VA2 OM MS ME EL 002 method statement of extra low voltage system rev 0

61 16 0

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Tiêu đề Method Statement Of Extra Low Voltage System
Tác giả V.K.Hoan, T.D.Thinh, T.N.Khoa
Trường học vung ang ii thermal power llc
Chuyên ngành extra low voltage system
Thể loại method statement
Năm xuất bản 2022
Thành phố tokyo
Định dạng
Số trang 61
Dung lượng 5,62 MB

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Cấu trúc

  • 1.1 General discription (4)
  • 1.2 Based on documents (5)
  • 2.1 Project Materials (7)
  • 2.2 List of machinery & tools (7)
  • 2.3 List of Personal Protection Equipment (PPE) (8)
  • 2.4 Manpower Mobilization (9)
  • 3.1 Site organization chart (10)
  • 3.2 Responsibilities (10)
  • 4.1 Coordination at site (12)
  • 4.2 Work flow chart (12)
  • 4.3 Construction requirements (13)
  • 5.1 ELV underground conduit installation (13)
  • 5.2 Rack Panel Installation (17)
  • 5.3 ELV cable tray and trunking installation (21)
  • 5.4 ELV PVC conduit installation (26)
  • 5.5 ELV cabling (32)
  • 5.6 ELV Equipment installation (39)
  • 5.7 Testing and Commissioning (49)
  • 6.1 Organization (50)
  • 6.2 Responsibilities (50)
  • 7.1 General (54)
  • 7.2 Medical Facility (55)
  • 7.3 Medical Staff (55)

Nội dung

METHOD SATEMENT OF FIRE SYSTEM FOR OM ACCOMODATION METHOD STATEMENT OF EXTRA LOW VOLTAGE SYSTEM 1 0 2022 05 13 V K Hoan T D Thinh T N Khoa First Issue Rev Date Prepared Checked Approved Details of Revision Owner VUNG ANG II THERMAL POWER LLC Owner’s Engineer TOKYO ELECTRIC POWER SERVICES CO , LTD EPC Contractor PACIFIC CORPORATION JSC Subcontractor HOP LUC CONSTRUCTION JOINT STOCK COMPANY Project VUNG ANG II THERMAL POWER PLANT PROJECT Title METHOD STATEMENT OF EXTRA LOW VOLTAGE SYSTEM Document.

General discription

Extra low voltage (ELV) system (Lan system, CCTV system, Public Address system,

Burglar and security system) construction methods apply to areas including: Family apartment, Management house, Multi-functional gym and healthy care house,

Supermarket and restaurant, external area, substations and pumping stations, sewage treatment plants

Based on documents

 Standards Required by Statutory Regulations

1 QCVN 32:2011/BTTTT National technical regulation on lightning protection for telecommunication stations and outside cable network

2 QCVN 09:2016/BTTTT National technical regulation on earthing of telecommunication stations

3 QCVN 22:2010/BTTTT National technical regulation on electrical safety of

4 TCVN 8235:2009 ElectroMagnetic Compatibility (EMC) -Telecommunication network equipment-ElectroMagnetic compatibility requirements

5 TCXD 175-2005 Permissible noise level in public works Design standards

6 TCVN 4510: 1988 Sound studio Architectural sound technical requirements

7 TCVN 4511: 1988 Sound studio Building sound technical requirements

Commercial Building Telecommunications Cabling Standard - Part 2: Balanced Twisted-Pair Cabling Components - Addendum 2 (ANSI/TIA/EIA-568-B.2-2-2001)

Commercial Building Telecommunications Cabling Standard - Part 2: Balanced Twisted-Pair Cabling - Addendum 3 - Additional Considerations for Insertion Loss and Return Loss Pass/Fail Determination (ANSI/TIA/EIA-568-B.2-3-2002)

10 EIA/TIA-568 Commercial Building Wiring Standard (superceded by TIA/EIA-

11 TIA/EIA-568-A Commercial Building Wiring Standard (superceded by TIA/EIA-

Additional Horizontal Cabling Practices for Open Offices (superceded by TIA/EIA-568-B.1, TIA/EIA-568-B.2, and TIA/EIA-568-B.3)

Commercial Building Wiring Standard, Addendum 1 - Propagation Delay and Delay Skew Specification for 100 Ohm 4-pair Cable (superceded by TIA/EIA-568-B series)

Technical Specifications for 100 Ohm Screened Twisted-Pair Cabling (superceded by TIA/EIA-568-B.1, TIA/EIA-568-B.2, and TIA/EIA-568-B.3)

Commercial Building Telecommunications Cabling Standard - Part 2: Balanced Twisted Pair Cabling Components

16 TIA/EIA-568-B.1 Commercial Building Telecommunications Cabling Standard -

Part 1: General Requirements (ANSI/TIA/EIA-568-B.1-2001

Commercial Building Telecommunications Cabling Standard - Part 1: General Requirements - Addendum 1 - Minimum 4-Pair UTP and 4-Pair ScTP Patch Cable Bend Radius (ANSI/TIA/EIA- 568-B.1-1-2001)

Commercial Building Telecommmications Cabling Standard - Part 2: Balanced Twisted Pair Components - Addendum 4 - Solderless Connection Reliability Requirements for Copper Connecting Hardware (ANSI/TIA/EIA-568-B.2-4-2002)

Commercial Building Telecommunications Cabling Standard - Part 2: Balanced Twisted Pair Components - Addendum 1 - Transmission Performance Specifications for 4-Pair 100 Ohm Category 6 Cabling (ANSI/TIA/EIA-568-B.2-1-2002)

Commercial Building Telecommunications Cabling Standard - Part 1: General Requirements - Addendum 2 - Grounding and Bonding Requirements for Screened Balanced Twisted-Pair Horizontal Cabling (ANSI/TIA/EIA-568-B.1-2-2003)

Commercial Building Telecommunications Cabling Standard - Part 2: Balanced Twisted Pair Cabling Components - Addendum 6

- Category 6 Related Component Test Procedures (ANSI/TIA-568- B.2-6-2003)

Commercial Building Telecommunications Cabling Standard - Part 1: General Requirements - Addendum 5 -

Telecommunications Cabling for Telecommunications Enclosures (ANSI/TIA-568-B.1-5-2004)

23 TSB-40-A Additional Transmission Specifications for Unshielded Twisted-

Pair Connecting Hardware (superceded by TIA/EIA-568-A) Table 1.1 Applicable technical standards

Project Materials

- Materials use at project for install of extra low voltage system: Lan system, CCTV system, Public Address system, Burglar and security system, ELV equipments, ELV cable, accessory

In accordance with the technical specifications outlined in the Bidding Documents and Design Drawings, all primary supplies and materials must be submitted as samples along with their respective material certificates for approval by the Owner prior to their utilization.

List of machinery & tools

No Name Unit Quantity Note

1 Drilling machine Pcs 1pcs/5 peoples

3 Electrical jack Pcs 1pcs/5 peoples

4 Cutting machine Pcs 1pcs/5 peoples

5 Electrical Panel Pcs 1pcs/5 peoples

8 Hand tools Set 1set/2 peoples

9 Measuring tape Pcs 1pcs/1 person

10 Line marker Pcs 1pcs/1 person

17 Level Instrument Pcs 1pcs/ 2 peoples

18 Hand crimping tool Set 1set/ 2 peoples

No Name Unit Quantity Note

19 PVC pipe cutter Pcs 1psc/1 person

23 Optical time-domain reflectometer Psc 1

Table 2.1 List of tools and machinery

+ Note: The certificated and relevant document of the special equipment will be submitted prior to use at site.

List of Personal Protection Equipment (PPE)

1 Hi vis 7 Half Rubber Coated Gloves

2 Safety shoes 8 Plastic coated gloves

Table 2.2 List of PPE mobilization

Manpower Mobilization

No Work item Quantity Scope of work

1 Mechanical worker 3 Workers are rotated from one item to another depending on the actual construction

No Work item Site manager

Multi-functional gym and health care house

Responsibilities

The Contractor sets up a Project Management Unit to oversee the project, which includes an executive board, an assisting department, and direct construction teams responsible for executing specific construction tasks.

Relationship between the Board of Management and the site management department

The Company's Board of Directors oversees the departments and the Site Management Unit, ensuring that each department is assigned tasks aligned with their expertise They provide direct guidance and supervision to the site manager to ensure effective contract execution, adherence to appropriate construction methods and regulations, quality control, technical management, and safety measures Additionally, they are responsible for the supply of materials and human resources.

The site management department, led by the Site Manager, is responsible for providing regular reports to the Board of Directors regarding the construction status and management aspects of the site The Site Manager must coordinate with relevant departments to ensure that all requirements are met and that construction proceeds in accordance with the design documents, maintaining the project's technical quality Additionally, the Site Manager is tasked with addressing issues in each construction area promptly and effectively.

- Perform the tasks assigned by the Board of Directors and take responsibility for the

TA DUC THINH Deputy Site Manager 0982.351.435

TRINH NGOC KHOA Site Manager 090.3468.016

DO DINH HUONG Mechanical Engineer 0359.445.933

A site engineer plays a crucial role in managing human resources, techniques, quality, and project progress They conduct daily checks and monitor the construction process to ensure adherence to the design specifications Additionally, site engineers coordinate effectively with the owner, design consultants, and the owner's engineer, as well as other relevant parties, to address any issues that arise on the construction site.

In the absence of the site manager, fulfill all assigned tasks and responsibilities to effectively oversee construction site operations on their behalf.

Department of Progress, Technical and Quality Management

- The head of this department is the construction technical manager - responsible to the Site Management Unit for the technique, progress and quality of the work

The technical department oversees project progress and construction techniques, ensuring quality in every job They assist the site manager and on-site technicians while maintaining communication with Party A and engineers Their responsibilities include consulting on construction technical solutions, conducting acceptance work, creating as-built documents, and maintaining a daily monitoring diary.

Safety, security and environment management department

The safety department is responsible for gathering, researching, and disseminating legal documents related to labor protection across teams Additionally, it organizes training courses on labor protection for employees at the construction site, ensuring compliance and safety standards are upheld This department is managed by a dedicated full-time officer alongside part-time site technicians.

Officers play a crucial role in maintaining safety, security, and environmental standards on construction sites They assist the Site Manager and technicians, ensuring their constant presence on-site Their primary responsibilities include implementing measures to protect both personnel and equipment while fostering a positive working environment.

The medical department is dedicated to ensuring the health and safety of staff and construction workers by providing care for minor illnesses and dispensing necessary medications In the event of an accident, they perform first aid and assess whether the patient needs to be transported to a hospital for further treatment Additionally, the department regularly reports to the site Management Unit and the company's board of directors regarding the status of occupational accidents occurring on the construction site.

The department tasked with overseeing and managing personnel is essential for ensuring timely worker payments and allocating funds for materials and equipment This department plays a critical role in coordinating with construction teams and equipment operations, fostering effective collaboration for project success.

The technical management department plays a crucial role in overseeing the supply of materials and equipment, which significantly impacts product quality and construction progress.

- Follow the direction of the technical management department for each work area

- Includes teams: Construction motorbike, formwork + scaffolding + reinforcement + concrete, masonry + finishing, mechanical group, aluminum and glass, plaster + paint, electricity and water team, construction team

- Each team will include 01 team leader and 01 supervisor who is responsible for managing the team's human resources, progress, and quality before the project

The field organization model prioritizes quality and construction progress, showcasing a well-structured and scalable approach It highlights the specialized expertise of each production team while ensuring their dynamic collaboration.

- Well perform the registration of temporary absence with local authorities

- Ensure absolute security and order, social safety in the area

- Establish site rules and regulations on labor safety, organize for workers to study and strictly implement the set rules

- Workers entering and leaving the construction site must have a card provided by construction unit

Coordination at site

- Survey at site before the installation

- Survey and understand the current progress of the main structure and the site with reference to Safety Management System and contract requirement and engineering due diligence.

Work flow chart

Proceed to other related works

Construction requirements

- When arranging the construction site, it does not affect the operation and general landscape, ensuring traffic, safety and environmental sanitation Ability to quickly adapt to unexpected changes

- The layout of the construction site must be reasonable and convenient, minimizing dust and noise affecting the operation of the surrounding area and not obstructing the construction process

- Ensure reasonable construction without overlap causing work stoppage and unsafety

- Ensure security and order and good fire prevention

- Listing for all materials used for ELV system, making plan for submission, purchasing and installation

- Listing for all shopdrawing used for ELV system, making plan for submission and installation

- Listing for all methodstatement used for ELV system, making plan for submission and installation

5 INSTALLATION OF EXTRA LOW VOLTAGE (ELV) SYSTEM

ELV underground conduit installation

- Describe construction works relate with installating of ELV underground conduit

Works are execute base on construction schedule and detailed approval drawing a Material

- ELV underground conduit must be ordered according to the approved type and manufacturer b Preparation

- Prepare the excavator to excavate ditches to lay conduit

- The work shall be start when installation schedule allowed

- Check ELV underground conduit location follow to approved shop drawing are ready for installation

- Check the route to transport the ELV underground conduit to the installation location

- Determine actual, correct size, type of conduit as per location need to install follow to approval drawing

- The Safety Officer will check the area to ensure no potential incidents before install c Installation work

- Mark the route of underground conduit the ground before excavate

- Re-check collisions with other systems

- Use the excavator to excavate underground duct until the required depth, wide and length

- Check the depth of trench for proper elevation

- Clean to ensure the trench is free from debris and foreign materials

- To execute install ELV underground conduit

- Invite main contractor and consultant to inspect

- Back-fill until the depth 300mm below finish grade then install warning tapes

- After inspect with consultant or take verification piecture, back-fill until finish grade

- Ensure that the back-fill material is properly compacted

* Detailled excavation and backfilling work follow design drawing:

- Use conduit cap and ELV tape to seal the exposed terminals on the ground to avoid rocks and foreign objects falling into the conduit

* Some picture about the ELV underground conduit installation work:

Picture 5.1-1 Excavation and conduit installation works

- Materials shall be checked for quality, quantity, size, type

- Inspect ELV underground conduit installation:

• Check location, route of ELV underground conduit follow to appoval shop drawing

• Check for warning tape laying and take verification photo to save record

• Check for compaction work after back-fill

+ Inspect with Contractor’s and Owner’s Inspector :

- Materials shall be checked for quality, quantity, size, type by PAC’s Inspector

- Inspect ELV underground conduit installation:

• Check location, route of ELV underground conduit follow to appoval shop drawing

• Check for warning tape laying and take verification photo to save record

• Check for compaction work after back-fill

Rack Panel Installation

Describe electrical works relate with installating of Rack panels

Works are execute base on construction schedule and detailed approval drawing a Materials

- Rack panels shall be standard manufacture’s as per approved type

- Size, type: As per approved catalogue manufacture b Preparation

- The work shall be start when civil works of Rack panels location have completed, clean, handed over and approval of installation schedule

- Check Rack panels location follow to approved shop drawing are ready for installation

- Visually inspect the device for warping, dents, scratches, etc Read the installation instructions of the equipment supplier

- The Safety Officer will check the area to ensure no potential incidents before lifting c Installation work

- Determine actual, correct type of rack panel as per position need to install follow to approval drawing

- Before construction, it is required to clean the construction site area

- For Rack panels on the floor, use means such as rollers, cranes, and lifts etc

- Making of position for Rack panels on foundation or wall

- Secure panel base to the floor/wall using anchor bolts

- Check the leveling before tighten bolt

- After installation, fix the electrical cabinet, proceed to connect the ground to the cabinet

- Determine Install modulies and equipment into rack panel

To ensure optimal safety and functionality, regularly clean the electrical cabinet using a vacuum cleaner Inspect all connections for secure bolts, verify the insulation on colored cables, and check the markings on the cables Additionally, connect the ground wire from the cable tray ladder to the electrical cabinet cover and seal any openings for both input and output cables.

+ Some picture about the Rack panels installation work:

Picture 5.2-1 Take out rack panel form storage

Picture 5.2-2 Bring the Rack panel into position using wooden rollers and levers

Picture 5.2-3 Outdoor Rack Panel Installation

Picture 5.2-4 Cable connection in rack panel

- Materials shall be checked for quality, quantity, size, type

• Check position, leveling and condition of Rack panels

• Check panel base frame bolt tightening

+ Inspect with Contractor’s and Owner’s Inspector :

- Materials shall be checked for quality, quantity, size, type by PAC’s Inspector

• Check quality of installed Rack panels on site

• Check position, leveling, rating and condition of Rack panels

• Check correct components of Rack panels

ELV cable tray and trunking installation

- Describe electrical works relate with installating of ELV cable tray and trunking

Works are execute base on construction schedule and detailed approval drawing a Material

- The ELV cable tray and trunking will be standard manufacturer’s galvanized structural steel & with all standard accessories

- As per approved catalogue manufacture

- Prepare angle bars or c-channel or unistrut as supporting

- Prepair anchor bolt, thread rod, nut M10, M12 b Preparation

- The work shall be start when civil works of Cable tray and trunking location have completed, clean, handed over and approval of installation schedule

- Check Cable tray and trunking location follow to approved shop drawing are ready for installation

- Check the route to transport the Cable tray and trunking to the installation location

- Determine actual correct size & type of ladder, tray as per location need to install follow to approval drawing

- Determine actual, correct & type of support(angle bars, c-channel,unistrut, thread rod) as per type of ladder, tray and installation location

- The Safety Officer will check the area to ensure no potential incidents before lifting c Installation work

- Making of position for Cable tray and trunking support on foundation or wall or ceiling

- Use a laser machine to mark the cable ladder, tray according to the approved drawing

- Re-check collisions with other systems

- Drilling hole & setting of anchor

- Setting thread rod and tghiten by hand tool (at ceiling location)

- Install the support bars for the cable tray/trunking with distance 1,2m – 1,5m

- Tighten bolt to fix support after verify correctly elevation of support

- Move each tray/trunking to the support

- Secure ELV tray/trunking by bolts and nuts

- Fix 2 adjacent ELV tray/trunking by connection of cable tray/trunking and bolt, nut

- Between 2 cable trays connected by grounded braided copper wire

- Aligning cable ladder/tray route correctly in elevation, vertical, horizontal

* Detailled ELV cable tray & trunking installation follow as:

* Some picture about the cable tray and trunking installation work:

Picture 5.3-3 Tray/trunking support installation

Picture 5.3-5 Finishing and installation of cable tray/trunking

- Materials shall be checked for quality, quantity, size, type

- Inspect ELV tray and trunking installation:

• Check position, leveling and condition of ELV tray and trunking

• Check tightening connection bolts between components

+ Inspect with Contractor’s and Owner’s Inspector :

- Materials shall be checked for quality, quantity, size, type by PAC’s Inspector

- Inspect ELV tray and trunking installation:

• Check quality of installed ELV tray and trunking on site

• Check position, leveling, rating and condition of ELV tray and trunking

• Check correct components of ELV tray, trunking and connection

ELV PVC conduit installation

- Describe construction works relate with installating of ELV conduits for protection of ELV cabling

Works are execute base on construction schedule and detailled approval drawing a Material

- ELV conduit must be ordered from an approved type and manufacturer b Preparation

- Check ELV conduit location follow to approved shop drawing are ready for proceed work

- Determine actual, correct & type of conduit as per location need to install follow to approval drawing

- The Safety Officer will check the area to ensure no potential incidents before lifting c Installation work:

* PVC conduit embedded in concrete floor

- Install PVC conduit exaclly of switch, Joint box in the wall/ floor follow shop drawing approved

- Use painting or pen colour marking location Switch, Junction box…

- After finish layer 1 rebar, and then install conduit exaclly area Fix conduit strong on rebar

- After install conduit finish we wiring iron fix all conduit Between 2 wiring fix conduit under 800mm- 1000mm

- Install conduit must follow area equipment and structure on floor

To optimize sound distribution, position two sound boxes 10 to 15 meters apart and install an additional intermediate sound box Ensure that the pipes connecting the sound boxes are joined with appropriate joints and secured using plastic pipe glue Additionally, reinforce the setup by firmly anchoring it to the floor with iron supports.

- Boxed inside the wall/ floor, we have push polyform and taping

- All Boxed must fix strong on the wall/ floor by wiring iron, 1 side boxe tangent coffa From boxes to wiring maxium 300mm

Pipelines with two or more parallel pipes must maintain a minimum distance of 20mm between the inner edges of adjacent pipes to facilitate proper concrete insertion, excluding the areas where the pipes connect to an intermediate box.

To ensure optimal functionality, it is crucial that the pipes are securely reinforced on the cabinet and the equipment ends Additionally, there must be a minimum distance of 20mm maintained between the inner edges of adjacent pipes.

- Before casting conrecte must be check all boxed and conduit and during time we have

* ELV conduit conceal in wall

- The job cutting walls are deployed after construction was complete walls and has been hand over by the parties

When conducting a deployment cut for a wall, it is essential that the cut is precise and compatible with the pipe installation The width of the wall cut should exceed the pipe diameter by at least 20 mm, while the depth of the cut should be approximately 5 to 10 mm greater than the pipe size.

- Marker the position of the switch and box in brick as approved drawings

- After finishing layer of bricks, the contractor will pipe marking on brick wall with 2 lines marked as pipe size, distance & number installed

- Use cutting tool or specialized cutters to cut brick wall exactly with 2-way marking and around box or cabinet

- Installation PVC conduit with sound box & room cabinet by threaded connection as approved drawing

- The conceal box must twist screw and filled with foam in box and taped to prevent sticking motar on the box

- Location as buit of pipe must be saved before to plastering

- The pipe must be fix to steel to prevent movement during plastering

- Use specialized stuccos and ciments wall to phaster where installed PVC conduits

* PVC conduit floating on ceilings, walls:

Conduit size Maximum distance between 2 saddle ỉ20 ≤1.0 m ỉ 25 ≤1.2 m ỉ 32 ≤1.5 m

Maximum distance from connection box to saddles : 0.3 m

+ Some picture about the ELV conduit installation work:

- Materials shall be checked for quality, quantity, size, type

• Check position, route of ELV conduit follow to approval shop drawing

• Check the physical condition of the conduit after installation (no distortion, damage )

• Check the inside of the pipe: there are no obstructions (bricks, mortar, etc.) to avoid blockages during cable pulling

+ Inspect with Contractor’s and Owner’s Inspector :

- Materials shall be checked for quality, quantity, size, type by PAC’s Inspector

• Check position, route of ELV conduit follow to approval shop drawing

• Check the physical condition of the conduit after installation (no distortion, damage )

• Check the inside of the pipe: there are no obstructions (bricks, mortar, etc.) to avoid blockages during cable pulling

ELV cabling

Describe construction works relate with ELV cabling

Works are execute base on construction schedule and detailed approval drawing a Material

EVL system cable include : Lan cable cat 6, audio cable 18AMG, lan cable cat 5, fiber optic cable, etc

- Make storage for gathering construction materials

- Gather materials to site or necessary location

- Request the representatives of main contractor and owner to inspect input materials b Preparation

- Prepare specific tools for pulling and laying cables: cable drum rack, rotation shaft, roller, bait wire, cable winch machine (if necessary), cordless crimper, etc

- The work shall be start when cable ladder, tray, underground conduit, conduit have completed and cleaned base on installation schedule

- Check cable route location follow to approved shop drawing are ready for pulling, laying

- Check the route to transport the cable to pulling, laying location

- Based on detailed schedule, approvalled cable route shop drawing, cable schedule to determine actual, correct type of cable as per location need to pull, lay

- The Safety Officer will check the area to ensure no potential incidents before lifting

- Deploy personnel depending on the details progress of construction:

 Each team of 20 to 25 people

 Each crew of 2 to 3 people

- Note: combine drawings of HVAC system, water system, electric system, fire fighting system with each other so that the installation will not be overlapped c Cable pulling, laying work:

* Pulling cable on tray & trunking

- Before putting up wide cable conduct discharge each cable wires in cable drum, using specialized cable discharge arm with large cross section

- Conduct scattered each cable wire by circulating method, prohibits use drag-end scratch and stretch cables

- When all of the cable in a process have finished, conduct rearrange and positioning them in ladder by nylon cable ties, ensure that the parallel cables and no cross,confusion

To install cable across the floor, an electric winch is mounted on the roof of the technical box to facilitate vertical hooking This process is initiated after securing the cable into the pre-installed cable ladder.

To ensure labor safety, it is essential to apply the technical box for cleaning the working platform on all floors To facilitate synchronized operations among the upper and lower levels and the electric winch operator, contractors will provide radios for effective communication during this process.

To ensure a smooth inspection process, the team leader must organize all scattered cable wires according to the designated lines Each cable line should be clearly marked with codes as specified in the drawings, and these markings must receive approval from both the main contractor and the consultant.

- All other exceptions and problems encountered during the construction must be reported to suppervidor try to correct, not arbitrarily constructed to avoid serious consequences later

To ensure proper identification and connection, mark the two exposed ends of the cable with colored glue, following the approved construction drawings It is essential to maintain the colored tape markings from the moment the cable is pulled until the electrical panel connection is completed.

* Pulling cable method in PVC conduit

- Before pulling the wire, must used bait thread through all the PVC conceal conduit to fix the broken pipes or stuffy concrete during concreting

- PVC conduit conceal are filled before pulling cable

- Follow shopdrawing approved, prepared raw wire coil and node rope Threaded bait thread in section PVC conduit for pulling wire

To ensure proper identification and compliance with approved construction drawings, mark the two exposed ends of the cable with colored glue while pulling the phases It is essential to maintain the colored tape marking on the cable ends from the moment of pulling until the connection to the electrical cabinet is completed.

When connecting equipment to electrical cabinets, it's essential to use reasonable wire lengths for optimal functionality For ceiling-mounted lights, a wire length of 20cm is recommended, while recessed ceiling lights should also have a 20cm wire length extending over the gypsum ceiling Additionally, ensure that the wire length at the electrical cabinets is appropriate for the rectangular layout, with a 15cm length designated for switches.

* After completing work the pull the wire, shall test insulation, between the cables, between phases, continuty test Testing record d Termination:

 Step 1: Prepare plans, materials and construction tools

 Step 2: Make sure all cables are neatly arranged in the rack panels with the right space

 Step 3: Cut and expose cable end

 Step 4: Put the cosse in the cable end, the number of holes in the cosse depends on the cable size

 Step 5: Use a cordless crimper to press the cosse and cables

 Step 6: Use a spanner to connect the cosse and the busbar with the appropriate force

 Step 7: Use a marker to mark bolt and bolt positions

* Some picture about the ELV cable laying, pulling work:

Picture 5.5-2 Fiber Optic cable pulling

Picture 5.5-3 Bait rope for ELV cable pulling

Picture 5.5-5 Connect ELV cable into rack panel

- Check cable type correctly with appoval cable shop drawing

• Fix cable by cable tie with requirement distance

• Physical check termination work at start point and end point

- Check cable status (start point, end point, cable route )after cable pulling, laying, termination compare with cable shop drawing and detailled cable schedule

+ Inspect with Contractor’s and Owner’s Inspector

- Materials (power cable)shall be checked for type by PAC’s Inspector

• Fix cable by cable tie with requirement distance

• Physical check termination work at start point and end point

- Check cable status (start point, end point, cable route )after cable pulling, laying, termination compare with cable shop drawing and detailled cable schedule

- Continuity test by tester witness by PAC and Owner Inspector

- Record test report and signed by 3 parties

ELV Equipment installation

- Describe construction works relate to installating of extra low valtage system equipments

Works are execute base on construction schedule and detailed approval drawing a Material

- CCTV system : Outdoor IP camera, outdoor PTZ 32x IP dome camera, indoor dome camera, Network video recorder, POE switch, Led monitor, etc

- Lan system : ODF, Lan outlet socket, Television outlet socket, Telephone outlet socket, Wifi module, etc

- PA system : Ceiling mount speaker, Pendant speaker, box speaker, horn speaker, remote microphone, audio interface unit, amplier controller,

- Burglar and security system : Communicator module, transmitter, receiver, siren, etc All EVL equipment must be ordered from approved specification and manufacturer b Preparation

- The work shall be start when civil works of ELV equipment position have completed, clean, handed over and approval of installation schedule

- Check ELV equipment location follow to approved shop drawing are ready for installation

- Determine actual correct type ELV equipment as per location need to install follow to approval drawing

- The Safety Officer will check the area to ensure no potential incidents before lifting c Installation work:

* Lan, TV, Telephone outlet socket:

- Specify type of equipment follow to approved shop drawing

- Use ELV featured hand tools connect wiring to socket follow instruction manual

- Fix wiring device on available conceal box by bolt M4

- Use level tool to check level of socket

+ Some picture about outlet socket and witch installation work:

Picture 5.6-1 Connect lan cable to Lan outlet socket

Picture 5.9-2 Install and align by water leveling

* Equipment mounted ceiling (indoor dome camera, Wifi module, ceiling mount speaker:

- Based on partition, column for specify grid line then use laser machine and scale meter for specify location of lighting fixture or depend on ceiling panel frame

- Note: While make shop drawing, we have to combine with HVAC, firefighting, ELV for combine system

- Determine actual correct type of equipment as per location need to install follow to approval drawing

- Specify support, hanger, fix support with the wall, concrete column

- Marking by marking pen or chalk

- For the long line of lighting, we need use laser machine for checking straight and level

- For the wall mounted lighting: ensure that level, dimension, beautiful

- For the ceiling mounted or concrete surface mounted lighting: ensure that dimension, direction and no gap Use laser machine and scale for check square, parallel and straight

* All the installation & connection of process above base on the design drawings following:

* Some picture about ceiling mount equipment installation:

Picture 5.6-4 Dome IP camera installation

Picture 5.6-5 Ceiling mount speaker installation

Picture 5.6-6 Wifi access point installation

* Concrete ceiling or wall mounted equipemt (Outdoor IP camera, outdoor PTZ 32x IP dome camera, Led monitor, Pendant speaker, box speaker, horn speaker, remote microphone, transmitter, receiver, siren, etc.) installation:

- Determine actual correct type of equipment as per location need to install follow to approval drawing

- Mark the mounting position on the wall

- Drill hole and install expansion bolt

- Align leveling of equipment before tighten bolts

- Connect power and signal cable to equipment

* All the installation of process above base on the design drawings follow in:

+ Some picture about ELV wall mounted equipment installation:

Picture 5.6-7 Leveling and installation for box speaker

Picture 5.6-9 Complete CCTV system installation

- Materials shall be checked for quality, quantity, size, type according to approvalled shop drawing, document, certificate of equipment

• Check tightening connection bolts between components

• Check the power and signal cable connection to the equipments

• Temporary power supply for testing ELV system equipments

+ Inspect with Contractor’s and Owner’s Inspector :

- Materials shall be checked for quality, quantity, size, type according to approvalled shop drawing, document, certificate of equipment by PAC’s Inspector

• Check beauty hygiene after installation

• Check tightening connection bolts between components

• Check the power cable connection to the equipment

• Temporary power supply for testing ELV system equipment

Testing and Commissioning

- Check all the cable connections and ensure correct

- Check all the devices ensure the correct connection

- Check the circuit, wire insulation all with DDC

- Commissioning of the unit each individual system

- Acceptance interlock load the electrical system under the supervision

Organization

The HCA Contractor is responsible for ensuring effective HSE Field Supervision by appointing a qualified Site HSE Manager, along with a sufficient number of Superintendents, Supervisors, and Officers This staffing must align with the number of direct work employees and the various work locations that require oversight.

- Each isolated area will be arranged with at least one safety officer per a working team

- One full time field safety officer will be arranged for per each 50 workers

- One full time field safety supervisor will be arranged for per each 200 workers

- The Vapco may varify Hsse personnel of CONTRACTOR and its subcontractors during implementation of the Project

VAPCO retains the authority to dismiss any HCA Contractor or Subcontractor Site HSE Manager following ongoing site competency evaluations In the event of such a dismissal, the HCA Contractor is required to submit the CV of the new Site H&S Manager to VAPCO for approval within seven days.

Responsibilities

The Project Manager is responsible for establishing the project’s Health, Safety, and Environment (HSE) organization This includes appointing a registered Health and Safety (H&S) Manager who will have clearly defined roles, responsibilities, and authority The H&S Manager ensures the effective establishment, implementation, and maintenance of the HSE Management System in compliance with applicable regulations and standards.

The Project Manager provides an organizational chart that outlines the site management team responsible for executing the Works This project management team is adequately sized and possesses the necessary experience and competence to effectively implement the Health and Safety management system.

The Project Manager has the ability to delegate specific tasks or functions to a member of their management team, granting them the necessary authority to fulfill these responsibilities However, it is important to note that the ultimate accountability for the project still lies with the Project Manager.

The Project Manager is responsible for establishing effective communication channels to inform employees about Health, Safety, and Environmental (HSE) matters Additionally, he will ensure that all staff members receive the necessary training relevant to their specific roles.

The Project Manager will spearhead the development and promotion of Health, Safety, and Environment (HSE) initiatives, utilizing the management system to set necessary standards He will consistently monitor the workforce's performance to ensure that the project meets its HSE targets.

The Project Manager plays a crucial role in upholding the Health, Safety, and Environmental (HSE) commitment of the project management team This responsibility entails a comprehensive understanding of the key objectives and requirements outlined in the HSE policy, standards, and procedures, particularly when assigning responsibilities across various levels of supervision.

- Specifically, the Project Manager shall:

- Assure that approved HSE procedures are adopted for defining methods and systems to be applied

- Assure that all relevant laws, regulations and other requirements in matters of HSE are respected

- Maintain HSE relations with Owner, Sub-contractors, Vendors and with Governmental Authorities and organizations for all items regarding HSE

- Overall charge of the Project HSE organization, including medical care and first aid, HSE Training, etc

6.2.2 Responsibilities of the HSE Manager

The HSE Manager will report directly to the Project Manager regarding all health, safety, and environmental (HSE) activities on site This role involves supporting the Project Manager in health and safety matters by promoting HSE programs and ensuring compliance with all HSE requirements.

- Set up an adequate and strong HSE management system

- Ensure the development and implementation at site on activities described in this plan and other procedures

- Organize site so that work is carried out to the required standard with minimum risk to men, equipment, and materials

- Provides H&S consultancy to project management team

- Report any HSE issues/incident/accident to VAPCO

- Lead and ensure HSE incidents and non-compliances are investigated and corrected;

- Set up an site emergency response plans and procedure

- Leads the development and maintenance of Site Emergency Response Plans and

- Participates in the development of Site Security Plans and Procedures

The development of a robust Health, Safety, and Environment (HSE) culture is essential for achieving outstanding HSE performance This involves creating comprehensive coaching and training plans, overseeing the preparation of relevant training materials, and ensuring effective delivery of these programs throughout the project.

- Leads the investigation of accidents and incidents

 Conduct and chair the site HSE Monthly Committee Meetings;

- Conduct and chair the weekly, monthly site HSE tours

- Update HSE plans and procedures

- Review and approve subcontractors’ HSE plans/procedures/permit to work

- Review Risk Assessment & JSEA’s when required

- Conduct and chair incident response drills

- Ensure construction methods minimize risk to public & workers e.g through adequate Traffic Management

All equipment delivered to the site must be safe, fully operational, and equipped with appropriate safety devices It is essential that all plant machinery is tested in compliance with HSE Management Plans, and that evidence of all necessary certifications is maintained on-site.

- Manage the H&S organization at site

- Ensure that all activities regarding work safety and hygiene are carried out in accordance with the HES plan and procedures

6.2.3 Responsibilities of H&S Officers (Engineers & staffs)

- The H&S officers shall assist the H&S Manager by ensuring that the provisions of the H&S plan and other H&S related requirements are correctly complied with by HCA

CONTRACTOR personnel and Sub-contractors in each working area

- They ensure direct supervision and coordination of the Sub-contractors’ activities and day to day contacts with them to deal with any H&S matters

6.2.4 The H&S officers’ general responsibilities include, but not limited to:

- Verifying that all workforce under HCA CONTRACTOR’s direct or indirect responsibility receive appropriate H&S information, induction and training, including supervision and control on the H&S training program by Sub-contractors

- Advising the H&S Manager of any necessary required actions to improve working and living conditions in the field under their individual responsibility

- The H&S officers shall attend tools box meetings

- The H&S officers shall inspect unsafe conditions and acts

- Organizing, managing and recording of meetings with sub-contractors as per the H&S relevant meetings program

- Ensuring adequate levels of working and living conditions by means of regular inspections on housekeeping, hygiene, potable water system, kitchens and canteens, sewer system and waste disposal etc

- Leading accident, incident investigations and attending any major accident investigation in areas under their responsibility and reporting on them to the H&S Manager as per the Accident Reporting Procedure

- Organizing and managing the medical and first aid facilities in areas under their control

- Daily check and regular inspection of PPE

- The H&S officers shall report to the H&S Manager on H&S matters

6.2.5 Responsibilities of Construction Manager, Section Managers and Supervisors

- Construction Manager, Section Managers and supervisors generally shall assist the

Project Manager / the H&S Manager in the execution of their duties

- Being familiar with the requirements and recommendations for Safe Working Practices Method Statements and Risk Assessments etc applicable to their work place and ensure that they are enforced

- Incorporating H&S instructions into the routine day to day orders and make sure they are understood and obeyed

- Preventing site persons from taking unnecessary risks

It is essential to ensure that all operatives and laborers receive appropriate training for their specific tasks, particularly for new employees and subcontractor personnel, to promote the adoption of proper health and safety precautions.

- Checking that all plant and equipment, including power and hand tools are maintained in a good condition and remove from use any defective items

- Maintaining organized, tidy and safe working areas

- Maintaining all welfare facilities in a clean and safe condition

- Ensuring that all operatives/labor are provided with and use approved personal protective equipment

- Ensuring that instructions are given in the use of any potentially hazardous materials

- Ensuring that other persons including Owner representatives, other contractors and members of the public are protected from the work activities of HCA CONTRACTOR and its subcontractors

It is essential to discourage horseplay in the workplace and to take decisive action against individuals who repeatedly neglect their own health and safety, as well as that of their colleagues and those nearby Prioritizing a safe working environment is crucial for everyone's well-being.

- Stopping any activity on site if there is an immediate risk of injury to any site personnel, or the possibility of a dangerous occurrence happening

- Each section or working groups’ supervisors shall have a skill to monitoring, supervision and instructions through the training courses

6.2.6 Responsibilities of Subcontractors and Vendors Personnel

Every Sub-contractors / Vendors Personnel working on the Project Site shall:

- Comply with all H&S rules and other requirements

- Adhere to this H&S plan and comply with the H&S requirements and procedures These are to be observed as minimum requirements

To ensure compliance with health and safety regulations, the site organization must include a Health and Safety (H&S) supervisor who directly reports to the subcontractor's site manager This supervisor will assist in overseeing that all activities within the subcontractor's or vendor's scope of work adhere to project-specific H&S requirements, the established H&S plan, and safe working procedures.

To maintain effective health and safety (H&S) standards, organizations must ensure that an appropriate number of H&S supervisors are present on-site, relative to the total workforce of subcontractors These supervisors are essential for supporting the H&S officer and ensuring proper enforcement of H&S procedures throughout the execution of the work.

- Ensure that all of their own personnel are aware of H&S requirements arising from laws, regulations and the contract and observe them by planning appropriate training of their personnel

To ensure the safety of their workforce, it is essential to identify and analyze all potential job hazards, implement necessary preventative and protective measures, and provide personal protective equipment (PPE) as required for the tasks at hand.

- Regularly record site H&S inspections and appropriate inspections for maintenance of installations, plant /equipment, work tools and personal protective equipment, with the objective of identifying early any potential hazard

- Cooperate with HCA CONTRACTOR in investigating incidents, accidents to identify and enforce corrective actions to prevent recurrence

Participate in health and safety meetings and adhere to the established coordination procedures to effectively prevent or reduce risks associated with overlapping activities in shared spaces.

General

HCA CONTRACTOR will ensure the availability of medical facilities on-site to provide immediate assistance to workers in case of incidents Trained first-aid personnel, along with appropriate first-aid equipment and facilities, will be present at both the Site and camp A doctor and a nurse will be assigned to these locations, with their CVs submitted to Vapco for approval Comprehensive medical resources will be provided to ensure worker safety and health.

The contractor will adhere to local standards for medical support services and is considering entering into a medical service contract with Ky Anh General Hospital Evidence of this agreement will be submitted to Vapco by the specified deadline.

Each work site will ensure effective communication with the Occupational Medical Service, whether it be a hospital or clinic A comprehensive list detailing the nearest hospitals, along with their locations and contact numbers, will be prominently displayed in all Site Offices, including those of subcontractors and camp offices.

- Prior to the start of work, arrangements will be made for medical facilities and medical personnel to be available at the construction Site and the camp

- Effective communication and transportation to care for injured workers will be provided

- Where professional medical services are available, each work Site will set up terms and conditions for use and maintain close communication with them

- A list of the available hospitals including locations and their phone numbers will be displayed at all Site and camp offices including Subcontractors’

- First aid arrangements and how-to use them will be thoroughly covered in inductions and other appropriate training.

Medical Facility

The medical facility will provide:

- A waiting / reception area, consultation / examination area, treatment area, sick bay / observation area, sanitary facilities, secure storage for drugs and medical equipment and confidential storage of medical records;

A thorough inventory of essential medical equipment and supplies is crucial for delivering first aid, immediate treatment, and stabilization of significant illnesses and injuries that may occur during work activities This inventory should at least comprise a bed, stretcher, chair, table, heating and lighting facilities, a sink with a water supply, cabinets for storage, and first aid supplies, including a portable defibrillator.

- A detailed inventory of medicines and drugs shall be kept and checked regularly

- Plans for medical transport/evacuation of injured or ill Personnel including detailed specifications for a dedicated ambulance and arrangements for on-going care.

Medical Staff

The Contractor shall appoint at least one nurse with a college degree or higher

His or her roles and responsibilities are to:

- Monitor the health and well-being of all Site employees and notify any adverse trends to the HSE Manager

- Make sure the medical facility is equipped with sufficient and adequate materials, consumables, instruments, and staff to function effectively

- Ensure that the medical facilities are always kept clean and hygienic and ready to use

- Be aware of any dangerous substances in use at Site, and obtain any Material Safety Data

Sheets (MSDS) to be able to take proper care when required

- Notify the HSE Manager of any trends with illness or injuries, especially for infectious disease

- Periodically check hygiene conditions of the canteens/restaurants, including all food

- Provide all possible medical assistance and care to improve the condition of persons suffering injury or illness

- Be available to attend accidents/incidents on Site to give medical treatment as required

- Carrying out training programs for construction personnel (First aid training, etc.)

- Dispense pharmaceutical items as prescribed by the doctor and maintain records of prescription drugs

- Keep stock records of pharmaceutical/clinic items, and order replacement items to maintain minimum stock levels

- Periodically check the hygiene conditions of all camps

- Keep accurate records of all medical matters and ensure they are kept strictly ‘Medical in Confidence’ and restrict access to Authorized Persons only

- Prepare a Monthly Report on major activities and topics on medical matters and monthly statistics including trend of patients, etc , for submitting to the HSE Manager

- Provide guidance for HSE Manager on Incident Classifications

- CONTRACTOR will provide the first aid equipment as per regulation of Cicular

The CONTRACTOR will furnish a designated first aid treatment room, fully equipped with essential amenities such as a bed, stretcher, chair, table, heating, lighting, and a sink with a water supply Additionally, the room will include cabinets for storage and a complete set of first aid equipment, featuring a portable defibrillator for emergency situations.

- HCA Contractor shall sign a medical service contract with Ky Anh General Hospital therefore a 24/7 first aid service and facility is available

Address: Hung Hoa residential group, Song Tri ward, Ky Anh town, Ha Tinh province

- CONTRACTOR and its Subcontractors will provide First Aid boxes for emergency use only

- CONTRACTOR and its Subcontractors will supply enough First Aid boxes to suit the size of the workforce, and locate them in close proximity to the work areas and check

- The stock of disposable medical items will be maintained according to the number of employees and consumption

- Guidance for medical personnel is one advanced First Aid staff per 50 workers and

- CONTRACTOR will ensure that adequate number of employees is trained in First Aid First

- Aiders will be competent people, trained in First Aid at Work

First Aiders will be easily identifiable by displayed photographs that include their name, location, company, and contact number Each First Aider will wear a safety helmet featuring a self-adhesive green cross sticker on both sides The CONTRACTOR Site HSE Manager is responsible for overseeing the design of high-visibility jackets or vests for First Aiders, which will incorporate additional functions for HSE personal identification as part of the BBS safety program or recognition initiative.

A certified first aider from an accredited association can become a "Principal First Aider" by completing an approved course that leads to the First Aider at Work Certificate.

- The principal First Aider will always be available at the first aid station of each

- A CONTRACTOR of any incident / accident happening with the required information for the Site H&S Statistics, as per the incident / accident reporting procedure

- The sub-contractor’s H&S supervisor shall ensure liaison between the sub-contractor and the HCA CONTRACTOR Site HSE organization

Evaluate the risk and decide on precautions

Table 1 outlines the consequence levels by assigning numerical values to each level, providing clear definitions regarding their impacts on the environment, health and safety, production loss, and property damage In cases of uncertainty about which outcome poses a greater risk, both outcomes should be evaluated, and the one with the higher risk level should be chosen.

Where there is doubt as to which outcome would have the highest risk level, both should be considered with the highest one being selected

Negligible impact on strategic objectives Nil/negligible:

Injury, loss, service interruption, environmental/estate impact, impact on reputation impact on quality litigation or complaint

Small variance from overall strategic objective First aid treatment with full recovery

Complaint possible Local low key external interest

Minor: financial loss (up to 5K),service interruption

,environmental/estate impact, impact on reputation, impact on quality

Notable variance from overall strategic objective Medical treatment required up to 3 months to recover

Reportable under RIDDOR(Reporting of Injuries, Diseases and

A moderate financial loss ranging from $5,000 to $200,000 can lead to service interruptions exceeding one week, alongside potential environmental and estate impacts This situation may also affect the organization's reputation, drawing concern from local press and stakeholders While there is a moderate risk of losing valuable information, recovery is possible, resulting in a moderate loss of data and a low-value claim.

Significant variance from overall strategic objective Long term illness or injury (up to one year)

Reportable under RIDDOR Complaint expected/received

A major financial loss ranging from $200,000 to $3 million can occur due to service interruptions lasting over one month, which also lead to environmental and estate impacts that compromise service delivery Such disruptions significantly tarnish the organization's reputation, attract substantial media attention for over a week, and raise serious concerns among stakeholders Additionally, these issues adversely affect quality, increasing the risk of failing to meet established standards.

‘excellent’ in annual health check in one or more standards, major loss of information (recoverable) , high value claim or action by HSE anticipated, moderate risk of low value claim

Failure to meet strategic objective threatens independent functioning or stability

The potential consequences of a significant data breach include severe financial losses exceeding $3 million, reputational damage that could attract national media attention for over three days, and the risk of serious long-term or permanent loss of critical information affecting service delivery Additionally, external controls may be enforced, leading to threats of judicial review and anticipated litigation valued at over $1 million The breach could also involve high-profile exposure of confidential information, such as patient identities, and may result in the condemnation of buildings or property, causing substantial disruption to services.

Likelihood can be examined with regard to the chance that a particular outcome will happen to any of the following:

• A single person or member of the general public

• The project (more persons potentially exposed)

Table 2 – Likelihood Levels below assigns a number to the likelihood As can be seen, likelihood can be very variable In order to protect people on a Project, the Likelihood Level for

Scor e Descriptor LIKELIHOOD OF REPEAT EVENT

1 Very unlikely to occur Will only occur in exceptional circumstances

2 Unlikely to occur Unlikely to occur but the potential exists

3 Could occur Reasonable chance of occurring – has happened before on occasions

4 Likely to occur Likely to occur – strong possibility

5 Almost certain to occur The event is expected to occur in most circumstances

• Use the Risk Matrix Tool and guidance in the Risk Assessment pro forma to grade the risk

Negligib le Minor Moderate Major Catastroph ic / Fatal Consequence

A combination of Tables 1 and 2 can be used to evaluate the risk by determining the overall risk level of a particular outcome eventuating

The matrix (Table 3 - Risk Level Matrix) below is shown in the conventional format of

Consequence on the horizontal axis increasing to the right and Likelihood on the vertical axis increasing with height

Escalation of Risk is determined by risk score

Risk level Risk score Escalation level

Extreme Red 15- 25 Board of Directors

High Orange 9-12 Management committee (reporting to Board) Moderate Yellow 6-8 Directorate/Department

Department but monitored at Directorate level

• For an initial risk assessment, the Risk Level is known as the Risk Factor Number

• For a residual risk assessment, the Risk Level is known as the Residual Risk Number

• In both cases, the risk level dictates the response and timing of risk controls required

The management of risks identified through the risk assessment process will be determined by the risk rating

The amount of effort/resources that are to be committed to an identified risk is determined by the risk score The Contractor has a scheme of escalation

• Risks scored 1-5: are considered low risk (L) and therefore risks are accepted (tolerated) by the Contractor No more countermeasures are required.

Ngày đăng: 15/05/2022, 15:05