Fundamentals of project management tài liệu, giáo án, bài giảng , luận văn, luận án, đồ án, bài tập lớn về tất cả các lĩ...
Trang 1PART III: THE PROJECT LIFE-CYCLE
Trang 2The Project Life-Cycle
Trang 3 Awareness of the need for change (situation, context) and
recognition by stakeholders that only a project can bring about the desired change
Consideration of project options
Collection of basic information to perform a preliminary project feasibility assessment and determine possible project costs
and outcomes (positive and negative)
Preparation of a formal project proposal for consideration by the project sponsors
Undertake a detailed project feasibility study if required
Decide whether project should be pursued, put on-hold for a future time or rejected
Make contracts with key stakeholders, issue project charter
and assign resources for the project
Move the project into the (detailed) planning phase
Overview of Project Initiation
Trang 4Key Project Initiation Deliverables & Inputs
Project (Business) Case
Project Pre-Feasibility
Project Feasibility Report
Formal Project Proposal
Project Scope & Key Deliverables Project Requirements & Specifications
Project Resources Project Stakeholders Project Risks Project Assumptions & Constraints Project Policies, Processes, Systems etc
Trang 5Limitations of the Project Initiation Phase
In the project initiation phase, a typical and serious
limitation is the lack of available of “quality
informa-tion” which exists about the project – especially for
complex projects and projects of a kind which have not
been attempted before
At initiation a project’s feasibility, outcomes, scope,
requirements and specifications, cost, time and risks,
stakeholders, resource needs etc are often not known
with a high degree of precision with the result that the
project may take longer, cost more and generally be
more diffcult to do than first thought when it was
con-sidered and accepted
Trang 6The Initiation Phase of a Project
(Awareness of a Need)
All projects are conceived and undertaken in ponse to some need (problem, opportunity) – internal, external, legal and other
res-The need could be commercial in nature – for example, an automobile company seeks to bring out
a new SUV as it perceives a large market of tomers who would be willing to purchase it, or a software company is asked by one of its major clients to develop an accounting software for its organization On the other hand, the need could be non-commercial – for example, a municipal office wants to introduce a modern sewage system to re-duce health hazards or the federal government wants to construct a highway linking major urban localities An NGO may initiate a project to provide basic health facilities needed by a village
Trang 7cus-The Initiation Phase of a Project
(Project Outcomes)
All projects have outcomes that are realized quent to (and sometimes during) their completion Some outcomes can be easy to quantify while others may not
subse-Project outcomes may be positive and/or negative and multifaceted For example, the (envisaged) out-comes or benefits of a provincial road construction project connecting two urban localities could be that transport between these localities becomes easier, quicker and cheaper and leads to a increase in the volume of trade and investment and economic pros-perity A negative outcome could be the project’s adverse environmental impact (chopping trees, dis-rupting ecological systems) and its social conse-quences for the communities which lie on both sides
of the road
Trang 8The Initiation Phase of a Project
(Project Strategic Dimension)
The projects which any organization in the cial and public-sector undertakes must have a “stra-tegic fit” – it must be consistent with the organiza-tion’s mission, goals and objectives so that it can
commer-“add value” to it
In practice, methods and models have been devised
to assess a project’s strategic fit and its ness for selection in a project portfolio Commercial organizations typically look at factors such as a pro-ject’s profitability (measured in terms of its Return
appropriate-on Investment), risk, technical complexity and other criteria In the public sector, the profit motive is not
an overriding consideration unlike other factors such
as development plans, targets and priorities against which projects are undertaken
Trang 9The Initiation Phase of a Project
(Project Goal, Objectives, Cost & Time)
Every project has one goal which is the ultimate tination of all project initiation, planning, execution and other activities
des-In addition to its goal, projects can have multiple objectives For example, when an NGO undertakes a project to improve secondary education facilities for students in a district by constructing a new school building, some of the project objectives may include prioritizing local resource suppliers and recruiting and selecting teachers preferably from the commu-nity
All projects necessarily incur cost and require time (per definition) Despite the existence of several estimation methods, acurate initial assessment of a project’s cost and time need can be challenging
Trang 10The Initiation Phase of a Project
(Project Scope & Key Deliverables)
The goal of a project determines its scope, i.e., the work which has been performed in order for the project to be considered complete by its owner
Scope can be a tricky issue which may cause cations if it not carefully defined In projects, any-thing not included in the scope definition is consi-dered outside the project boundary or purview In determining a project’s scope, numerous require-ments and specifications (possibly subject to change over the course of the project) may be inputs
compli-Key deliverables of a project are the final composite deliverable (e.g an airport) and its constituting sub-deliverables (e.g airport buildings, runways, parking lots, shopping area)
Trang 11The Initiation Phase of a Project
(Project Requirements & Specifications)
Requirements and specifications are key elements of any project The success or failure of the project is assessed largely in terms of the extent to which it satisfies its requirements and specifications
Requirements and specifications imply that a
pro-ject’s deliverables must exhibit certain defined
capa-bilities in terms of appearance, function, mance etc For example, the owners of a planned shopping mall may require that it is designed as a three-storied glass structure, is “aesthetically
perfor-pleasing”, can accommodate up to 120 shops and 25,000 visitors daily, in addition to conforming to all city building and environmental regulations The owners can also specify the dimensions of the mall and its constituting spaces, the interior décor and quality of the building materials
Trang 12The Initiation Phase of a Project
(Project Resources)
No project can be attempted unless the requisite resources have been made available by the project sponsor and client
Resource consumption ultimately results in a cial cost but even having abundant funds does not mean that the resources specifically needed for the project in question are available For example, a financially robust and rapidly expanding software company may have come up with several good ideas for advanced software programmes catering to
finan-different market segments The company’s ability to undertake the projects concurrently would be deter-mined in large measure by its ability to mobilize the needed number of programmers inhouse or through external channels In such a case even a highly lucra-tive project may not be undertaken
Trang 13The Initiation Phase of a Project
(Project Stakeholders)
All projects have stakeholders It is not possible to envision any project without their direct and indirect involvement
Project Stakeholders may range from very few in number to many millions Their interest in and attitude and behaviour towards the project in question may also vary considerably
When initiating any project, it is essential that the key stakeholders are identified and their stake in the project documented
Stakeholders can be a great source of help – and also pose a formidable obstacle – for a project and any new project must keep this in mind
Trang 14The Initiation Phase of a Project
(Project Risks)
Risks are a defining element of projects Complex projects in particular harbor numerous and diverse risks and if these risks turn into events, they may endanger a project
When initiating any project it is essential to take an initial analysis of the risks inherent to the project, seeking in particular to identify those risks that may have a bearing on the project in the course
under-of its life-cycle If a project similar in nature was undertaken previously, then lessons learned from risk management on that project may be used for the new project
Trang 15The Initiation Phase of a Project
(Project Assumptions and Constraints)
Projects are usually undertaken in very complex internal and external environments and are subject
to a multitude of factors and influences
Assumptions may constitute the basis for the quent planning and execution of the project For example, an assumption could be that the cost of project inputs will not increase over the project life-cycle, that project requirements will not signifi-cantly change and that all key stakeholders will support the project
subse-Constraints are factors which have a limiting effect
on how the project is undertaken These include for example constraints with regard to project policies, recruitment and selection, reporting, financial
outlays, completion of activities etc
Trang 16The Initiation Phase of a Project
(Project Policies, Processes, Systems etc.)
Projects are not undertaken in a vacuum but in an environment which is characterized by diverse policies, processes, systems, infrastructure and so forth Project success is conditioned in part by the maturity of these “environmental factors”
When considering a new project careful thought must, therefore, be given to whether the project can
be supported to the extent it requires through the organization’s existing assets
Trang 17Project Pre-Feasibility Studies
A Pre-Feasibility Study is done with the purpose of
determining whether or not it is worthwhile to
proceed with a detailed Feasibility Study of a project
Pre-Feasibility Studies have ”exploratory” framework
character but sometimes they evolve into full-fledged
Feasibility Studies
Pre-Feasibility Reports are usually of a (comparatively)
short length and duration than Feasibility Reports
which analyze a project in great detail
Trang 18Example of a Project Pre-Feasibility Study
The Small and Medium Enterprise Development Authority has 118 pre-feasibility reports relating to projects
in Pakistan which are freely loadable from its website
down-The reports span following areas:
Agriculture, carpets, ceramics, chemicals, construction, dairy, education, electronics, entertain-ment, fisheries, food, furniture, gems & jewelery, IT, leather, light engineering, livestock, marbel &
granite, minerals, paper, petroleum, pharmaceuticals, plastic, services, textiles, tourism and travel, and trading
Trang 19Project Feasibility Studies
A Feasibility Study is done with the purpose of
deter-mining whether or not it a project should be
under-taken A formal study is typically performed on large,
complex projects
Feasibility Studies can be regarded as projects in their
own right and are usually undertaken by experienced
consultants
Feasibility studies can be very detailed and explicit,
spanning volumes in some cases They look at
alterna-tive solutions and come up with the best possible one
Trang 20Project Feasibility Studies
A Feasibility Study examines at diverse issues, including
the project’s technical feasibility, its financial viability, its social desirability and legal acceptability On infrastruc-
ture projects a Feasibility Study may assess the project’s ecological consequences and impact on archeological
and cultural assets
The Feasibility Report can contain a lot of useful
infor-mation for the project planning phase.
Feasibility Reports may sometimes generate erroneous
results which can cause serious problems for projects
Trang 21Project Feasibility Case Studies
Karnataka State Highways Improvement Project
Hotel Development in Isle of
Wight County, VA, USA
Trang 22Project Preliminary Scope Statement
The Project Preliminary Scope
Statement provides an indication
of the project deliverables and
serves as a guide for developing
the detailed project scope
statement and for planning the
• Project Acceptance Criteria
Trang 23Project Preliminary Scope Statement
(Case Study)
SharePoint Portal Development
Trang 24Project Charter
According to the Project Management Institute, the
Project Charter is the document that “formally authori-zes
the project”
The Project Charter provides the Project Manager and
Project Team with the authority to use resources for the
purpose of undertaking the project
The Project Charter is usually short and is issued by the
Project Sponsor or a senior official outside the level of the
project organization
Some Project Charters contain brief general information
about the project; others may contain specific details
Trang 25Project Charter
Information contained in – or referred to in other project
documents – the Project Charter may span the following:
– Project Background– Purpose for undertaking the project– Project Justification
– Requirements– Stakeholder expectations from the project– Assumptions and Constraints
– Project Organization – Stakeholder Roles and Responsibilities– Schedule and milestones
– Indication of budget– Supporting infrastructure
Trang 26Project Charter Case Studies
California Child Support Automation System
CMS