It is calculated simply by the amount of machines available and hours per day determined to work to be realistic ,one has to determine the efficiency level of the operators and incorpor
Trang 1© SOFT Student Handouts,
By, Sunil Talekar, Faculty, SOFT-Pune
SunilTalekar
Trang 2Following part are involve while Garment
APPAREL ENGINEERING CONCEPTS
Trang 3 METHOD STUDY
The in depth monitoring and analysis of the way an operator performs its task is called method study.
Three to four method study will guide you to select the right method
to perform any operation and the we can proceed for next operation as well to find out the causes of delay in the process of stitching.
Once the method study is done, one looks for better ways to save time and less effort by the operator This could be done by improving work motions / provide work aids like gauges , folders , attachments , trolleys , movers, tracks or machine automation.
APPAREL ENGINEERING CONCEPTS
Trang 4 TIM E STUDY
The recording of time of every motion conducted by the operator is termed as time study Once the time is recorded, allowances for fatigue, machine delays , personal breaks and various times are integrated into the pure time to derive real time This time is termed as SAM ( Standard Allowed M inutes) of SM V ( Standard M inute Value ).
Time study will guide us to calculate the standard minutes for any specific operation and it is the average for one cycle of an operation that
we would measure over a typical day if we had;
1 A skilled operators
2 Plenty of works
3 Workplace and machinery
4 Output with correct level of quality
5 Less weakness
6 Expected delays due to process
Exercise: sewing machine threading exercise, to calculate SM in SOFT
APPAREL ENGINEERING CONCEPTS
Trang 5 IDLE TIM E
During the course of production, it is observed that operators are idle and wait for production buildup to make them go into motion, this idle time is loss of time and production
CREATIVE PRODUCTION PLANNING
Creative production planning is use of various techniques to assure that idle time is less or eliminated more production in less time is key to success for any manufacturing plant
APPAREL ENGIEERING CONCEPTS
Trang 6 FACTORY PRODUCTION CAPACITY
Factory production capacity is derived from the resources available at the manufacturing plant It is calculated simply by the amount of machines available and hours per day determined to work
to be realistic ,one has to determine the efficiency level of the operators and incorporate the percentage to derive actual capacity.
Example : if a factory has 100 machines and working hours are 8 hours per day and 26 days per month the efficiency level of operators is observed to be at 80% the production capacity available time per month would be calculated as below :
Available monthly production time capacity :
100 machines x 480 M ins x 80 / 100 = 38400 M ins / day.
38400 M ins x 26 days = 998400 M ins /month or 16640 hours/month.
APPAREL ENGINEERING CONCEPTS
Trang 7 SPECIAL MACHINE PRODUCTION CAPACITY
Once planning production , it has to be known that if any special operation is required within the garment which require special machine or machines if so , the output capacity for those garments have to based upon special machine production the management can then decide if those machines be worked overtime or if required
to meet shipment date , additional machines be purchased
To calculate special machine capacity per month , the available machines are 10 , work hours /day are 8 hours , efficiency level is 80% and working days per month is 26 days
Special production capacity in time / month =
10 machines x 480 M ins x 80 / 100 = 3840 M ins / day
3840 M ins x 26 days = 99840 M ins / month or 1664 hours /month.
APPAREL ENGINEERING CONCEPTS
Trang 9 AVAILABLE CAPACITY :
Difference between potential capacity and committed capacity for a certain time period
REQUIRED CAPACITY :
Sam or SAH necessary to produce a specified volume
in a certain time period
EXCESS CAPACITY :
Difference between potential capacity and required capacity
PRODUCTION CAPACITY
Trang 10Lets say ABC garments company has 20 operators who work 8 hours a day The plant has 90% efficiency level Working shift is 8 hours a day in which 1 hour is mainly for lunch and tea time break.
So their potential capacity for next 10 days will be,
20 machines x 7 hours /day = 140 hours/day x 90% efficiency = 126 potential
production hours /day.
Potential capacity for 10 days = 10 days x 126 hours = 1260 hours potential capacity.
EXERCISE TO UNDERSTAND
RELATIONSHIP OF CAPACITY TERMS.
Trang 11EXERCISE TO UNDERSTAND
RELATIONSHIP OF CAPACITY TERMS.
A Sale brings in order for 10000 units of style “ax” that needs to be delivered in
10 days the plant already has a committed capacity of 600 hours for the 10 days period It was established that style “ a” has a production time of 5 SAM
So their required capacity for 10000 units will be;
5 SAM /unit x 10000 units = 50,000 SAM or 833 SAH to complete the order Capacity required = 833 hours
What is available capacity in the plant currently ?
Ans Available capacity = potential capacity – committed
capacity
Available capacity = 1260 hours – 600 hours = 660 hours available
Trang 12Lets say ABC garments company has 10 operators who work 8 hours a day The plant has 90% efficiency level A customer brings in order for 6000 units of style “a” that needs to be delivered in 10 days the plant already has a committed capacity of 300 hours for the 10 days period.
Working shift is 8 hours a day in which 1 hour is mainly for lunch and tea time break
It was established that style “ a” has a production time
of 5 SAM The order of 6000 units require 30,000 SAM ( 500 hours ) What factors should be considered in deciding whether to accept the order or refuse?
EXERCISE TO UNDERSTAND
RELATIONSHIP OF CAPACITY TERMS.
Trang 13What is the potential capacity of united garments company for the 10 working days ?
Ans 10 machines x 7 hours /day = 70 hours/day x 90% efficiency = 63 potential
production hours /day.
Potential capacity for 10 days = 10 days x 63 hours = 630 hours potential capacity.
What is required capacity for the 6000 unit order ?
Ans 5 SAM /unit x 6000 units = 30,000 SAM or 500 SAH to complete the order
Capacity required = 500 hours.
What is available capacity in the plant currently ?
Ans Available capacity = potential capacity – committed capacity
Available capacity = 630 hours – 300 hours = 330 hours available
Is available capacity adequate to accept the order ?
Ans 330 hours of available capacity – 500 hours of required capacity = -170 hours
Capacity is not sufficient to accept order
Trang 14 Require more time from buyer to accommodate the 170
hours
Work overtime to cover the 170 hours
Increase more machines and operators
Find way to increase efficiency level to 100 %
Use creative production technique to increase
productivity
Try to eliminate idle time within production to decrease
throughput time
Assess the performance of individual operators.
WHAT ADJUSTMENT HAS TO BE MADE TO
ACCOMMODATE THE ORDER IN HAND ?
Trang 15 Estimate the rate or time for completion of each
operation.
Determine the required capacity for an order or style.
Determine the production start dates and completion
dates for orders.
Plan the daily volume that should have been completed.
Determine the backup inventory needed to support the
work flow.
Determine how many operaqtors and machines should be
performing on each operation.
Schedule specialized equipment
M onitor daily production delays.
PRODUCTION STANDARDS ARE USED IN
PRODUCTION PLANNING TO DO THE FOLLOWING :
Trang 16QUESTION ONE.
Plant capacity is :
A projection of the total hours available for production in a given time period.
N umber of garments a plant can produce in a certain time period
N umber of machines available to meet the capacity of orders
Committed capacity is :
The orders which P.O Still not received
Orders waiting for confirmation
Total hours previously allocated for production in certain time
Available capacity is :
The volume which can be still produced in a plant
The styles which orders can be taken and ship on time
The difference between plant capacity and committed capacity for a certain time period
If a garment has Sam = 6 min the plant capacity is 4800 min/day efficiency of plant at 100% how many days will it take to produce 12000 garments ? how many machines does the plant own ?
Trang 17QUESTION TWO
What will be plant potential capacity ? If the plant has:
125 machines
6 working hours / day
5 working days / week
Efficiency level 80%
Answer : Plant capacity / day: _
Plant capacity / week:
QUESTION THREE.
What will be the required order capacity ? If the order details are :
Order quantity : 30,000 garments
Sam / garment = 15 M ins
Answer : Required capacity total hours :
Days required to complete order: _
QUIZ
Trang 18Product description :
Fleece top L/S with neck band / cuff & w Band all sewn on over lock machines
Fill in blanks 8 hours work time /day 26days/month 100% efficiency.
Op no Operation Sam Prod/day M achine type M achine qty
B-Total machines required to produce 320 garments/day? _
C-How many days required to produce 2880 garments? _
D- how many machines required to produce 24,000 in 20 days? QUESTION FOUR GARMENT BREAKDOWN SHEET
Trang 19Equipment requirement : O/L = 19
Production output target = 1000 units per day Indirect labor: Operation SAM Prod/day M anpower Req
1-Turn cuff(2) 0.50 960 1
2-Turn Col 0.37 1297 1
3-Turn W Band 0 40 1200 1
Productivity increase: 8.567 – 7.290 = 1.277 / 8.567 = 15 %
Separating indirect labor resulted into :
15% productivity increase 1000+150 = 1150 output
19 machines-16 machines = 3 less machines
Indirect labor cost ½ the operator cost saved.
3 machines less inline less space.
3 less machine machine cost saved
Trang 20Quiz ( Answer Sheet )
Question one.
Plant capacity is :
Projection of the total hours available for production in a given time period.
Number of garments a plant can produce in a certain time period
Number of machines available to meet the capacity of orders
Committed capacity is :
The orders which P.O Still not received
Orders waiting for confirmation
Total hours previously allocated for production in certain time
Available capacity is :
The volume which can be still produced in a plant
The styles which orders can be taken and ship on time
The difference between plant capacity and committed capacity for a certain time period
If a garment has Sam = 6 min the plant capacity is 4800 min/day efficiency of plant at 100% how many days will it take to produce 12000 garments ? how many machines does the plant own ?
10 days 10 machines
2.5 days 20 machines
5 days 40 machines
15 days 10 machines
Trang 21 QUESTION TWO
WHAT WILL BE PLAN T POTEN TIAL CAPACITY IN SAH’S ? IF THE PLAN T HAS:
125 M ACHIN ES
6 WORKIN G HOURS / DAY
5 WORKIN G DAYS / WEEK
EFFICIEN CY LEVEL 80%
AN SWER : PLAN T CAPACITY / DAY:_125 X 6HR X80%= 600 HRS
PLAN T CAPACITY / WEEK: 600 HRS X 5 = 3000 HRS
QUESTION THREE.
WHAT WILL BE THE REQUIRED ORDER CAPACITY ? IF THE ORDER DETAILS ARE
ORDER QUAN TITY : 30,000 GARM EN TS
SAM / GARM EN T = 15 M IN S
AN SWER : REQUIRED CAPACITY TOTAL H OURS : 30,000 X 15 SAM /PC / 60 = 7500 H RS
DAYS REQUIRED TO COM PLETE ORDER: 7500 H RS
- = 12.5 DAYS
600 H RS/DAY
Trang 222 Close/set n.Band 4.50 106 O/L 3
3 Set sleeve 3.00 160 O/L 2
4 Close side 1.50 320 O/L 1
5 Close/set cuff 6.00 80 O/L 4
6 Close/set w.Band 3.00 160 O/L 2
Answer:
A- Total Sam / garment : 16 Sam
B- Total machines required to produce 320 garments/day ? 14 machines
C- How many days required to produce 2880 garments ? 2880 / 320pcs/day=
9 days
D-How many machines required to produce 24,000 in 20 days ? ?
24,000 / 20 days = 1200 units Req./day 1200 units x 16 Sam
= 19200 Sam/ 480mins= 40 machine
Trang 23THANK YOU