Bạn đang học MBA nước ngoài, đang vất vả hoàn thiện final môn Thẩm định dự án đầu tư bằng tiếng anh, đang không biết viết như thế nào để hoàn thành một trong những môn khó nhất về tài chính, mà lại viết bằng tiếng anh nữa chứ. Và đương nhiên cũng muốn điểm A. Kèm theo đây là bài final môn Project Management đạt điểm A của tôi. Chúc quý vị nhanh hoàn thành chương trình học một cách tuyệt vời.
Trang 1COURSE TITLE:
PROJECT MANAGEMENT
Student:
ID:
Lecturer:
COURSE CODE
MGT 605
Trang 2PROJECT MANAGEMENT
PROJECT OF OPENING LIBRARY FOR HIEP PHUOC CORPORATION
Submitted by
– August04th, 2016
Trang 3Table of Contents
PROJECT OF OPENING LIBRARY 2
FOR HIEP PHUOC CORPORATION 2
Executive Summary 5
Project Overview 5
The requirements of the project 6
Completion time: 6
Cost: 6
Scope of the project 7
Objectives: 7
Key to Success 7
Project Life-cycle 7
The project's resources 8
Finance Committee: Consists of 2 people 9
Human Resource Management Unit includes 3 people 9
Management and procurement of equipment: 9
Environmental Committee: composed of 3 people 10
Committee collect resources, documentation includes 3 people 10
Committee design and layout library: 2 people (1 architect, 1 artist) 10
Committee inspection, supervision and promotion of project completion: 4 people 10
Committee evaluation of the project results at the end of the project includes 3 people 10
Time management 10
Duration of the project 10
(Work Breakdown Structure) 11
Gantt Chart 14
To ensure the project schedule, daily, the chief function to check and report progress made by mail to the project manager If members do not have time in the project schedule will be reprimanded, and the chief function must allocate overtime to ensure progress in accordance with the approved timeline 14
The cost of the project 14
Project Quality Management 15
Trang 4Project Risk Management 17
Completion and Delivery Projects 18
Acceptance of work 18
Conclusion and Recommendation 18
References 18
Trang 5Executive Summary
Hiep Phuoc Joint Stock Company is one of the famous companies in HCMC, Viet Nam on the real estate business and industrial parks
Chi Minh City, Viet Nam
- Main business sectors:
Investment in construction and trading infrastructure of industrial parks and residential, investment consultants, land lease, land leveling
This paper outlines the process to set up the project, the resources to implement, the risk management include:
Project Overview
The requirements of the project
The project's resources
Duration of the project
The cost of the project
Project Quality Management
Project Risk Management
Completion and delivery projects
Conclusion and recommendation
Project Overview
In the future, Hiep Phuoc Industrial Zone will be expanding; staff will increase from 10,000 today to more than 20,000 in the next 5 years Along with the increased demand is demand for enhancing knowledge, self-improving more and more So Hiep Phuoc Industrial Zone staff will want to have a quiet and spacious place having abundant, diverse books and materials for research and study Therefore, the investment, opening a library here is desirable, to meet the needs of people
Project Name: Project of establishing library in Hiep Phuoc Industrial Zone
Place:
The library is located on the 5th floor of the building B, consists of 5 rooms:
Trang 6Self-study room.
Reading room, newspapers and magazines
Foreign Language Room
Thesis Room
Room rare and valuable documents
Project management group chose this place because it has advantages and benefits as follows: Library aloft will be cool, quiet
If the employees go to the library, there will be plenty of time to learn more because the full equipment and ideas hesitate to go up and down takes time
Zone B in the direction of the southeast so library will not be hot in the summer and the winter winds, creating conditions to ensure the employees' health
The requirements of the project
Completion time:
Within 3 months from T8 / 2016 - T11 / 2016
Cost:
The total allocated fund is 300 million VND
The whole area of the library will be divided into 5 main rooms:
Self-study room
Self-study room accommodate 300 people
Statistics desk long ranges, each side ranked 15 seats so make the most of the table space area
Reading room, newspapers and magazines
The room has a capacity of 150 people
The area order to the shelves of books, newspapers and magazines accounted for a third of the room, left furniture Statistics
Librarian's desk order to a television monitoring, 1 computer
In a room with photo-spot service
Foreign Language Room
There are 6 computers are connected to the internet
There are 4 TVs order to employees movie subtitles in foreign languages
There are 4 languages bookshelf
Trang 7And many video tapes and CD racks serve for learning
Thesis Room
Storing at least 500 scientific research projects, the research work of scientists
There is also the topic of the master's, Ph.D., professor had successfully defended in the country as well as abroad
There are 2 computers for employees quickly find the document you need
Room rare and valuable documents
Storage of precious books were lost or no longer reproduce
There are 2 computers to lookup
Scope of the project
The project was carried out in the premises of the Hiep Phuoc Industrial Park As a sub-project, a component of the overall features of the Hiep Phuoc Industrial Park
Objectives:
Short-term goal: Meeting the needs of learning, reading and studying of cadres and workers Long-term goals: To contribute to improve the quality of labor Since then, the reputation of the industrial park has gradually been confirmed
Key to Success
Needs of large users
Under the sponsored and consent from the parent company
Facilities available
Financial capability and operator of the project is very strong
Project Life-cycle
The project has four phases:
Definition
After a long time studying the needs of the project members, plus synthetic feedback through events, meetings in Hiep Phuoc Industrial Zone Identifying the need for setting up the library is huge Industrial Park Management Board found that the establishment of this project is very urgent
Planning
Project Director is the person assigned to carry out the whole of the work to implement the project, including:
Effective financial appraisal
Trang 8Appraisal of customer segments
Appraisal ability to meet terms of personnel
Appraisal of the financial capacity of the owner
Appraisal of the compatibility than stipulated by law
Appraisal of project risks and risk mitigation plans
Appraisal of the current resources of the company
Then the company Hiep Phuoc CEO approval
Execution
After the project is approved, the Project Manager will implement
Establishment of project personnel
Meetings, assign tasks
Leasing and design, decoration
Operating permit
Contracts for electricity, water, telephone, internet, cable television, garbage
HR Recruitment
Develop operating procedures
Delivery
After project completion, the Project Manager will be handed over to the CEO, the records handed over include:
Handing over a business license, the company seal and legal records
Handing over the lease premises, premises design documents, detailed tools and supplies The contract on electricity, water, telephone
Handing over personnel decisions
Handover of the segregation of duties and job description
Handing costs
Handing over the minutes of the meeting, the problems, the difficulties, the proposed requirements of the stakeholders in the process of establishment
The project's resources
Project sponsor is CEO of Hiep Phuoc
Trang 9Project chief administrative director
After having launched the idea, chief project committees set up to implement the project after each part of the work 8 committees include:
Financial Management committee
Human Resources Management Board
Committee to collect resources, materials
Committee design and layout library
Environmental Committee
Management and equipment procurement
Committee inspection, supervision and project promotion
Committee evaluation of project results
Each Committee has a Chairman, responsible for all aspects of the project to the head and to the law
As the project leader assigned to specific departments, project teams must be concretized in writing, signed and stamped and certified by the parties
After having established the Project Board, Head of Project chief summoned to retrieve comments and reach a consensus After that, each project committee to get together to understand and thorough work to be done ahead of each individual is:
Finance Committee: Consists of 2 people
Perform the financial management of invoices, made money in a reasonable manner Remember the full amount of equipment and the amount spent Monthly reporting and accounting for the end of the project
Human Resource Management Unit includes 3 people
Responsible for decorative lighting hire professional installation, mounting racks, shelves, installing computers, cameras, air conditioners, TVs Hire a professional bearing, carrying furniture from 1st to 5th floor
Management and procurement of equipment:
Consists of 4 people:
Responsible for the procurement of equipment to ensure good quality, transported to a safe place, not for the loss, and to have full invoices Buy the request, do not buy too much or too little
Trang 10Environmental Committee: composed of 3 people
To perform the work support during the implementation of projects such as electricity, drinking water, eating places for workers Ensuring clean cleanup during and after completion of the project In addition, the environmental committee should also plan for fire protection
Committee collect resources, documentation includes 3 people
While completing the formality library, finding resources is very important Three people have split away to collect information, find cheap and quality source, can solicit donations from employees and leaders Find resources on the internet because the library serves not only the employees but also of conventional electronic books Then report back to the project leader, if there is difficulty in finding the assistance proposed by the relationship of the project leader and the members of the committees and other groups
Committee design and layout library: 2 people (1 architect, 1 artist)
The architect responsible for designing each suitable and convenient for employees and librarians
From the design of architects, interior painter so logical, natural landscape without enforcement practitioners
Committee inspection, supervision and promotion of project completion: 4 people
Turns to regularly monitor and supervise the implementation of the project in order to avoid errors, forgotten Urge and encourage you to work energetically, hard, rational payoff
Committee evaluation of the project results at the end of the project includes 3 people
After completion of the project, the project manager and team leader of the evaluation committee carried out the result Meeting the entire project team and learn from experience: praise, criticism, reward and punishment Then hand over the project to the general director of Hiep Phuoc
Time management
Duration of the project
Split up the work table (WBS)
Trang 11Total time to allow completion of the work is: 90 days
Expected completion time of work is: 72 days Standby time is 18 days
Structural separation work
(Work Breakdown Structure)
and equipment procurement
collect resources,
2.5 Tables, chairs, shelves,
bookcases
2.7 artificial flowers
documents
collect resources, materials
Magazines old, new
design and layout library
Trang 124.2 Conditioning Installation
4.3 Installation of camera
4.5 Installation of Computer
data into the warehouse
collect resources, materials
document
collect resources, materials
evaluation of project results
design and layout library
room
Committee
Committee
bookshelves
Environmental Committee
Trang 1310 Ratings on the price of
books, cabinets
inspection, supervision and
on
Committee
11.4 Set the water softener at
the top of the corridor
and equipment procurement 12.1 Wiping tables, chairs
12.2 Tidy up excess material
Trang 14Gantt Chart
The cause of project planning, project kick-off, Do Project Charter, Scope Due Statemen
Appraisal of financial performance, appraise current resources of the company, Review & Approve
Establishment of project personnel
Cleaning Purchase equipment Find resources and documents Installation of equipment Transfer documents and data into the warehouse
Data classification, document
Check equipment
Decore Moved furniture into the room Ratings on the price of books, cabinets Transfer office equipment on
Cleaning Handing over project
1-May 20-Jun 9-Aug 28-Sep
Gantt Chart
To ensure the project schedule, daily, the chief function to check and report progress made by mail to the project manager If members do not have time in the project schedule will be reprimanded, and the chief function must allocate overtime to ensure progress in accordance with the approved timeline
The cost of the project
The following is a calculation of the cost has been discussed and agreed by the project team This calculation tables are approved, Overhauled and signed by both parties, together with the original
is a photo
Trang 15number
Expenses Unit cost estimates (million VND)
1 Salary costs for project leader and
members
41
Reading room, newspapers and
magazines
26
The total estimated cost and funds 300
To control and ensure the approved costs The chief function absolute compliance:
The quota is allocated
Type, origin, quantity, quality approved
Save costs and combat waste, loss
Effective management of work by members of the board
Daily Report for the project director of the costs incurred
Project Quality Management
To be able to manage the quality of the project well, we need to make good management criteria: time to complete work; Explicitly assigning functions to each committee, to each employee; standardization of equipment investment; clarity and transparency in the allocation and management of the budget As follows:
Trang 16Timeline Absolute compliance timetables
according Gantt Chart
Project Manager Clear division of tasks to each
board functions and staff
Every employee, every committee assigned functions clearly written KPIs
Head of function, Project Manager
Standardization of equipment
investment
The equipment investments are purchased from companies certified by "Vietnam high quality goods", with clearly a VAT invoice and a minimum warranty
of 12 months
Head of function, Project Manager
Clarity and transparency in
management of the budget
The budget will be allocated in accordance with the approved budget table Daily periodic finance chief will report the situation project manager of the project budget
Head of financial, Project Manager
meetings, trainings for the staff, the board functions shared, unified way of working, to help complete the project on time set
Head of function, Project Manager
Project Director is the direct supervisor of the quality standards based on the report and take direct responsibility for the company's CEO Hiep Phuoc For example, time management will be based on the project Gantt chart