The scope of the work is a proper way of Antitermite Treatment with the use of (Antitermite Material) on concrete in contact with the soil and on the outer wall to prevent from entering, the steps to be taken in meeting the technical standards and EHS requirements of Van Phong 1 BOT Thermal Power Plant
Trang 1Page 1 of 1
Document Title METHOD STATEMENT FOR ANTI-TERMITE WORK Document Type For Approval
No Section/
Page
Date
Status O/C * Remarks
1 5 24/06/2020
it is recommended to apply termite protection whole slap area to ensure proper termite protection solution.
Rev.B Revised as per comment
2 6 24/06/2020
Please replace this photo to show proper safety performance.
Rev.B Revised as per comment
3 6 24/06/2020
Please replace this photo to show proper safety performance
Rev.B Revised as per comment
4 7 24/06/2020
General comment:
Before conduct spray the chemical, please check wind direction, proper coordinate with other contractor to minimize affect to worker
Rev.B Revised as per comment
5 8 24/06/2020
No good Vietnamese translation
Rev.B Revised as per comment
Additional Notes (if any)
* O - Open, C – Closed
Closed
Closed
Closed
Closed
Closed
Trang 2
OWNER
VAN PHONG POWER COMPANY LIMITED
PROJECT
Van Phong 1 BOT Thermal Power Plant Project
OWNER ’S ENGINEER
Pöyry Switzerland Ltd
Status
□Approved
□Approved with Comment
□Not Approved
□Reviewed
EPC CONTRACTORS
IHI –TESSC–CTCI–DHI CONSORTIUM
PROJECT DOCUMENT No
VP1-0-L4-A-GEN-20025
REV
B DOCUMENT TITLE
METHOD STATEMENT FOR ANTI-TERMITE WORK
EPC
Doosan Heavy Industries and Construction
EPC DOCUMENT No
VP1-0-L4-A-GEN-20025
REV
B
For Approval
Revise the correction and resubmit before proceeding
Information acknowledged with no comment
REVIEWED WITH COMMENT RC
Information acknowledged with comments Note: Approval or comment does not relieve the Contractor of
Discipline:
all obligations covered under contract
Date:
Architectural
08 Jul 20
Trang 3Page | 2
TABLE OF CONTENTS
1 PURPOSE 3
2 MACHINERY & EQUIPMENT 3
3 RESPONSIBILITIES 3
4 MATERIALS 4
5 PROCEDURE & SEQUENCE 4
6 QUALITY CONTROL 7
7 ENVIRONMENT, HEALTH AND SAFETY (EHS) 7
Trang 41.0 PURPOSE
The scope of the work is a proper way of Anti-termite Treatment with the use of (Anti-termite Material) on concrete in contact with the soil and on the outer wall to prevent from entering, the steps to be taken in meeting the technical standards and EHS requirements of Van Phong 1 BOT Thermal Power Plant
2.0 MACHINERY & EQUIPMENT
2
Spray Nozzle ( used to facilitate the formations of spray in the targeted area)
3.0 RESPONSIBILITIES
It is overall responsibility of Project Manager to organize resources prior to perform construction activities as per project specification in compliance with the quality, schedule & safety requirements EHS Manager will ensure in coordination with Site Engineer that all measure/construction taken shall be maintained till completion of job
It is the responsibility of Construction Manager/Site Engineer that construction activities are executed according to the relevant project specification in compliance with the quality, schedule & safety requirements
EPC will ensure that all works are performed safely
The relevant EPC Supervisor will ensure that the work is carried out in accordance with this method statement and project specification
The QC Inspector will ensure that the work is executed according to the requirements of quality dossier are fulfilled
Trang 5Page | 4
4.0 MATERIAL
Anti-Termite material: Termize 200SC (Imidacloprid 200g/L) Material to be changed caused by a letter attached
Reference standard: TCVN 7958
5.0 PROCEDURE AND SEQUENCE
5.1 PRELIMINARY ACTIVITIES
Properly coordinate with the concerned party or main contractor on how the process will be done with regards to application scheduling and area preparation
Coordinate and confirmation of people site access And the water source accessibility on site
The Method Statement (MS) must be on hand with the QA/QC Engineer before the commencement of the work
5.2 PRECONSTRUCTION ACTIVITIES
Remove all wooden pieces, concrete debris, plastic strips, tree stump roots, deleterious materials etc The soil shall be leveled and compacted if in case bottom of the blinding before treatment starts
All construction related tests shall be approved by the Engineer prior to treatment
5.3 CONSTRUCTION ACTIVITIES
A solution of the Anti-termite material diluted with water at a rate of (10-15ml:1 liter) will be sprayed prior to casting with the application rate of 3-5 liters per square meter
The list of building will be anti termite:
1 CCB
2 Coal handling control/electrical house
3 Switchyard control house for 500kv
4 Laboratory
5 Material storage
6 Electricity and C&I workshop
7 Mechanical workshop
8 Administration building
9 Main gate house
10 Sub gate house
B
Trang 6TYPICAL ANTI-TERMITE PLAN
TYPICAL ANTI-TERMITE SECTION
B
Trang 7Page | 6
Inside building the treated area shall then be covered with polythene sheet, it can be opened free until 2 hours, and then casting can be started Casting must be completed by 2 to 24 hours after the Anti-termite application
With Anti-Termite trench (for outside boundary of the building), after spraying, backfill will be done with the backfill material
B
B
Trang 86.0 QUALITY CONTROL
The Site Inspection and Test Plan (ITP) for this work summarize various characteristics to be checked The concerned Site Engineer/Foreman will be responsible to ensure stage wise compliance for these operations and the Site QA/QC Engineer/Inspector will carry-out quality control checks and report the inspection results
7.0 ENVIRONMENT, HEALTH AND SAFETY (EHS)
7.1 RESPONSIBILITIES AND INSTRUCTIONS
PM/EHS Officer shall ensure that all work is undertaken in accordance with the specified work scope Safety training should be conducted to all personnel assigned at site prior to commence any work Carry-out daily tool box and safety talks
Personal Protective Equipment (PPE) shall be worn at all times
Good housekeeping shall be observed in work areas
Keep non-essential workers clear of machinery whilst it is in operation
Construction wastes shall be segregated and disposed to an approved dump yard area
Adequate lighting equipment when working night time
Periodic refresher trainings, toll box talk and audit shall be conducted
7.2 SAFETY (PPE)
All works shall comply with the safety procedure or instruction as set out in project safety plan and municipality rules and regulations
Basic Personal Protective Equipment ( PPE ) shall be worn by all staff or laborers
7.3 ENVIRONMENTAL
The work will be carried with full protection to environment
Working area shall be clean, not slippery and free from any debris
Before conduct spray the chemical, the contractor shall be checked wind direction, proper coordinate with other contractor to minimize affect to worker
B
Trang 9Page | 8
JOB SAFETY ENVIRONMENT ANALYSIS (JSEA) PHÂN TÍCH MÔI TRƯỜNG AN TOÀN CÔNG VIỆC Project: VAN PHONG 1 BOT THERMAL POWER PLANT
dự án:
Date:
Ngày:
Subcontractor:
Nhà thầu phụ:
JSEA No: BD234-JSA-ATW 005
Số JSEA:
Job Location:
Vị trí làm việc:
No of workers:
Số lượng công nhân:
Job Details: Anti-Termine work
Chi tiết công việc: Chống mối
Work Duration / Thời gian làm việc: From / Từ:
To / Dến:
Permit Required: YES NO OTHERS:
Yêu cầu giấy phép: Đúng Không Khác:
Night Work / Holiday Work
Làm việc ban đêm/Làm việc trong kỳ
nghỉ
Electrical Work / LOTO Công việc điện / LOTO
Grating Removal Work Công việc loại bỏ lưới
Radiography Works Công việc chụp ảnh phóng xạ
PPE Required: Head Ear Eye Pulmonary Face Foot Leg Whole Body Others:
Yêu cầu PPE: Cái đầu Tai Con mắt Phổi Khuôn mặt Chân Chân Cả người Khác
B
Trang 10JOB SAFETY ENVIRONMENT ANALYSIS (JSEA) ATTENDANCE LIST PHÂN TÍCH MÔI TRƯỜNG AN TOÀN CÔNG VIỆC (JSEA) DANH SÁCH THAM DỰ
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Trang 11Page | 10
STEP
NO
SỐ BƯỚC
JOB STEP / BƯỚC CÔNG VIỆC NGUY HIỂM HAZARD CÁC BIỆN PHÁP KIỂM SOÁT CONTROL MEASURES ACTION BY DIỄN BỞI
1 Prepare the workforce for
the task
1.1 HSE Induction and confined space training not completed
1.1.1 All personnel must have completed the FADHILI EHS Safety Induction and confined space training prior to commencing work
Safety staff Site Engineer
1.2 Workers not familiar with the scope of works or workplace hazards
1.2.1 JSA to be read & signed by all workers 1.2.2 Scope of work to be discussed with the employee and the hazards of each task
1.3 Inadequate skill specific training for the employees involved in the task
1.3.1 Install fences to restrict access to construction areas
1.3.2 Register of Trainings and Workshop to be kept and maintained by project HSE
2
Pre-start Checks to be
carried out on all
equipments and materials
prior to start any work
2.1 Defective / Faulty machinery; materials, tools and equipment
2.1.1 Ensure all required Pre-start checklist are carried out prior to start any work (generator, welding machines,etc.)
Safety staff Site Engineer
2.1.2 Defects to be documented in the daily log and reported to the supervisor
2.1.3 Employees to inspect all gear prior to use to ensure integrity
2.1.4 All guard and safety features are to be operable, Ensure that the guard and handle are secure
3 Use of Compressor
3.1 Damaged / Defective Equipment
3.1.1 Workers are to check the condition of the equipment for defects prior to use: hose, fuel indicator, and inspection tag
Safety staff Site Engineer 3.2 Sudden release or whipping of hoses
3.2.1 Ensure airline hose connections are secured with whip check or safety cable whips
3.2.2 Ensure nobody is near the hose connection and barricade the compressor
noise level
Trang 123.4 Eye injury
3.4.1 Use safety glasses with side shield or safety goggles
3.4.2 Keep others away from activity 3.5 Dust inhalation 3.5.1 Ensure workers are wearing respiratory
protection, dust mask
3.6 Slip and Trip 3.6.1 Ensure after work, all hoses are rolled or
kept properly
4 Touch-up termite chemical
4.1 Inhalation of paint, lung damage 4.1.1 Wear a respirator and other PPE as
recommended on the MSDS
Safety staff Site Engineer 4.2 Skin Irritation
4.2.1 Wear long-sleeved, loose fitting clothing that covers all exposed skin
4.2.2 Wash exposed areas thoroughly with soap and water after handling (Refer to MSDS)
4.2.3 Do not wash skin or hands with paint thinner
or lacquer thinner, use hand cleaner
4.2.4 Use Appropriate PPE (Mask, Gloves )
4.3 Contamination of clothing
4.3.1 Wash work clothes separately from other clothing; rinse washer after thoroughly after use
10.3.2 Use Appropriate PPE 4.4 Eye Irritation 4.4.1 Wear goggles that seal eyes from chemical
(Safety Glass)
5 Clean Up 5.1 Poor Housekeeping / Slips & Trips
5.1.1 All tools & equipment is to be returned to the appropriate storage area
5.1.2 Housekeeping to be done by all workers before, during and after work To be monitored by their corresponding supervisor
5.1.3 Waste accumulated to be segregated and be disposed properly (wood, steel, general waste and hazardous waste)
5.1.3.2 Loose clothing, exposed jewelry, and uncontained long hair are not permitted to work under pre-ops area
Safety staff Site Engineer
Trang 13Số: 102/2020/CV.HT/PKD TP Hồ Chí Minh, ngày 26 tháng 05 năm 2020
THÔNG BÁO v/v: NGƯNG KINH DOANH SẢN PHẨM LENFOS 50EC
Kính gửi: Quý khách hàng
Công ty Cổ Phần Đầu Tư Hợp Trí cảm ơn Quý khách hàng đã luôn tin tưởng & hợp tác với chúng tôi
trong suốt thời gian qua
Công ty Hợp Trí trân trọng thông báo đến Quý khách hàng về việc ngưng kinh doanh sản phẩm
Thuốc trừ mối Lenfos 50EC, như sau:
1 Thông tin sản phẩm:
- Tên sản phẩm: Lenfos 50EC
- Hoạt chất: Chlorpyrifos ethyl 500 g/L
- Quy cách đóng chai: 100 ml & 1 lít
2 Thời gian ngưng kinh doanh sản phẩm Lenfos 50EC : kể từ ngày 26/05/2020
3 Sản phẩm thay thế: Termize 200SC
- Hoạt chất: Imidacloprid 200g/l
- Quy cách đóng chai: 50 ml, 250 ml & 500 ml
- Liều dùng: Từ 6,25ml đến 12,5ml/5 lít nước hoặc từ 12,5ml đến 25 ml/10 lít nước
+ Xử lý cho công trình đang xây dựng: Phun 5 lít thuốc đã pha cho 1 m2 Phun lên mặt nền trước khi đổ hoặc lót sàn
+ Xử lý cho công trình đang sử dụng (nhà ở, bệnh viện, trường học, …): Khoan lỗ sâu 50
cm dọc theo chân tường và cách chân tường 15 cm Bơm 5-6 lít/lỗ
- Tính năng – tác dụng:
+ Termize 200SC là thuốc trừ mối có tác dụng tiếp xúc và vị độc
+ Thuốc không có mùi và không có tác dụng xua đuổi nên mối không thể phát hiện vùng đã
xử lý thuốc
+ Mối sau khi nhiễm phải Termize 200SC không chết ngay mà sẽ là nguồn lây lan thuốc sang những con khác qua các hoạt động xã hội
(tiếp xúc, cho ăn, làm vệ sinh, …) và sẽ gây chết cả đàn
Trân trọng thông báo!
CÔNG TY CỔ PHẦN ĐẦU TƯ HỢP TRÍ
Giám Đốc Kinh Doanh
NGUYỄN QUANG TRUNG CHÍNH