Upon completion of this lesson, the successful participant will be able to: Minimum cost concepts, Economic Order Quantity (EOQ) analysis methods, Just‐in‐time (JIT) purchasing quantities based on EOQ, setup time reduction, push and pull inventory scheduling and EOQ.
Trang 1Chapter 9 – Unit 1
Minimum Cost Analysis
IET 350 Engineering Economics
Learning Objectives – Chapter 9
Upon completion of this chapter you should understand:
Minimum cost concepts
Economic Order Quantity (EOQ) analysis methods
Just‐in‐time (JIT) purchasing quantities based on EOQ
Setup time reduction
Push and pull inventory scheduling and EOQ
2
Learning Objectives – Unit 1
Upon completion of this unit you should understand:
Minimum cost concepts
Economic Order Quantity (EOQ) analysis methods
Just‐in‐time (JIT) purchasing quantities based on EOQ
Setup time reduction
Push and pull inventory scheduling and EOQ
3
Trang 2 Basis for understanding and applying techniques such as:
Economic purchase quantity analysis
Economic production quantity analysis
Just‐in‐time purchasing
Just‐in‐time scheduling
Inventory reduction
Capacity maximization
Cost minimization as related to quality, maintenance and
design
4
Minimum Cost Analysis
Cost analysis problems frequently include opposing costs.
Changes to a variable may cause some costs to increase
while other costs decrease
Example J increasing production quantities reduce cost
Example J increasing production quantities reduce cost
associated with setup but increase costs associated with
holding and storing inventory
Objective of minimum cost analysis is to find the point at
which total costs are minimized
5
Minimum Cost Analysis
Breakeven, isocost and make/buy analysis techniques apply
to situations where cost increase relative to a key variable
(output quantity)
Minimum cost analysis techniques apply to situations where y q pp y
some costs increase and some costs decrease relative to a
key variable (typically output quantity).
Concept of minimum cost occurs frequently when designing
and manufacturing products
“It is not enough to design a technically good product; it
must be economical as well.”
6
Trang 3 Minimum cost analysis is typically used in the manufacturing
process in the following areas:
Amount and type of quality control
Amount of raw material and/or components in each
Amount of raw material and/or components in each
purchase order.
Scheduling delivery frequency of materials from vendors
Determination of the equipment setup and scheduling of
production
Determination of the production lot size
Response and delivery times to customers 7
End Unit 1 Material
Go to Unit 2 Economic Order Quantity
8
Chapter 9 – Unit 2
Economic Order Quantity
IET 350 Engineering Economics
Trang 4Learning Objectives – Unit 2
Upon completion of this chapter you should understand:
Minimum cost concepts
Economic Order Quantity (EOQ) analysis methods
Just‐in‐time (JIT) purchasing quantities based on EOQ
Setup time reduction
Push and pull inventory scheduling and EOQ
10
Inventory and Minimum Cost
Technique for minimizing inventory costs is known as
Economic Order Quantity (EOQ) analysis
Economic Order Quantity analysis is applied to:
Production lot (batch) quantity determination
Production lot (batch) quantity determination
Purchase quantities for raw materials or components
used in the product from outside suppliers
Purchase quantities for supplies required for the
organization’s operation
11
Inventory and Minimum Cost
Just‐in‐time (JIT) is an economic order quantity concept of
having inventory and supplies available just before they are
required rather than holding large quantities in inventory
Large inventories are sometimes known as just‐in‐case.g j
Just‐in‐time is a philosophy that requires a fundamental shift
in how manufacturing organizations operate
Known and predictable quality is mandatory
Just‐in‐time also requires a fundamental change in many
manufacturing methods to allow quick and inexpensive
changeover of equipment to produce different parts
12
Trang 5 Determination of inventory levels is a critical decision for
manufacturing organizations:
Inventory represents significant costs and investment of
financial resources
Lack of inventory leads to customer dissatisfaction and
potential loss of sales
Inventory must be ordered, scheduled and monitored
which requires personnel resources
Levels of in‐process inventory significantly affects the
operation of the production area
13
Inventory EOQ
Determination of EOQ requires minimizing opposing costs.
Increasing order quantities and the resulting inventory:
Ordering/setup costs are lower since fewer orders per
time period are required.p q
Holding (storage) cost of inventory increases due to
higher levels including the requirement of more space
Funds used to purchase the inventory have a cost (ROI)
Inventory is readily available for immediate sale
Loss due to scrapping inventory due to obsolescence
14
Inventory EOQ
Determination of EOQ requires minimizing opposing costs.
Decreasing order quantities and the resulting inventory:
Ordering/setup costs are higher since more orders per
time period are required.p q
Holding (storage) cost of inventory decreases due to
lower levels including the requirement for less space
Funds used to purchase the inventory have a cost (ROI)
Potential for lost sales due to lack of inventory
Less chance of loss of inventory due to obsolescence
15
Trang 6Inventory EOQ – Factors
Order Cost J costs associated with obtaining quotations and
placing the order for materials, supplies or components
Setup Cost J costs associated with the setup or changeover
of production equipment for each production batch (lot).p q p p ( )
Holding (Storage) Cost J costs associated with:
Value of warehouse space
Cost of the investment (ROI)
Other costs such as insurance, spoilage, damage,
materials handling and related storage costs
16
Inventory EOQ – Factors
Total Inventory Cost = Order Cost + Storage Cost
17 Example problem from Bowman text page 351
Inventory EOQ – Factors
Annual Storage or Holding Cost J uses average inventory/year:
( )( )
Q Holding Cost = H PV
2
⎛ ⎞
⎝ ⎠
18
( )( )
where: Q = Units/order (EOQ)
H = Holding costs/year (%)
PV = Part Value ($/unit)
2
⎜ ⎟
Trang 7Inventory EOQ – Factors
Annual Setup Cost:
( )
AU Setup Cost = SU
Q
⎛ ⎞
⎜ ⎟
⎝ ⎠
19
( )
where: Q = Units/order (EOQ)
AU = Annual Usage (units/year)
SU = Setup Cost ($/setup)
Q
⎜ ⎟
⎝ ⎠
Inventory EOQ – Factors
EOQ occurs when Annual Storage Cost = Annual Setup Cost :
H PV = SU
20
( )( ) ( )( )
solving for Q
2 AU SU EOQ = Q =
H PV
Inventory EOQ – Factors
This EOQ equation yields an exact mathematical solution
( )( ) ( )( )
2 AU SU EOQ = Q =
H PV
This EOQ equation yields an exact mathematical solution
Frequently it is advantageous to modify the actual quantity
ordered to better reflect schedule or customer requirements
Often firms maintain a safety stock to account for unexpected
orders or delays in delivery. However, safety stock adds cost
21
Trang 8Inventory EOQ – Factors
This EOQ equation yields an exact mathematical solution for
( ) ( )
( )( )
2 AU EOQ = Q = PO
H PV
This EOQ equation yields an exact mathematical solution for
purchased raw materials, components or supplies
The Setup Cost per order (SU) is replaced with the Purchase
Cost per order (PO)
Like EOQ for manufactured parts, EOQ for ordered items is
adjusted within reason to account for specific situations
22
Example Problem 9.1
23
Example Problem 9.1 Solution
End Unit 2 Material
Go to Unit 3 Just‐In‐Time Purchasing
24
Trang 9Chapter 9 – Unit 3
Just‐In‐Time Purchasing
IET 350 Engineering Economics
Learning Objectives – Unit 3
Upon completion of this unit you should understand:
Minimum cost concepts
Economic Order Quantity (EOQ) analysis methods
Just‐in‐time (JIT) purchasing quantities based on EOQ
Setup time reduction
Push and pull inventory scheduling and EOQ
26
Just‐In‐Time Purchasing
Successful just‐in‐time ordering is based on EOQ analysis
Philosophy J if the cost of executing the purchase order (PO)
is reduced, the order frequency (f) increases and the quantity
per order (Q) decreases
27
per order (Q) decreases
Result J reduced stored inventory and shorter response time
to the customer
Reduced inventory requires less space allowing for
conversion to productive purposes
Objective J extend J‐I‐T philosophy to all purchased
materials and supplies
Trang 10 J‐I‐T purchasing implementation:
Work with vendors to establish long‐range ordering plans
under a single purchase order with more frequent
deliveries and smaller quantities per delivery.q p y
Utilize single vendors and establish long‐term relationships.
Long‐term commitments generally result in:
Investment by vendor yielding lower costs to the vendor
and customer
Higher‐quality products with less variation. Quality
assurance responsibilities are transferred to the vendor
28
Just‐In‐Time Purchasing
As suppliers and customers become “partners,” costs decrease,
quality increases, and schedules become more synchronized.
The results of this effort are better profits for both the supplier
and customer as well as higher customer satisfaction
29
J‐I‐T purchasing requires the vendor (supplier) to make
similar changes in their production system:
Producing large quantities, storing inventory and shipping
small frequent quantities will increase costs to the vendor
resulting in higher costs to the customer
Quantity Discounts and EOQ
Suppliers frequently offer quantity discounts for minimum
order quantities or order dollar value
Buyers must consider the effect on total cost if the EOQ is
ordered or if the quantity needed for the discount is ordered.q y
Total cost is determined by totaling for the EOQ and for each
discount quantity:
Storage cost
Ordering (acquisition) cost
Material Cost
30
Trang 1131
Example Problem 9.2 Solution
EOQ Concerns and Limitations
Lumpy demand J usage and demand are not linear or
constant.
Minimum order quantity J suppliers may require minimum
order quantities which are more than the EOQ.q Q
Transportation costs J should be factored into the ordering
cost. More frequent smaller orders may result in increased
total shipping costs
Unit loads J there may be a standard quantity such as a
pallet load which is different than EOQ
32
Just‐In‐Time History
First examples of J‐I‐T can be found in the grocery industry in
the United States
Dairy and bakery companies began providing home
delivery in the late 1800s J small, frequent deliveries y , q
when the item was needed
Grocery stores in the 1950s were receiving non‐
perishable items on a two week delivery schedule J
small delivery quantities minimizing inventory on‐hand
Japanese auto industry adapted inventory techniques used
by the U.S. grocery industry in the 1970s
33
Trang 12Go to Unit 4 Setup Time and Inventory
Scheduling
34
Chapter 9 – Unit 4
Setup Time and Inventory Scheduling
IET 350 Engineering Economics
Learning Objectives – Unit 4
Upon completion of this unit you should understand:
Minimum cost concepts
Economic Order Quantity (EOQ) analysis methods
Just‐in‐time (JIT) purchasing quantities based on EOQ
Setup time reduction
Push and pull inventory scheduling and EOQ
36
Trang 13 Key element of J‐I‐T in the production environment is
minimum setup or changeover times
If setup time can be reduced, setup costs are decreased
resulting in lower EOQ.g Q
37
Figure 9‐2 Revised RL 12‐40
Setup Costs
Push and Pull Inventory and EOQ
Pull inventory system:
Supplier waits for customer order to begin assembling the
final product
Replenishment components are requested from prior
Replenishment components are requested from prior
department in the manufacturing sequence J pulled
from the prior step
Sequence repeats backward through the manufacturing
process until raw material inventory is reached
Order to replenish the materials and components issued
to replenish the inventory J pulled from the supplier.
38
Push and Pull Inventory and EOQ
Push inventory system:
Supplier forecasts the customer needs
Product is produced in advance of customer’s needs
Product is pushed through the manufacturing sequence
and placed in finished goods inventory until needed
Push inventory system typically used when changeover
times are high
EOQ minimum cost analysis can be used to implement the
preferable pull system
39
Trang 14 Benefits of J‐I‐T purchasing, EOQ and quick changeover:
Reduced inventory levels
Increased productivity
Increased inventory turnover
Reduced costs
Increased ROI
Reduced customer delivery times
Increase the organization’s overall financial results
40
Conclusions on J‐I‐T
41 Figure 9‐3 Inventory Improvement Cycle
Minimum Cost Applications
Maintenance costs J implementation of preventive
maintenance policies that balance opposing costs of
inspection and preventive replacement with costs associated
with equipment downtime
42
Trang 15 Electrical conductor sizing J balance opposing costs of
reducing resistance by increasing conductor diameter with
additional cost of larger conductor
43
Minimum Cost Applications
Fluid flow and pipe sizing J balance opposing costs of
increasing pipe diameter to reduce flow resistance with
additional cost of larger pipe
44
Minimum Cost Applications
Heat transfer and insulation thickness J balance opposing
costs of increasing insulation thickness to reduce heat loss
with additional cost of thicker insulation
45
Trang 16 Structural design J balance opposing costs of increasing
column spacing reduce number of columns with additional
cost of heavier column cross‐section
46
End Chapter 9 Material
Student Study Guide Ö Chapter 9
Homework Assignment Ö Problem Set 9
47