Cleaning borehole shall be performed before the installation of reinforcementrebar cage, and then the casting concrete of the bored piles will be taken place.. The following diagram show
Trang 1PROJECT TITLE:
Ho Chi Minh City Urban Railway Construction Project Ben Thanh - Suoi Tien Section (Line 1)
Construction Package 2 : Civil (Elevated & Depot)
Method Statement of Bored Pile Construction on
Land
REVISION STATUS
B 19th Feb 2013 SECOND ISSUE
PREPARED BY CHECKED BY APPROVED BY NAME
SIGNATURE
DATE
Trang 21 INTRODUCTION
1.1 OVERALL OF PROJECT
- Project name: Ho Chi Minh City Urban Railway Construction Project Line 1, Ben Thanh
- Suoi Tien Section
- The project comprises about 17,24 km of elevated rail way from Km2+360 toKm19+591.37 (including 5 special bridges) and 1 depot
- Location: Starting at District 1 and ending at Long Binh Ward, District 9, Ho Chi MinhCity
1.3 WORK SCOPE
This method statement includes below scope of works
- Drilling works: D=1,500mm, 1200mm & 1000 mm
- Installation of Rebar Cage
- Casting Concrete
Temporary steel casing, of which diameter is 50~100mm larger than designed bored pilediameter, will be installed The boring works will be carried out until the designated toelevel Bored hole is filled with Bentonite slurry once the boring works commenced
Upon completion of the boring works, the reinforcement rebar cage will be lowered into theborehole Cleaning borehole shall be performed before the installation of reinforcementrebar cage, and then the casting concrete of the bored piles will be taken place
Bored piles with different diameters and lengths will be constructed in accordance with theconstruction working drawings
Trang 32 CONSTRUCTION PROCEDURE
2.1 WORK FLOW-CHART
The work sequence of the bored pile construction is depicted by the following flow-chart
The following diagram shows the continuous sequence of bored piling works
Preparation WorksSetting center point of bored pile
Assembling Guide frame
- Vertical of bored
KODEN Test
1st Cleaning of the Bottom Hole Inspection:
-Rebar cages (at yard)
-Sonic and core tubes
-Depth of bored hole by using rebar cages
Installation of the Rebar Cage (including Sonic
and core tubes)
Inspection:
-Property of Bentonite
-Depth of bored hole
2nd Cleaning of Bottom Hole (if necessary)
- Slump of concrete
- Level of concrete rising
- Center of Pile
-Level of top concrete
- Depth of bored pile by
Removal of the Temporary CasingBackfill with suitable material
SONIC TestCore test (if necessary) Grouting SONIC and core tubes
Completion
Trang 41.Pre-boring for temporary
casing installation 1 Temporary casing installation by vibro hammer 1.Pumping of bentonite slurry for maintaining bored hole
2.Drilling of bored hole from EGL to Design Toe Level
Stage 4
1.Desanding the complete bored hole
2.Bentonite in bored hole will be pumped back to
bentonite plant for treatment
Stage 5
1.Lowering of reinforcement to the bored hole
2 Hanging the rebar cage at the designed level
Trang 5Stage 6
1.Concreting of bored pile
2.Pumping of displaced bentonite back to bentonite
2 Backfilling the bored hole with suitable backfilling material 1 to 2 hours after the completion of concreting
Fig.1 Sequence of Bored Piling Works
Temporary drainage system shall be provided around the platform so that the platform andthe surrounding area are kept dry and accessible all the time
The temporary access road shall be made in case that existing road is not available forsupplying material and mobilizing to equipment
Bentonite mixing tank will be installed for fluent execution of the work maintaining includingconnection of pipe or hose to supply bentonite for the bored pile location It will be checkedfrom time to time for any possible spillage of bentonite slurry as per environmental
Trang 6The density and consistency of the concrete for the bored piles shall conform to the tremiecasting method and the maintenance of sufficient workability (slump) of all the concreteduring the casting and handling period, including calculated allowance delay time, shall besecured by a design mix (including the necessary retarders and plasticizers) which istested by trial mixes prior to the pile construction.
The number of tank used for bentonite mixing plant shall be calculated to make sure thatthe volume of mixed bentonite slurry is enough for carrying out drilling work continuously
Typical layout of equipment and facilities set up for bentonite solution is shown below
* This layout could be changed according to site condition
Fig.2 Layout of equipment and facilities set up
Precipitation Tank 1 Precipitation Tank 2
Waste Tank Withdrawal Tank
Trang 7(2) Setting center point of the bored piles
Positioning drilling hole is based on the approved drawings, positioning benchmarks andpiling arrangement layout for specifying positions of pile center in compliance with theapproved design Specifying the position of the pile center is performed by electronic totalstation The position shall be approved by the Employer’s Representative
In addition, subsidiary benchmarks shall be set up by steel piles for direction of pile centerand the pile center shall be checked again upon sinking temporary well casing Thesepositions shall be protected and maintained until sinking and completing inspection of thewell casing
Checking of the bored hole location shall also be carried out for all the piles after thecommencement of boring, but not later than when boring has reached the top of the firststiff layer
Fig.3 Setting out center of Bored pile
(3) Assembling Guide frame
Assembling guide frame will be prepared before Setting of the temporary casing
(4) Setting of the temporary casing
Bored pile construction will be commenced from setting out pile location and pre-drillingand installing temporary casing The length of the casing will be considered and justifiedbased on the soil condition and underground water level for maintaining the stability of thepile excavation holes against collapse, the casing length is from 6m to 9m The top oftemporary casing will be extended about 0.5 meter above the ground level
In installation of temporary casing, the verticality and stability will be checked and movement during drilling shall be kept Inner diameter of casing pipe will be at least 5 ~10cm larger than bored hole diameter The casing will be plumbed and checked foreccentricity against reference pegs, or it will be checked with survey equipment at the top
non-of the casing with the same elevation aside from the location frame installed above groundlevel
Pile center Subsidiary benchmark
Datum point
Trang 8Fig.4 Installation of temporary casing
(5) Drilling work
The design length of piles will be specified in approved drawings During drillingexcavation, all holes for cast-in-place concrete pile should be excavated to the designlength Excavated holes will be protected from collapse by the provision of bentonite slurryand temporary steel pipe casing
Fig.5 Casing
Trang 9Bentonite will be mixed thoroughly with clean fresh water to make a suspension which willmaintain the stability of the drilled hole for the period of casting concrete and completeconstruction Dry powder Bentonite is mixed with clean water according to required ratio bymixing machine and stored in the tanks which will supply to bored hole The drilling fluidproperties of bentonite slurry will be measured by taking samples before concreting Thedensity of freshly mixed bentonite slurry will be measured as a check on the quality of thesuspension being formed.
b) Setting up of Bentonite Plant
The following are the various stages of works in the setting up of site facilities:
Setting up
Installation of desander unit
Preparation and levelling of ground
Installation of bentonite silos
Setting up of bentonite plant facilities
Layout of bentonite and water piping systems
Pre-mixing of bentonite slurry on site
Trang 10c) Bentonite Slurry Mix Design
Basic function of bentonite is to act as a stabilizing agent for the bored hole
In soil with high clay content, the bentonite slurry becomes very thick during excavationdue to the suspended clay particles The thick slurry becomes difficult to pump fordesanding To avoid this problem, a polymer / sodium bi-carbonate is added to the slurry
d) Testing Bentonite Slurry
Bentonite Slurry Testing:
The following tests will be conducted on bentonite slurry at the beginning and during boredpile construction period
1 Viscosity test - test on site
2 Sand Content – test on site
3 Density test - test on site
4 pH meter test - test on site
Bentonite characteristics have to meet the requirement (refer to Sub-clause 6.3Tolerance/Range, page 24-25)
The bentonite properties shall be measured by taking samples at the bottom of bored holebefore concreting All checking of bentonite slurry shall be carried out complying with thecriteria proposal The measuring device shall be calibrated to read in the minimum unit of0.01gm/ml
Fig.7 Bentonite Slurry
0.5-1.0 m above G.L
Bentonite
Trang 11e) Drilling works
Temporary casings shall be free from any significant distortion They shall be of uniformcross- section throughout each continuous length During concreting, they shall be freefrom internal projections and encrusted concrete which might disturb the proper formation
of piles
From the ground level to one meter above the toe of the temporary casing will be drillingwithout stabilization bentonite The measurement of the depth of drilling bucket shall beclosely monitored when it gets near of the toe of the temporary casing
After putting bentonite into the borehole, drilling work will be continued and the top level ofbentonite slurry will be maintained 1.5m higher than ground water level or equal withground level for prevention of cave-ins or bored hole collapses
Based on the soil properties, drilling speed is adjustable in order to maintain the drillingaccuracy
The soil materials encountered in the bored pile drilling shall be checked to confirmwhether the actual soil conditions are similar to those assumed based on the geotechnicalinvestigation boreholes or not
During the drilling work, the verticality of bored hole will be checked by plumb with stringline or theodolites from two directions in 90 degree And the depth of bored hole will bechecked for the conformation of borehole condition When the bucket is lifted up, thebucket is to be rotated reversibly to release from the bottom and to be lifted up slowly toprotect the hole from collapse
Kelly-Bar shall be kept at the centre of the casing because drilled holes start to bend withKelly-Bar’s deviation from the centre In case any the deviation is found, the drilling should
be operated slower than usual and to correct the Bar’s verticality
After a borehole is formed to the designated depth, sonic caliper test (Koden Test) shall becarried out for checking the depth, diameter and verticality of the boreholes
Bentonite introduced into the borehole achieves the stabilizing effect by ensuring that thepressure inside the borehole is greater than the horizontal soil pressure and groundwaterpressure, at all depths
Piles shall not be bored so close to the piles, which have been casted not long ago withworkable or unset concrete The piling may disturb the fresh concrete in the neighboringpiles Boring and excavation for a pile shall only be commenced 24 hours after completion
of any pile within a radius of 6.0m, center to center, and only after the concrete strength ofthe neighboring pile reaches 15N/mm2
The excavated material and disposal bentonite will be kept in tanks or containers thentransported to approved disposal areas by special trucks The proposed disposal areas will
be submitted to the Employer’s Representative for approval later and separately
(6) 1 st Cleaning bottom of the holes & Changinh Bentonite
Trang 12For the supply of fresh bentonite slurry, tank for fresh bentonite slurry will be installed atthe position which is separated apart from the bentonite pit.
The sequence of cleaning work for the bottom of hole is as below:
- Using cleaning bucket to remove lumps of clay, coarse sand and gravels at thebottom of the borehole Then,
- Using reverse circulation method or air lifting method for replacing sedimentation ofslime with good slurry
After cleaning work, the depth of hole will be measured by measuring tape connected to aplump bob Measuring of hole will be carried out at the center and four corners of the hole
Fig.8 Cleaning by cleaning bucket
(7) Fabrication and Installation of the rebar cage
Fabrication of rebar cage:
Steel bar shall be tested when delivery to site and only approved steel bar will be used Rebar cages, sonic tube and core tube will be fabricated and assembled according to theapproved construction working drawing
After the completion of fabrication for one segment of rebar cage, this segment shall becarefully kept in the dry and stable condition at stockyard which is elevated about 20 cmhigher than ground surface level Condition of re-bar cage will be checked and cleanedconstantly If some soil or rust are pound remained on the re-bar cage, all of them shall beremoved before the installation of re-bar cage
Additional reinforcing ring will be used for hanging of rebar cage segment and for the cagestabilized against distortion
Trang 13Fig.9 Reinforcement fabricationInstallation of rebar cage and sonic tubes and core tube:
After the 1st cleaning of borehole is completed, the rebar cage will be installed carefully inorder to avoid the wall of the borehole from collapsing The lowest rebar cage segment will
be put into the casing and temporarily fixed at the section to be spliced with the next rebarcage segment When the rebar cage reaches the designed level, it will be suspended fromtop of the casing The top level of the rebar cage will be confirmed in comparison to that ofthe casing
The ultra-sonic tubes and core tube will be fixed to rebar by additional bar and ties to therebar cage Top level of the sonic tubes and core tube will be positioned approximately15cm above the ground level and checked for the rigidity and watertight of tubes duringinstallation The sonic tubs and core tube will be poured with water and covered on the top
of tubes prior to casting concrete
Trang 14
(8) Setting of Tremie Pipe and Re-cleaning (2nd Time Clearing) of Bored hole
a) Setting of Tremie Pipe
Tremie pipes of dia 8-10 inches shall be used The tremie pipes with standard length,such as 0.5M, 1M, 2M, 3M and 6 M, shall be used
Since the tremie pipes are segmented and connected by bolts as a flange type and arubber gasket will be used therein to watertight, these are lowered piece by piece until itreaches to the bottom of the borehole And the tip of tremie pipe will be at least 300mmaway from the bottom of bored hole in order to have enough clearance in discharging ofconcrete The top of tremie pipe is fitted with a head hopper
The length of each tremie pipe and the sequence of installation shall be recordedcompletely
Fig.11 Tremie Pipe
b) Re-cleaning of the Borehole (2nd Time Cleaning)
Prior to placing concrete, the depth of bored hole will be measured carefully and thebentonite slurry will be tested once again, and the second time cleaning of pile base will becarried out if required by the Employer’s Representative with 1 of 2 methods:
1 1 Airlifting method: Air-lift system will be used as second measure to take all slime out
of the bottom of bored hole, before casting concrete The pressure of compressed airhas to be properly checked Since stabilizing fluid is supplied to the piling hole, thecompressed air will create an upward jet flow which carries the bottom sludge out of thehole The circulating time of airlift varies depending on the amount of bottom sludge
Trang 152 2 Reverse circulation method: using the capable submerged pump connected to tremiepipe for removing the slime sedimentation at the bottom of bored hole and replacing byfresh slurry.
A measurement tape is to be used for the re-confirmation of drilling depth and effect ofcleaning work The concrete placing will be started as soon as possible (approx in 30minutes) after second cleaning of bottom of bored hole And before casting concrete, it will
be confirmed by measurement tape that the sedimentation has been removed completely
Slump(cm)
Compressivestrength at 28days (Cylinder)
* Selection of the suitable tremie pipe (diameter, length per pipe and joint)
* Check of pipe joints leakage (visual Inspection)
Once again taking of Bentonite samples at the bottom of the bored hole by specialequipment and testing shall be performed before pouring concrete
Concrete will be placed and poured directly to the bored hole in one continuous operationfrom tip to cut-off elevation by tremie pipes and this operation will be carried out in such amanner that segregation of concrete is avoided The tip of the tremie will generally beapproximately 2.0m lower than the casting concrete surface A sliding plug or similarbarrier will be placed within the tremie pipe to prevent direct contact between the firstcharge of concrete and the water or bentonite