METHOD STATEMENT FOR PERMANENT PILLING WORK ON SHORE

53 11 0

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Tiêu đề Method Statement For Permanent Pilling Work On Shore
Trường học Van Phong 1 Bot Thermal Power Plant Project
Thể loại For Approval
Năm xuất bản 2020
Định dạng
Số trang 53
Dung lượng 12,34 MB

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Nội dung

The purpose of this Method Statement is to describe the methodology for structural work of PILLING WORK (Preboring PHC Pile) and to details out the steps to be taken in meeting the technical requirements of Van Phong 1 thermal power plant project.

Trang 1

Page 1 of 5

Project Title Van Phong 1 BOT Thermal Power Plant Project

Document Title METHOD STATEMENT FOR PERMANENT PILLING

No Section/

Page

Date

Status O/C * Remarks

1 4 h Approved MS xxx? for test pile to be listed MS of test pile is added 02/06/2020 O

2 5 Considering the piling procedure is a common and

single activity, Lot-4 is requested to share the work plan for each specific structure when the piling work to be carried out in different condition

of ground level

Chimney area the working plan was mention in VP1-O-L4-C-UHN-10054 Working plan of excavation works for Chimney

For the other area piling working plan will be done at the current ground level (G.L EL+6.1m)

02/06/2020 O

3 9 - Add work sequence diagram including work

place preparation, surveying, soil and pile head disposal

- Casing will not be used?

Site preparation and survey work procedure is described Soil handling is described in 7.4 Excavating soil and the cutting pile head to be disposed by waste treatment company

The casing is applied for proper depth to prevent the collapsing of the soft and loose soil/sand layer of the hole

02/06/2020 O

Noted

Closed

Trang 2

Well noted and updated

The auger can be lower than the cement milk level from 0.5m~1m (in case have underground water in the borehole to avoid mix grout with water)

02/06/2020 O

5 13 Clarify code/standard for this requirement The frequency of MT test will be clarified and

described in ITP for permanent piling work

02/06/2020 O

6 15 Testing for lateral and tension forces need to be

added as required by PIII-2 Exh B1 8.8.2

Design loading capacity of piles had been verified pursuant to Clause 8.8.2 [Technical specification] Corresponding plan had informed

to client through VP1-0-L4-C-GEN-00020 and the result of test reported though VP1-0-L4-GEN-

1005, 53&54 The working load will be verified

by PDA or compression test Contractor would like to verify the integrity of working pile using PDA

8 21 Please give the evaluation of PDA test compared

with static loading test before acceptance

We will make evaluation of PDA test compared with static loading test when get the results and report it in the final report

02/06/2020 O

9 21 Please clarify frequency of PDA test The frequency will be clarified and described in

ITP for permanent piling work

02/06/2020 O

10 22 Drop height of 2m and 2.5m are commonly

applied After PDA any test to determine integrity

of piles???

The drop height depend on the hammer which will be used The calcuation of drop height will be added in Rev.B During PDA test, the intergrity of test pile will be checked

The cited documents include lateral and tension tests, thus they they should be

included here as well

Trang 3

Page 3 of 5

11 3 of 20 Please detail how many steel plates should be

provided for the piling machine movement on the site to prevent overturning for subcontractor implementation

We will use 4 pieces steel plates that will be used

to spread on road to stabilize the auger machine and crane

Dimension 1500x600x15mm

02/06/2020 O

12 3 of 20 Open holes from all the piles which are driven

down are potential hazards and are the traps on the site it should be covered by stable steel nets

Please detail the countermeasure clearly against this hazards for site implementation

In case of the Open holes from all the piles which are driven down are potential hazards and are the traps on the site it should be covered by stable steel nets Contractors have fabricate steel nets (square wire mesh d10a150 and wider than hole diameter 20cm) to cover open hole and set up barricade with signage installed around the hole

02/06/2020 O

13 4 of 20 Please prepare JSEA and submit pertaining to

this document for site implementation base on Doosan's VP1-C-L4-H-GEN-00003 B HSE Risk Management

14 4 of 20 Please prepare JSEA and submit pertaining to

this document for site implementation base on Doosan's VP1-C-L4-H-GEN-00003 B HSE Risk Management

15 5 of 20 Please prepare JSEA and submit pertaining to

this document for site implementation base on Doosan's VP1-C-L4-H-GEN-00003 B HSE Risk Management

16 6 of 20 Please prepare JSEA and submit pertaining to

this document for site implementation base on Doosan's VP1-C-L4-H-GEN-00003 B HSE Risk Management

OPEN Please reflect it in the risk assessment for site implementation and provide the clue for review

OPEN Please reflect it in the risk assessment for site implementation and provide the clue for review

OPEN please refer to JSA for detail comments

OPEN please refer to JSA for detail comments

OPEN please refer to JSA for detail comments

OPEN please refer to JSA for detail comments

Trang 4

Page 4 of 5

17 7 of 20 Please prepare JSEA and submit pertaining to

this document for site implementation base on Doosan's VP1-C-L4-H-GEN-00003 B HSE Risk Management

18 8 of 20 Please prepare JSEA and submit pertaining to

this document for site implementation base on Doosan's VP1-C-L4-H-GEN-00003 B HSE Risk Management

19 9 of 20 Please prepare JSEA and submit pertaining to

this document for site implementation base on Doosan's VP1-C-L4-H-GEN-00003 B HSE Risk Management

20 10 of 20 Please prepare JSEA and submit pertaining to

this document for site implementation base on Doosan's VP1-C-L4-H-GEN-00003 B HSE Risk Management

21 11 of 20 Please prepare JSEA and submit pertaining to

this document for site implementation base on Doosan's VP1-C-L4-H-GEN-00003 B HSE Risk Management

22 12 of 20 Please prepare JSEA and submit pertaining to

this document for site implementation base on Doosan's VP1-C-L4-H-GEN-00003 B HSE Risk Management

23 13 of 20 Please prepare JSEA and submit pertaining to

this document for site implementation base on Doosan's VP1-C-L4-H-GEN-00003 B HSE Risk Management

OPEN please refer to JSA for detail comments

OPEN please refer to JSA for detail comments

OPEN please refer to JSA for detail comments

OPEN please refer to JSA for detail comments

OPEN please refer to JSA for detail comments

OPEN please refer to JSA for detail comments

OPEN please refer to JSA for detail comments

Trang 5

Page 5 of 5

24 14 of 20 Please prepare JSEA and submit pertaining to

this document for site implementation base on Doosan's VP1-C-L4-H-GEN-00003 B HSE Risk Management

25 16 of 20 Please prepare JSEA and submit pertaining to

this document for site implementation base on Doosan's VP1-C-L4-H-GEN-00003 B HSE Risk Management

26 17 of 20 Please prepare JSEA and submit pertaining to

this document for site implementation base on Doosan's VP1-C-L4-H-GEN-00003 B HSE Risk Management

Additional Notes (if any)

Trang 6

1

ö

Approved

Contractor to revise the correction and resubmit

Revise the correction and resubmit before proceeding

Information acknowledged with no comment

Information acknowledged with comments Note: Approval or comment does not relieve the Contractor of

Trang 48

Page 43

This JSA for only crane operating, what about other risk residual in the risk assessment

Trang 49

Page 44

Trang 50

This is not in line with Doosan risk assessment procedure (only residual risk at job task which exceed 6 need to be

supplement the JSA), please do intensive study Doosan

procedure for the compliance.

Trang 51

Page 46