Method Statement of Bored Pile ConstructionAppendix 2: Equipment and manpower Appendix 3: Plan of drawing construction method of bored pile Appendix 4: Sequence of construction bored pil
Trang 1Method Statement of Bored Pile Construction
CONTENTS
1) Standards related 2
2) Pile works 2
2 Work Quantity 3
3 Construction Schedule 4
4 Construction team 4
5 Site Organization Chart 4
6 Equipment and Manpower 4
7 Material list 4
8 Overall Construction Sequence 5
1) Work flow-chart 5
2) Bored pile construction works 7
9 Method Proposed to Mix, Supplying and Recycling Bentonite 21
1) General Requirements 21
2) Detail of Method to mix Bentonite Suspension 22
3) Supplying and Recycling of Bentonite Suspension 23
10 Construction Schedule 23
11 Safety Control 23
1) Provisions for Workmen 23
2) Provisions for equipment, plant, machine 24
3) For bored drilling works 24
4) Table of hazard assessment 25
12 Environmental Control 25
13 Quantity Control 26
1) Bentonite mud testing 26
2) Slurry testing 26
3) Concrete testing 26
14 Emergence Response Chart 28
Appendix :
Appendix 1: Site Organization Chart
0 | P a g e
Trang 2Method Statement of Bored Pile Construction
Appendix 2: Equipment and manpower
Appendix 3: Plan of drawing construction method of bored pile
Appendix 4: Sequence of construction bored pile
Appendix 5: Drawing of construction method for bored pile
Appendix 6: Construction schedule for 1 pile
Appendix 7: Inspection and test plan
Appendix 8: Safety work proceduce manual
Trang 3Method Statement of Bored Pile Construction
1 General
This method statement describes the procedure and the quantity control for construction of boredpile d=1.2m The drilling method will be apply the earth drilling method The method consist ofthe content as following:
- Work Quantity
- Site Organization Chart
- Material List
- Equipment and Manpower
- Overall Construction Sequence
- Quantity Control
- Safety & Environmental Control
The method statement for the construction bored pile (D=1.0m) shall be submitted separately.The method statement for the static load test, PDA test, sonic pulse test and other tests forbored pile shall be submitted separately
Construction and Measurement of Bored PilesBored Piles – Determination of identify of concrete –Pulsed ultrasonic method
Bored Piles – Method of detection of defects by lowstrain dynamic test
Material for the pipes Standard penetration test (SPT)Construction shall follow Technical specification and approved working drawing
Number
Of pile
Total Length (m)
2 | P a g e
Trang 4Method Statement of Bored Pile Construction
Trang 5Method Statement of Bored Pile Construction
- Team no.1 – 422 Company: From A1 to P5;
- Team no.2 – Sub Contractor no.1: From P6 to P8;
- Team no.3 – 407 Company: From P16 to P22;
- Team no.4 – 412 Company: From P23 to P27;
- Team no.5 – 414 Company: From P28 to P31;
- Team no.6 – 482 Company: From P32 to P35;
- Team no.7 – 423 Company: From P36 to P40;
- Team no.8 – 479 Company: From P41 to P44;
- Team no.9 – Sub Contractor no.2: From P59 to P60
5 Site Organization Chart
Please see appendix No.1
6 Equipment and Manpower
Please see appendix No.2
7 Material list
List of required the approved major materials is shown below:
1 Steel Rebar
TCVN 1651 : 2008TCVN 197 : 2002TCVN 198 : 2008
Fy =400 Mpa
2 Concrete S10.07-TCKT Specification Y-30 Mpa
4 | P a g e
Trang 6Method Statement of Bored Pile Construction
Dout=113.5mmt=3.5mm
Dout=59.9mmT=3.0mm
4 Cement mortar for
fillup sonic pipe TCVN 9396 : 2012 30 Mpa
8 Overall Construction Sequence
1) Work flow-chart
The work sequence is presented in the Flow-Chart as follows:
Inspection:
← - Check point
← - Check vertical of casing
← - Elevation of top casing
- Check to vertically kelly bar
- Property of bentonite,
- Depth of bored hole,
- Characteristics of the soil
- Diammeter of bored hole
- Vertical of bored hole (Koden machine)
Set up electric line and water line
Step 2
MobilizeTime excavator
50T Crane, drilling equipment
Chipping equipment
Assembly crane boom
Mobi tank and setting
Casing, bending, cutting machine and setting
Re-bar, sleeper, bentonite powder
No.2 Pile pre-drilling and installing casing for accumulation bentonite
No.1 drilling, checking bored hole, cleaning bored hole 1st time, installing rebar cage, cleaning bored hole 2nd
Step 3
Trang 7Method Statement of Bored Pile Construction
Casting concrete and remove casing
Step 7
Construction final pile
Setting casing at near final pile for accumulation bentonite
Drilling, checking bored hole, cleaning bored hole 1st time, installing rebar cage, cleaning bored hole 2nd time Casting concrete and remove casing
Cleaning inside of bentonite casing and extract that casing
Step 8
For the next pier
Re – arragement bentonite facilities and rebar yard
Re – location bentonite facilities (follow the water supply system)
Construction all pile by same methodMoving to next Island (Use Bubber plate)
Cleaning inside of bentonite casing and extract that casing
+ Moving bentonite facilities, re-bar yard
← - Check vertical of casing
← - Elevation of top casing
- Check to vertically kelly bar
- Property of bentonite,
- Depth of bored hole,
- Characteristics of the soil
- Diammeter of bored hole
- Vertical of bored hole (Koden machine)
- Decide length of pile with soil condition bearing
Inspection:
← - Check point
← - Check vertical of casing
← - Elevation of top casing
- Check to vertically kelly bar
- Property of bentonite,
- Depth of bored hole,
- Characteristics of the soil
- Diammeter of bored hole
- Vertical of bored hole (Koden machine)
- Decide length of pile with soil condition bearing
Trang 8Method Statement of Bored Pile Construction
2) Bored pile construction works
Step 1 : Make fence for keep working area and traffic control
Step 2 : Set up electric line and water line
Step 3 : Demolish and removing
+ Center medion strip, lighting pole …
+ Set up wasing facility
Step 4 : Mobilize
1 Time excavator
2 50T Crane, drilling equipment
3 Chipping equipment
4 Assembly crane boom
5 Mobi tank and setting
6 Casing, bending, cutting machine and setting
7 Re-bar, sleeper, bentonite powder
Step 5 : Start drilling (for 1st pile)
1 No.1 pile pre-drilling and installing casing
Locating center point of the bored Pile
The transeverse line setting out:
Trang 9Method Statement of Bored Pile Construction
Center point of Bored pile
The center point of the pile shall be surveyer and marked by suitable stakes After setting
of the casing this center point shall be re-checked to confirm the accuracy Anycoordinate of pile shall be submitted to the Engineer to get approval
The center point of pile will be marked as specified in the Drawings
Reference marks will be established for determination of pile center line duringconstruction The center of the pile shall be surveyed and inspected by Engineer
Pre-drilling
Base Machine to be set upon the pile center horizontally and vertically
The centering of the machine is to be made by the tip of Kelly bar to be position on thepile center and examine the horizontal of the machine and the verticality of the Kelly bar.These examinations are to be made by a water level equipped in the machine and byplumb
To protect the upper part of hole, a temporary Casing pipe to be installed
For this purpose, pre-drilling is to be made by Earth drill
Installing Casing Pipe
Bored pile construction will commence from setting out pile location, the contractor willinstall temporary casing by crane with Vibro Hammer
Before installation, the casing shall be free from significant distortion They shall haveuniform cross-section throughout each continuous length
The casing will be set at the exact point by total station and plumb as below:
Guide frame Plumb
8 | P a g e
Trang 10Method Statement of Bored Pile ConstructionThe diameter and thickness of casing shall be considered for such calculation Totalstation setting up in the site will be maintained to check the verticality of pile untillcompletion of drilling bored hole.
Using the vibratory hammer to drive the casing, as below:
- Using Drilling machine to make a hole with 1m depth Next, Crane will load ofcasing and put in bored hole so that exacting center point
- Using Vibration hammer to clamp the casing and starting to make vibration on point ofcasing top in turning circle, then vibrato hammer will be used to install the casingcontinuously to reach the designed level
- During driving of the casing, its location and verticality will be checked by the totalstation and plumb
- Elevation of top casing higher than 0.5m of ground level
- Temporary casing after installation shall be checked for elevation and position with therequirement in S10.07(5) “position tolerance” (Section g):
- Casing for drilling shall be fixed with steel cage
+ The centre of the casing shall not deviate more than the minimum (D/6=200mm;100mm) from the theoretically center correct position shown on the Drawings
Casing Vibrating hammer 60KW
2 No.2 Pile pre-drilling and installing casing for accumulation bentonite
3 No.1 drilling, checking bored hole, cleaning bored hole 1st time, installing rebar cage,cleaning bored hole 2nd time Casting concrete and remove casing
Preparation of bentonite Liquid
The facility for circulation of bentonite liquid shall be set up as below
Trang 11Method Statement of Bored Pile ConstructionRestoring bentonite mud from bored hole
Providing bentonite into the bored hole
2
Bored hole Dimension 6x2.3x2.2
1
Pump
4 Water tank
Water tank Desander
Pump
Mixer
Bom Pump
3 Pump
Mixer
4
Dimension 6x2.3x2.2 Dimension 6x2.3x2.2 Dimension 6x2.3x2.2
Sandbox
Statistics table specifications of bentonite tank:
Drilling Drilling Cleaning1st Cleaning2nd
10 | P a g e
Trang 12Method Statement of Bored Pile Construction
hole)
(Bottom
of boredhole)
(Bottom
of boredhole)
Circulation tank for bentonite liquid shall be checked timely during piling work andprecipitated material in tank such as sand or mud shall be removed adequately
Water used for mixing bentonite is potable water (well water) in accordance withstandards TCVN 4506 :2012
When the bucket is lifted up, the bucket is to be rotated reversibly to release from thebottom and to be lifted up slowly to protect the hole from collapse by piston effect Thecontrol of verticality during drilling work shall be made by plumb with string or theodolitesfrom two directions in 90 degree
Contractor will monitor bentonite suspension properties during the construction period toprevent it from being over flown to the site and the neighborhood In process drilling, toavoid the overflow of betonite, building brick wall after installing fence
Excavated soil shall be continuously investigated by eye checking to compare with thegeological data during drilling time
If there is any discrepancy between excavated soil and geological data during excavation,the Construction shall report it to the Engineer
During boring, vertical alignment of the drill rod shall be checked
Soil sampling is taken at the beginning and end of any soil layer and each 2m
In case of stop working for a long period, bucket shall be placed outside of bore hole
In process of drilling, the contractor will arrange two plumps in two vertical directions andalways appearing worker to check the vertical of Kelly bar
Trang 13Method Statement of Bored Pile Construction
kelly bar
Casing
Bottom EL
Supplying betonite liquid
Bentonite liquid
The contractor shall use dredge humus Bucket which has the shape of toe bucket likedrilling bucket to dredge the disturb soil and moving of tremie pipe during clearing byreverse circulation method to clean the disturbed soil
Construction tolerance:
The following construction tolerances shall be maintained in constructing drilled shaft:
- The center of the completed pile at the cut off level shall not deviate more than min D/6
=200mm or 100mm from the theoretically correct position shown on the Drawings
- The inclination of the pile shall not deviate more than 1:100 from the required vertical alignment
- The Engineer will confirm the final pile toe level after his inspection of the earth layers penetrated by the pile
Inspection
Checking bentonite solution before placing concrete
Any method and the equipment shall meet all safety requirements
Check vertically of Kelly bar by plumb and check vertically of bore hole by koden machineClean and Clear the site
Problem – solving when drilling :
- When drilling hole wall is collapsed, it is require to find out the reason and location of collapse for appropriate counter measures
- If the wall of drilling hole is substantially collapsed, earth filling will be required to the collapsed location, check and change the technical criteria of bentonite solution, stop the drilling work for a while, find out the reasons and take treatment measures prior to restarting the drilling work
- If bored hole is inclined, curved, hang drilling auger at curved position to re-drill until theverticality is reached If it is extremely inclined, use clay to refill and wait until soil is consolidated then restart the drilling
- When drilling hole loss bentonite and height of solution column is decreased, it is required to deepen casing, compact soil surrounding pipe casing, make bentonite
12 | P a g e
Trang 14Method Statement of Bored Pile Constructionmortar more solid, add clay into drilling hole and then control drilling gause or drilling auger slower to seal all bentonite leaks.
- If the drilling auger is fallen in bored hole, use wire, hook to pull it out In any case, it is strictly prohibited to allow worker to dive to solve the problems in bored hole
3.2 Method of confirmation the verticality of bore hole
After drilling completed, Koden test will be carried out under the supervision of theContractor, the Engineer To check the bored hole verticality and shape to ensures thatthe deviation is less than the tolerance of project specification
The steps are as follows:
- Checking bore hole and bentonite slurry before to Koden test;
- Install Koden test machine by crane;
- Input the parameters of bore hole;
- Place the winch unit over the top of drilled hole or on the steel casing Position the sensor at the center of the hole;
- Lower the sensor into bentonite slurry Hole the sensor at depth approximately 1.00 to 1.50m for initial calibration;
- After calibrations, restore the sensor to the starting position and perform the test The tests are carried out in downward monitoring and upward monitoring Drill hole profile along 2 perpendicular axes are printed out immediately
In case the inclination of borehole exceeds the allowed criteria, then we drill by reamingthe bored hole side to obtain the verticality of borehole
In case, height of sediment at bottom of bored hole is more than 2m, contractor should usecleaning Bucket to take out it before carrying out clean bore hole
Cleaning by submerged pump
Replacing bentonite inside boring holes by new bentonite with higher quality Submergedpump shall be fixed with tremie pipe in location from the ground at least 15-20m and thenbentonite shall be pumped to the tank During pumping bentonite circulated continuously.Debris, mud, sand… that pumped out of the bored hole shall be disposed to the hole andre-treated by sand filtering rig for the re-use
In case of Submerged pump capacity is not enough, additional pump will be set at the top