1. Trang chủ
  2. » Kỹ Thuật - Công Nghệ

Addendum no 6 to TD for CP3 EN

7 121 0

Đang tải... (xem toàn văn)

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 7
Dung lượng 164,65 KB

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Nội dung

Appendix A to Addendum No.62.. Key Dates related to Installation Tests, System Acceptance Tests, Trial Running Week 177 RSKD3-1 Week 191 RSKD4-1 Week 200 RSKD3-2 Depot Installation Tests

Trang 4

Appendix A to Addendum No.6

2 Key Dates related to Installation Tests, System Acceptance Tests, Trial Running

(Week 177) RSKD3-1

(Week 191) RSKD4-1 (Week 200) RSKD3-2

Depot

Installation Tests Partial Acceptance Tests (installation and testing of Railway

Systems) (Trial Running for Testing)

System Acceptance Tests

(Week 212) RSKD4-2

(Week 236) RSKD8-1 RSKD8-2

(Week 293) RSKD3-3 (Week 300) RSKD4-3 (Week 306) RSKD8-3

(Week 314) RSKD9

RSKD3: Achievement - Completion of Track and wayside equipment sufficient to commence Rolling Stock acceptance testing

RSKD4: Achievement - Completion of installation and testing of Railway Systems sufficient to commence Dynamic System Integration

RSKD8: Achievement - Completion of Trial Running and Performance Demonstration

RSKD9: Achievement - Completion of Whole Works for Taking Over Certificate

Trial Running for Training of Revenue Operation

System Acceptance Tests Integration & Commissioning (Dynamic System Integration) (Performance Demonstration) (Trial Running for Testing)

Trang 5

Ho Chi Minh City Urban Railway Construction Project Appendix 2A to Letter of Tender Ben Thanh - Suoi Tien Section (Line 1) Package-3: E & M, Rolling Stock, Trackwork, Maintenance

<Appendix B to Addendum No.6>

INSTRUCTIONS TO TENDERERS

PRICING DOCUMENT

CONTRACT PACKAGE - 3

COST CENTRE - 16 REQUIREMENTS OF ADDENDUM NO.4

Trang 6

Ho Chi Minh City Urban Railway Construction Project Appendix 2A to Letter of Tender Ben Thanh - Suoi Tien Section (Line 1) Package-3: E & M, Rolling Stock, Trackwork, Maintenance

COST CENTRE NO.16 (OUTLINE) REQUIREMENTS OF ADDENDUM NO.4

This Cost Centre No.16 comprises all the relevant increased costs due to the requirements of Addendum No.4 issued on 4th November 2010

The costs entered herein are deemed to be incurred due to delayed access to the underground structures, and shall include but not be limited to the following items:

• Site administration cost, including personnel, premises and facilities

• Cost for additional demobilization & remoblization of the Contractor’s workforce and common equipment resources

• Operation and maintenance cost for the CP-3 equipment installed in the elevated section including site security, periodic maintenance of the system to keep the system in workable condition, and electric power for their activities

• Any other administration and financial costs to be incurred due to delayed access to the underground structures

For the payment procedure, the Tenderers shall propose the Milestones and payment schedule by selecting appropriate events, in accordance with Clause “D Cost Centres and Milestones” of Appendix 2 to Letter of Tender

It shall be noted that the above conditions will be applied for tendering purpose only, and these conditions as well as the proposed tender price will be further discussed and adjusted at the time of contract negotiation with the successful tenderer, taking into account the latest project situation at that

time

Trang 7

Ho Chi Minh City Urban Railway Construction Project Appendix 2A to Letter of Tender Ben Thanh - Suoi Tien Section (Line 1) Package-3: E & M, Rolling Stock, Trackwork, Maintenance

COST CENTRE NO 16 (OUTLINE) – CONTRACT PACKAGE 3

REQUIREMENTS OF ADDENDUM NO.4

MILE-

STONE

NO WORK DESCRIPTION

AMOUNT COLUMN A

Japanese Yen

Vietnamese Dong

Add.1 Provide the Additional Administration

Work due to the requirements of

Addendum No.4

COST CENTRE AMOUNT CARRIED FORWARD

Ngày đăng: 28/05/2018, 00:51

TỪ KHÓA LIÊN QUAN

w