The purpose of this method is to describe the methodology involved in construction work for tMETHOD STATEMENT FOR CONCRETE REPAIRING WORK and to detail out the steps to be taken in order to meet the technical requirements of VP1 BOT Thermal Power Plan
Trang 1
Project Title Van Phong 1 BOT Thermal Power Plant Project
Document Title METHOD STATEMENT FOR CONCRETE
REPAIRING WORK
Document Type For Approval
Document No VP1-0-L4-C-GEN-10025 Returned Status NA Prepared by L4
CRS No VP1-0-L4-C-GEN-10025-A-CRS CRS Issued Date 13/05/2020 Engineer Construction
No Section/
Page
Date
Status O/C * Remarks
1 3 Supplement item "Classification of the concrete
defects and its reason" so that can propose a proper repair method (Voids, Honeycomb, Scaling, Crack, Cold joint, Damaged)
2 3 Before stepping the repair procedure for each
defect, please provide summary table as below
3 4 It needs to be assessed if there is any other
underlying damage before the repair methods described in this document can be applied
Lot4 will proposal method case by case specifically and addition in revision B
Trang 2
Page 2 of 3
8 5 Not agreed since consider the material strength in
case air void is serious
Lot4 change material as revision B 13/05/2020 O
9 5 Cement slurry will make crack due to strong
shrinkage, recommend to use Sika Refit 2000 or cement mortar with Sika latex
Lot4 will use Sika Refit 2000 or GPS mota 16 13/05/2020 O
10 5 Specify maximum depth of chipping for which this
treatment can be applied
Maximum depth of chipping for this treatment is 20mm
11 6 Specify maximum depth of chipping for which this
treatment can be applied What will be done if the reinforcement bars are reached/exposed?
Maximum depth of chipping for this treatment is 50mm
12 6 Before apply Monotop R, recommend to use Monotop
610 as primer layer
13 6 Before any remedial measure the cause of the
crack needs to be assessed
14 7 Missing method to repair crack for the floor for
example in building floor when through crack
Base on assessed actual reason and width of crack Lot4 will propose method for case by case specification
15 8 Water leak test is needed after treatment Please
add
16 11 Supplement repair method for Scaling concrete,
Cold joint and Damaged
17 11 It needs to be checked if the reinforcement bars
have moved so that they might be closer to the repaired surface than the prescribed cover
Unsuitable placement of reinforcement might require more extensive repair including complete removal and reconstruction
Lot4 noted and addition in revision B 13/05/2020 O
Trang 3
Additional Notes (if any)
* O - Open, C – Closed
Trang 4
METHOD STATEMENT FOR CONCRETE REPAIRING WORK
EPC
Doosan Heavy Industries and Construction
EPC DOCUMENT No
Contractor to revise the correction and resubmit
Revise the correction and resubmit before proceeding
Information acknowledged with no comment
Information acknowledged with comments Note: Approval or comment does not relieve the Contractor of
Trang 8B
Trang 9Revise material according
to item 5.1; 5.2
Trang 10B
Trang 14B
Trang 16B