NGAI SECTIONEXPRESSWAY CONSTRUCTION METHODS Including construction method for Thruway, Drainage System, Service area, Frontage road and Miscellaneous Works... General Requirements Having
Trang 1NGAI SECTION
EXPRESSWAY CONSTRUCTION METHODS
(Including construction method for Thruway, Drainage System, Service area,
Frontage road and Miscellaneous Works)
Trang 2NGAI SECTION
GENERAL CONSTRUCTION PLAN
I General Requirements
Having studying the Bidding Documents issued, prevail regulation on quality control and construction supervision of construction works, our Bidder will
propose the proper plan for construction and completion of Work of this Package
in compliance with the conditions of contract
II Construction organization plan
The Bidder will arrange temporary road for construction Construction progress will be construction simultaneously over all section of line
1 Construction arrangement
For ensuring the construction progress schedule and construction quality required by the Employer and basing on the quantities of works to be completed and site conditions, the construction lines are proposed to arrange as follows:
The Works will be constructed and completed mainly by construction
equipment and machinery in combination of use of common labor
All construction lines shall be almost developed at the same time over the site upon receiving the commencement order from Employer
A The Project Management Board shall be located at the site for overall
management and direction of construction and completion of works of
construction lines during construction period, that will mobilize construction units from this construction section to other, distribute and arrange properly the
construction equipment, machinery, manpower so that they will be used
effectively
2 Primary construction method for road
Sequences of construction for road construction lines:
Excavation
Construction embankment K95
Construction embankment K98
Construction of Sub-base, base aggregate course, asphalt treated base
Construction cement concrete pavement
Trang 3NGAI SECTION
Construction of asphalt concrete pavement
Bituminous Surface Treatment
Construction of Completed works
3 Primary construction method for bridge
Construction of bored piles
Construction of Foundation pit
Construction of Abutment
Construction of Pier
Construction of beam Installation
Construction of Completed works
MANPOWER MOBILIZATION
1 General
This is the most important factor in execution of works, because the quality and construction progress to be depended on this factor
Bidder shall provide the construction equipment and machinery, testing instrument and measurement instruments in enough number and type with high productivity in good operation conditions, responding the advantaged construction line and technology for construction and completion of works as required by the Employer One workshop shall be arranged by the Bidder for maintaining construction equipment and machinery in good conditions time by time during construction period
The key personnel consisting the experience skill management staffs and professional engineers, they have been trained with the professional education and success experience from previous similar construction work, which they have participated in They are able to manage and direct construction and completion of works success
Bidder shall mobilize the experience Technicians, Machinery Operators, Driver and Skill Labor, they have been trained at the professional training schools and have the professional acknowledge and skill They are able to operate machinery and carry their work effectively
Firstly Bidder shall use maximally their available resource, if still not enough, the local labor shall be employed in place
Trang 4NGAI SECTION
2 Mobilization of manpower and equipments
As shown on “Main machinery and equipment mobilization plan for
construction of the contract” and “Workforce Mobilization Plan”