHORING (H400) KINGPOST (H400)
Trang 13TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
PROJECT PACKAGE NO NGÀY GIAO - ISSUE DATE TỶ LỆ - SCALE
1/100
TENDER - ĐẤU THẦU
Rev00
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
SHORING (H400) KINGPOST (H400)
Trang 14HIỆU CHỈNH / REVISION
STT/NO NGÀY/DATE NỘI DUNG/CONTENTS 01
02 03 04
TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
TENDER - ĐẤU THẦU
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
MẶT CẮT HỆ SHORING
MẶT CẮT HỆ SHORING
SHORING LỚP 1 (H400) Ở CAO ĐỘ -1.400 SHORING LỚP 2 (H400) Ở CAO ĐỘ -4.500 SHORING LỚP 3 (H400) Ở CAO ĐỘ -7.700
Trang 15NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG
ASCONS
ĐỊA CHỈ: 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
CHỦ ĐẦU TƯ -OWNER:
DỰ ÁN - PROJECT
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI BÀ
TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
BÀ HUỲNH THỊ KIM DUNG
ĐỊA CHỈ: 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
BIỆN PHÁP THI CÔNG PHẦN HẦM
Trang 16HIỆU CHỈNH / REVISION
STT/NO NGÀY/DATE NỘI DUNG/CONTENTS 01
02 03 04
TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
TENDER - ĐẤU THẦU
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
GIAI ĐOẠN 1 GIAI ĐOẠN 1
TƯỜNG VÂY DÀY 600
THI CÔNG TƯỜNG VÂY
THI CÔNG CỌC KHOAN NHỒI
Trang 17TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
PROJECT PACKAGE NO NGÀY GIAO - ISSUE DATE TỶ LỆ - SCALE
1/100
TENDER - ĐẤU THẦU
Rev00
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
22/05/2021 9:24:23 AM
MẶT CẮT GIAI ĐOẠN 1
MS-2001a
MẶT CẮT GIAI ĐOẠN 1
THI CÔNG TƯỜNG VÂY
THI CÔNG CỌC KHOAN NHỒI
MẶT ĐẤT TỰ NHIỆN ±0.000
Trang 18HIỆU CHỈNH / REVISION
STT/NO NGÀY/DATE NỘI DUNG/CONTENTS 01
02 03 04
TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
TENDER - ĐẤU THẦU
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
GIAI ĐOẠN 2 GIAI ĐOẠN 2
KINGPOST H400 ĐỈNH Ở CAO ĐỘ -0.850
LẮP ĐẶT KINGPOST TẠI VỊ TRÍ CỌC VÂY
Trang 19TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
PROJECT PACKAGE NO NGÀY GIAO - ISSUE DATE TỶ LỆ - SCALE
1/100
TENDER - ĐẤU THẦU
Rev00
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
Trang 20HIỆU CHỈNH / REVISION
STT/NO NGÀY/DATE NỘI DUNG/CONTENTS 01
02 03 04
TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
TENDER - ĐẤU THẦU
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
GIAI ĐOẠN 3
GIAI ĐOẠN 3
ĐÀO ĐẤT TỚI CAO ĐỘ -2.000 -2.000
Trang 21TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
PROJECT PACKAGE NO NGÀY GIAO - ISSUE DATE TỶ LỆ - SCALE
1/100
TENDER - ĐẤU THẦU
Rev00
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
Trang 22HIỆU CHỈNH / REVISION
STT/NO NGÀY/DATE NỘI DUNG/CONTENTS 01
02 03 04
TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
TENDER - ĐẤU THẦU
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
Trang 23TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
PROJECT PACKAGE NO NGÀY GIAO - ISSUE DATE TỶ LỆ - SCALE
1/100
TENDER - ĐẤU THẦU
Rev00
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
Trang 24HIỆU CHỈNH / REVISION
STT/NO NGÀY/DATE NỘI DUNG/CONTENTS 01
02 03 04
TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
TENDER - ĐẤU THẦU
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
GIAI ĐOẠN 5
GIAI ĐOẠN 5
LẮP ĐẶT SÀN THAO TÁC LẮP ĐẶT CẨU THÁP
CẨU THÁP SÀN THAO TÁC
-2.000
LAN CAN AN TOÀN
Trang 25TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
PROJECT PACKAGE NO NGÀY GIAO - ISSUE DATE TỶ LỆ - SCALE
1/100
TENDER - ĐẤU THẦU
Rev00
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
SÀN THÁO TÁC TẤM THÉP THÉP H250@2000 THÉP H350a2500 THÉP 2H400, GÁC LÊN KINGPOST
-2.000
HỆ SHORING LỚP 1( H400) Ở CAO ĐỘ -1.400
Trang 26HIỆU CHỈNH / REVISION
STT/NO NGÀY/DATE NỘI DUNG/CONTENTS 01
02 03 04
TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
TENDER - ĐẤU THẦU
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
Trang 27TENDER REFERENCE PRELIMINARY FOR APPROVAL FOR CONSTRUCTION REVISED AS-BUILT
TENDER
DỰ THẦU
CHỦ ĐẦU TƯ - OWNER :
NHÀ THẦU - CONTRACTOR:
CÔNG TY CỔ PHẦN XÂY DỰNG ASCONS
ĐỊA CHỈ : 766/19-21 Lạc Long Quân, Phường 9, Quận Tân Bình, Thành phố Hồ Chí Minh
TÊN BẢN VẼ - DRAWING TITLE
PROJECT PACKAGE NO NGÀY GIAO - ISSUE DATE TỶ LỆ - SCALE
1/100
TENDER - ĐẤU THẦU
Rev00
METHOD STATEMENT
BÀ HUỲNH THỊ KIM DUNG
VĂN PHÒNG LÀM VIỆC TẠI SỐ 147-147BIS, ĐƯỜNG HAI
BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM
ADDRESS : 147-147BIS, ĐƯỜNG HAI BÀ TRƯNG PHƯỜNG 6, QUẬN 3, TP.HCM