Thi công hầm theo công nghệ NATM là một công nghệ thi công hầm được dùng hầu như toàn bộ cho các hầm trên Việt Nam hiện nay. công nghệ này được áp dụng lần đầu tiên ở dự án Hầm Hải Vân, và cho đến nay có rất nhiều hầm áp dụng công nghệ này. Bản Thuyết minh tính toán này sẽ cung cấp cho Sinh viên, kỹ sư nắm bắt được cách thức tính toán áp dụng trong công nghệ hầm NATM. Bản tính được thực hiện bằng phương pháp phần tử hữu hạn thông qua phầm mềm MISES
Trang 1CHƯƠNG 1 - CHAPTER 1 SUPPORT SYSTEM TYPE D1-1
1- Input data
1.1 Tunnel Cross Section
Figure 1: Typical cross section of D1 pattern
1.2 Cross Section of Support System
Support System is includings:
- Shotcrete with thickness t = 200mm
1.3 Construction Sequence
Tunnel conruction sequence as below:
- Stage 1: Crown excavation ( Upper bench as Figure 2)
- Stage 2: Install steel rib, shotcrete, rock bolt for crown
Install monitoring equipment, control stress and deformation
- Stage 3: Bench excavation ( Lower bench as Figure 2)
- Stage 4: Install steel rib, shotcrete, rock bolt for bench
Install monitoring equipment, control stress and deformation
- Stage 5: Tunnel lining concrete construction
C.L
C.L PHASE-2 PHASE-1 C.L C.L
F.G
Trang 2Figure 2: Cross section of D1 support system
Trang 3+ Bottom of the tunnel: 50m from tunnel center line.
+ Beside of the tunnel: 50m from tunnel center line
- By symmetry of tunnel cover, in this model we describe the half of tunnel cross section and the surrounding rock to calculate
3- Stress state and deformation in the tunnel construction (Design load):
According construction sequence above, stress state and deformation of support system and surrounding rock in construction stage as following:
- Stage 1: Determination of stress formation in the original rock mass
- Stage 2:
Crown excavation Stress state and deformation of surrounding rock is changed
Assuming that 40% of the change of stress state and deformation due to crown
excavation (40% load of crown excavation) in the structure without shotcrete
- Stage 3:
Shotcrete for crown; 60% of the change of stress state and deformation of remaining
(60% load of crown excavation) in the structure with shotcrete
- Stage 4:
Bench excavation Stress state and deformation of surrounding rock is changed
Assuming that 40% of the change of stress state and deformation due to bench
excavation (40% load of bench excavation) in the structure without shotcrete
- Stage 5:
Shotcrete for bench; 60% of the change of stress state and deformation of remaining
(60% load of crown excavation) in the structure with shotcrete
Trang 4d1-1 - without invert
Trang 54- Calculation Result of MISES3: 4.1 Diagram element:
Trang 224.2 Construction sequence:
Trang 274.3 Stress state:
Trang 484.4 Deformation:
Trang 61d1-1 - with invert
Trang 624- Calculation Result of MISES3: 4.1 Diagram element:
Trang 794.2 Construction sequence:
Trang 844.3 Stress state:
Trang 1054.4 Deformation: