Construction arrangement For ensuring the construction progress schedule and construction quality required by the Employer and basing on the quantities of works to be completed and site

Trang 1

NGAI SECTION

EXPRESSWAY CONSTRUCTION METHODS

(Including construction method for Thruway, Ha Lam IC, Parking Area, Cross

-Frontage road and Miscellaneous Works)

Trang 2

NGAI SECTION

TABLE OF CONTENTS

A GENERAL CONSTRUCTION PLAN

B METHOD STATEMENT DETAIL

CHAPTER I: METHOD STATEMENT FOR ROAD

I SITE CLEARING, GRUBBING, EXCAVATION TOP SOIL

II EXCAVATION III ROCK BLASTING

IV EMBANKMENT

V CONSTRUCTION SUB - BASE AND BASE COURSE

VI CONSTRUCTION ASPHALT CONCRETE PAVEMENT, ASPHALT TREATED BASE COURSE

VII PORTLAND CEMENT CONCRETE PAVEMENT VIII BITUMINOUS SURFACE TREATMENT

CHAPTER II: CONSTRUCTION METHOD FOR DRAINAGE SYSTEM

I DETAIL CONSTRUCTION METHOD FOR PILE CULVERT, BOX CULVERT AND UNDERPASS BOX CULVERT

II DETAIL CONSTRUCTION METHOD FOR SIDE DRAINAGE AND SLOPE DRAINAGE

III DETAIL CONSTRUCTION METHOD FOR IMPROVEMENT AND RELOCATION OF EXISTING IRRIGATION CHANNELS.

IV DETAIL CONSTRUCTION METHOD FOR CATCH BASINS, MANHOLES, INLETS, AND OUTLETS.

CHAPTER III METHOD STATEMENT FOR OTHER ITEMS

I CONSTRUCTION MSE WALL

II SODDING AND PLANTING III OTHER MISCELLANEOUS

Trang 3

NGAI SECTION

A.GENERAL CONSTRUCTION PLAN

I General Requirements

Having studying the Bidding Documents issued, prevail regulation on quality control and construction supervision of construction works, our Bidder will

propose the proper plan for construction and completion of Work of this Package

in compliance with the conditions of contract

II Construction organization plan

The section from KM32+600 - KM42+000 with 9.4 km in length, The Bidder will arrange temporary road for construction Construction progress will be

construction simultaneously over all section of line

1 Construction arrangement

For ensuring the construction progress schedule and construction quality required by the Employer and basing on the quantities of works to be completed and site conditions, the construction lines are proposed to arrange as follows:

Constructions Line 01: From Km32+600 to Km35+447

Constructions Line 02: From Km35+447 to Km38+000 included parking area

Constructions Line 03: From Km38+000 to Km40+300;

Constructions Line 04: From Km40+300 to Km42+000 included Ha Lam interchange

The Works will be constructed and completed mainly by construction

equipment and machinery in combination of use of common labor

All construction lines shall be almost developed at the same time over the site upon receiving the commencement order from Employer

A The Project Management Board shall be located at the site for overall

management and direction of construction and completion of works of

construction lines during construction period, that will mobilize construction units from this construction section to other, distribute and arrange properly the

construction equipment, machinery, manpower so that they will be used

effectively

2 Primary construction method for road

Sequences of construction for road construction lines:

Trang 4

NGAI SECTION

3 Primary construction method for bridge

III PLAN FOR CONSTRUCTION EQUIPMENT AND MACHINERY AND

MANPOWER MOBILIZATION

1 General

This is the most important factor in execution of works, because the quality and construction progress to be depended on this factor

The construction equipment and machinery :

Bidder shall provide the construction equipment and machinery, testing instrument and measurement instruments in enough number and type with high productivity in good operation conditions, responding the advantaged construction line and technology for construction and completion of works as required by the Employer One workshop shall be arranged by the Bidder for maintaining construction equipment and machinery in good conditions time by time during construction period

The Key personnel

The key personnel consisting the experience skill management staffs and professional engineers, they have been trained with the professional education and success experience from previous similar construction work, which they have participated in They are able to manage and direct construction and completion of works success

The Technicians, Machinery Operators, Driver and Skill Labor etc.

Bidder shall mobilize the experience Technicians, Machinery Operators, Driver and Skill Labor, they have been trained at the professional training schools and have the professional acknowledge and skill They are able to operate machinery and carry their work effectively

The Common Labor

Firstly Bidder shall use maximally their available resource, if still not enough,

Trang 5

NGAI SECTION

2 Arrange manpower and equipment for road

2.1 Excavation

For the construction of this item, the Bidder shall arrange Intended

Manpower and equipment of 1 team as follows:

- The construction equipment and manpower:

Trang 6

NGAI SECTION

Intended Intended Manpower and equipment of 1 team

TT Equipment Capacity Quantit

y

Manpowe r

Quantity

2.2 Construction embankment K95, K98

For the construction of this item, the Bidder shall arrange Intended Manpower and equipment of 1 team as follows:

- The construction equipment and manpower:

Intended Manpower and equipment of 1 team

TT Equipment Capacity Quantit

y

Manpow

er Quantity

2.3 Construction sub base, base aggregate course

Trang 7

NGAI SECTION

For the construction of this item, the Bidder shall arrange Intended Manpower and equipment of 1 team as follows:

- The construction equipment and manpower:

Intended Manpower and equipment of 1 team

TT Equipment Capacity Quantit

y

Manpow

er Quantity

2.4 Construction asphalt pavement, asphalt treated base

For the construction of this item, the Bidder shall arrange Intended Manpower and equipment of 1 team as follows:

- The construction equipment and manpower:

Intended Manpower and equipment of 1 team

TT Equipment Capacity Quantit

y

Manpow

er Quantity

Trang 8

NGAI SECTION

2.5 Construction Bituminous Surface Treatment

For the construction of this item, the Bidder shall arrange Intended Manpower and equipment of 1 team as follows:

- The construction equipment and manpower:

Intended Manpower and equipment of 1 team

TT Equipment Capacity Quantit

y

Manpow

er Quantity

2.6 Construction Portland cement concrete pavement or cement treated base

For the construction of this item, the Bidder shall arrange Intended Manpower

Trang 9

NGAI SECTION

- The construction equipment and manpower:

Intended Manpower and equipment of 1 team

TT Equipment Capacity Quantit

y

Manpow

er Quantity

concrete spreader

01

2.7 MSE retaining wall

For the construction of this item, the Bidder shall arrange Intended Manpower and equipment of 1 team as follows:

- The construction equipment and manpower:

Intended Manpower and equipment of 1 team

TT Equipment Capacity Quantit

y

Manpow

er Quantity

Trang 10

NGAI SECTION

TT Equipment Capacity Quantit

y

Manpow

er Quantity

2.8 Finish items construction as planting grass, tree

For the construction of this item, the Bidder shall arrange Intended Manpower and equipment of 1 team as follows:

- The construction equipment and manpower:

Intended Manpower and equipment of 1 team

TT Equipment Capacity Quantit

y

Manpow

er Quantity

3 Arrange manpower and equipment for bridge

As shown on bridge section and “Workforce Mobilization Plan”