Test Report for lOin x lOin x lOin piggable wye fitting design test, HydroTech Project 1763H, January.. Test Report for lOin x lOin x lOin piggable wye fitting investigative test, HydroT
Trang 1There were also five tests performed with a misaligning flange installed in
the transit spool The VetcoLog intelligent pig was tested once with a 5° offset
in the misaligning flange, and twice with a 10° offset The TDW dual-diameter
(14x10) scraper pig and the Knapp Polly Pig dual-diameter (14x10) gauging
pig were also tested once each, with a 10° offset
CONCLUSIONS
The test results showed that all of the pigs tested can pass through the
symmetric wye fitting geometry without problem and without damage to the
pig or the fitting Moreover, the successful passing of each type of pig was
demonstrated under a wide range of flowing conditions, i.e pig velocities and
flow conditions in the opposite inlet
The tests using air with the short, light pigs, such as the foam pigs and
spheres, show that concerns over stalling pigs with high by-pass potential can
be eliminated by simply undercutting the inside of the fitting For these types
of pigs, it is recommended that the ID of the fitting be enlarged to remove at
least one-half of the pig squeeze just prior to the crotch area This generally
amounts to approximately a 2-4% increase in the wye fitting ID in the
undercut region
The test results presented in this paper are exclusively for 10-in pigs and
for dual-diameter (14x10) pigs passing through a lOin x lOin x lOin piggable
wye Additional testing is required over a range of other sizes before the
results can be generalized for all sizes
There are a large number of pigs used routinely in pipeline construction
and production operations that have not been tested Therefore, additional
tests are recommended to extend the conclusions to other pigs Specifically
of interest are the other large, heavy, intelligent pigs, such as the British Gas
On Line Inspection pig and the Tubescope Linalog pig.
ACKNOWLEDGEMENTS
The authors wish to thank Transcontinental Gas Pipe Line Corporation,
HydroTech Systems, Inc, Conoco, Inc, and their joint interest owners in the
Jolliet Project, Oxy USA Inc, a subsidiary of the Occidental Petroleum Corp,
and the Four Star Oil and Gas Company, a subsidiary of Texaco Inc, for their
Trang 2Pigging through YJiWngs
kind permission to publish the pig testing results
REFERENCES
1 L.A.Decker, 1989 Test Report for lOin x lOin x lOin piggable wye fitting
design test, HydroTech Project 1763H, January
2 LA.Decker, 1989 Test Report for lOin x lOin x lOin piggable wye fitting
investigative test, HydroTech Project 1763H, March
3 L.A.Decker, 1989 Test Report for lOin x lOin x lOin piggable wye fitting
operational test, HydroTech Project 1763H, May
4 L.A.Decker, 1990 Test Report for lOin x lOin x lOin piggable wye fitting
using gas (air), HydroTech Project 1978S, March
5 LA.Decker and W.S.Tillinghast, 1990 Development of a 10-in piggable
pipeline wye fitting for the Jolliet Project, Offshore Technology
Confer-ence, Paper no.OTC64l5
6 A.Ghielmetti and T.B.Schmitz, 1989 A case history: Agip Barbara lateral
pipeline installation, Offshore Technology Conference, Paper no.OTC6l01
7 B.R.Oyen, 1985 wye connection replaces offshore platform, Pipe Line
Industry, January.
8 W.S.Tillinghast, 1990 The deepwater pipeline system on Conoco's Jolliet
Project, Offshore Technology Conference, Paper no.OTC6403
Trang 3PEAK PIGGING DIFF PRESS
PIG IN TRANSIT DESCRIPTION SPOOL(PSI)
Scraper Pig(Pig Train)
Knapp Foam Pig & TDW 29-40
Dual-Diameter(14X10)
Scraper Pig(Pig Train)
Sun Engineering Squeegee 37-42
0
2-10 N/A 6-25 11-37
1 Soluble sphere velocities based on flow rates.
Table 1 Summary of pigging results.
Trang 4Pigging through Yfittings
.59 FPS (146 6PM) 92 FPS (214 GPM)
2 2 3 FPS (519 GPM) 2.31 FPS (567 GPM) 2.50 FPS (582 GPM) 2.60 FPS (606 GPM)
400-550 GPM
NO FLOW
300-450 GPM
NO FLOW
100-200 GPM
Trang 5PEAK PIGGING DIFF PRES
IN
T-(PSI)
FLOW IN OPPOSITE SIDE
NO FLOW
400-550 GPM
NO FLOW
Table 3 Knapp Polly Pig foam pig (using water)
NO FLOW
Trang 6Pigging through Yfittings
AVG VEL
(FLOW RATE)
.41 FPS (102 GPM) 63 FPS (145 GPM) 66 FPS (163 GPM) 74 FPS (173 GPM) 1.35 FPS (333 GPM) 1.73 FPS (425 GPM) 1.78 FPS (437 GPM) 2.08 FPS (484 GPM)
2 2 3 FPS (518 GPM) 2.40 FPS (559 GPM) 3.68 FPS (855 GPM) 6.90 FPS 1
(1,698 GPM)
PEAK PIGGING DIFF PRES
IN "T"
(PSI) 28
1 Pig also passed through Misaligning Flange with 10 degree offset.
Table 4 TDW dual-diameter (14 x 10) scraper pig (using water).
Trang 7PEAK PIGGING DIFF PRES
IN T"
(PSI)
FLOW IN OPPOSITE SIDE
NO FLOW
NO FLOW
Table 5 Knapp foam pig and TDW dual-diameter (14 x 10) scraper
pig in a pig train (using water).
Trang 8Pigging through Yfittings
PEAK PIGGING TRANSIT PEAK PIGGING
DIFF PRES SPOOL DIFF PRES FLOW IN
IN TRANSIT AVG VEL IN T" OPPOSITE
SPOOL(PSI) (FLOW RATE) (PSI) SIDE
Table 6 TDW 'Redskin' foam pig and dual-diameter (14 x 10)
scraper pig in a pig train (using water).
Trang 9.82 FPS (191 6PM) 91 FPS (211 6PM) 1.49 FPS (346 6PM) 1.78 FPS (437 6PM) 2.08 FPS (485 6PM) 2.40 FPS (559 6PM) 5.18 FPS 1
(1,274 6PM)
PEAK PIGGING DIFF PRES
1 Pig also passed through Misaligning Flange with 10 degree offset.
Table 7 Knapp dual-diameter (14 x 10) gauging pig (using water).
Trang 10Pigging through Y fittings
PEAK PIGGING DIFF PRES
IN T"
(PSI)
FLOW IN OPPOSITE SIDE
(636 GPM) 2.70 FPS (665 GPM) 3.11 FPS (764 GPM)
4 7 8 FPS 2
(1,176 GPM) 4.78 FPS 1
NO FLOW
NO FLOW
1 Pig also passed through Misaligning Flange with 5 degree offset.
2 Pig also passed through Misaligning Flange with 10 degree offset.
Table 8 Vetcolog intelligent pig (using water).
Trang 114.1 FPS (175 SCFM) 5.6 FPS (259 SCFM) 10.0 FPS (510 SCFM) 20.0 FPS (1,477 SCFM)
TOW 'Redskin'
PEAK PIGGING DIFF PRES
IN (PSI)
5.0 FPS (769 SCFM) 7.7 FPS (355 SCFM) 8.3 FPS (1,108 SCFM) 16.7 FPS (1,293 SCFM)
PEAK PIGGING DIFF PRES
IN
T-(PSDN/A
N/A
N/A
N/A
FLOW IN OPPOSITE SIDE
NO FLOW
2,107 SCFM
NO FLOW
NO FLOW
Table 10 S.U.N.Engineering 'squeegee' cup-type pig (using air).
Trang 12Pigging through Yfittings
PEAK PIGGING DIFF PRES
IN (PSI)
T-FLOW IN OPPOSITE SIDE
10
10
4.50 FPS (184 SCFM) 6.30 FPS ( 7 6 9 SCFM) 10.0 FPS (1,539 SCFM) 20.0 FPS ( 1 , 6 4 3 SCFM)
Trang 14PART 4 THE CONSEQUENCES OF INSPECTION
Trang 16Interpretation of pig survey results
INTERPRETATION OF INTELLIGENT-PIG
SURVEY RESULTS INTRODUCTION
Recent years have seen a dramatic growth in the use of on-line inspection
technology for the revalidation of operational pipelines Much of this growth
can be attributed to the success of high-resolution inspection technology in
providing cost-effective solutions to a range of pipeline problems; the
extensive application of these advanced services has allowed pipeline
opera-tors to confirm their accuracy and value
As with all pigging operations, the technical details associated with the
in-field running of inspection tools is of great importance to both the inspection
contractor and the pipeline engineer, and adequate preparations in advance
of any in-field work are essential if expensive errors or delays are to be
avoided Ultimately, however, the provision of inspection data in a final
report is the sole objective of running an on-line inspection tool in a pipeline,
and the value of the entire exercise is determined only by the quality and
nature of the information contained in the report
This paper addresses a number of important aspects relating to British Gas'
inspection technology and to the eventual interpretation of data and
prepa-ration of inspection reports
ACQUISITION OF PIPELINE DATA
In most circumstances, pipelines are selected for on-line inspection on the
basis of some form of risk assessment This is usually related to considerations
for personnel safety and security of supply for gas pipelines, and with an
additional consideration for pollution in the case of liquid lines Although such
assessments are often of a qualitative nature, an increasing number of pipeline
Trang 17operators are adopting formalized, quantitative schemes, which can be used
to great effect in ensuring that the most appropriate inspection, repair and
maintenance programmes are employed over the life of a pipeline
Once the decision has been made to perform an on-line inspection survey
of a pipeline, considerations of technical standard and cost become the focus
of attention The two factors are closely related, since the inspection phase
of a project cannot be financially divorced from the consequent costs of
remedial work and the subsequent costs of pipeline maintenance The
inspection service must, therefore, be regarded as an integral part of pipeline
maintenance, with the accuracy and repeatability of the service determining
the final out-turn of maintenance costs
Preparation
Before a pipeline is inspected, it is prudent to perform a detailed review
of its engineering records to gain early information about it's suitability for
on-line inspection This phase is usually complemented by extensive discussions
with the pipeline operator, and an on-site survey of the line by a British Gas
engineer Once it has been established that the pipeline is suitable for the
running of an inspection tool, the in-field operational phase can begin
In-field tool running
This phase comprises a series of operations, carried out in a specific order
to ensure the successful running of the inspection tool The first part entails
the running of cleaning and bore-proving pigs, to provide optimum
condi-tions for inspection; the second part involves the running of the inspection
tool itself
Extensive preparatory work ensures the timely execution of this part of
the service, together with specialized handling equipment to simplify the
insertion and extraction of pigs In addition, the detail of inspection tool
design provides a virtual guarantee that the tool will pass through the pipeline
without becoming stuck or damaged
Validation of survey data
Of particular importance in the field is the post-inspection validation of the
survey data, and this occurs following the withdrawal of the magnetic tape
store from the on-board tape recorder During the inspection operation, data
Trang 18Interpretation of pig survey results
will have been processed digitally in real time, securely coded against errors,
and organized in a particular format for acceptance by the on-board tape
recorder Clearly, early validation of the data, to confirm the successful
operation of the system, is essential This is a complex task in view of the huge
quantities of data involved, and has demanded major developments in
microcomputer-based test equipment for its completion Following the
confirmation of a successful survey run, the magnetic tape, containing the
inspection data, is returned to the British Gas Computer Centre in England for
detailed analysis and interpretation
Interpretation of inspection data
At the On-Line Inspection Centre, the data recorded on tape during the
inspection run is replayed via a process-control type of computer on to
standard computer tapes, which can then be analysed using one of the
Centre's five main computers These machines reformat and reorganize the
data so that information from the various types of sensor is properly aligned
and correlated with positional data
The next process is to reject signals from normal, defect-free pipeline
fittings such as welds and bends Each fitting gives a particular shape of signal
which can be identified, checked and then eliminated If existing pipeline
maps resulting from previous inspection runs are available, these are also used
to verify and reject data Significant sensor data is then presented on an
electrostatic plotter, and interpreted by trained operators This form of
output allows many parallel sensor traces to be plotted and quickly analysed
Finally, a mathematical sizing model, used in conjunction with a computer
graphics terminal, is employed to obtain a direct estimate of the size and shape
of defects This system is complemented by a comparative sizing technique
based on an automatic search through a large library of known signals
Inspection data must be preserved for comparison with subsequent
inspection logs and as a historical record The scale and frequency of
inspection operations demand that data analysis must be a highly-automated
process The keys to rapid and reliable data analysis are defect sizing
capability, and the ability to recognize and classify automatically the signals
which characterize particular pipeline fittings When such a signal is
identi-fied, it is necessary to check that the fitting is not faulty in some way, for
example to check that a weld between sections of pipe has not become
corroded The integrity of each fitting must be verified, but the obvious
approach of comparing new signals with standard examples works only in a
limited number of cases
Trang 19For instance, a good weld at one point in a pipeline can produce a very
different image from an equally-good weld at a different point on the same
pipeline More sophisticated techniques have had to be used
Possible faults are analysed using pattern-recognition and
image-process-ing techniques similar to those employed in medical scannimage-process-ing and satellite
imaging Such techniques, originally developed for purposes like enhancing
blurred photographs, or teaching computers to recognize particular words,
are equally relevant to the interpretation of pipeline inspection data Instead
of a blurred photograph, the on-line inspection device provides a record of
magnetic field variations in the pipeline; its sharpness is limited by the
response of sensors and electronics and the errors introduced during data
collection in the harsh conditions inside a pipeline
British Gas has modified and developed existing techniques to cope with
the problems posed by pipeline inspection The general approach has been
to measure various parameters to characterize a signal and then to use
statistical techniques to discriminate between significant and spurious data
Much depends on choosing the appropriate image parameters to measure
The experience of engineers who design and operate inspection vehicles has
proved invaluable for this purpose
The data-reduction techniques employed are designed to operate in a
cascade fashion, so that only the simplest operations are applied to the bulk
of the inspection data, more complex steps being reserved for later stages in
the analysis sequence Using various software tools, the operator may search
for particular types of feature, manipulate images on graphics terminals, and
test new signal-processing algorithms to identify any misclassification errors
These techniques have been developed at the On-Line Inspection Centre and
by leading consultancy organizations working under contract
The procedure may be modified when dealing with data from seamless
pipe in which the method of manufacture produces large variations in wall
thickness (often outside specified tolerance limits) over quite small areas of
pipe In addition, the amount of metal-working associated with the forging
process also produces significant variations in the material's magnetic
char-acteristics Such wall-thickness and magnetic variations are detected by
magnetic-flux leakage inspection vehicles, and can obscure or distort signals
from potential defects A special de-blurring process has been developed by
British Gas which enables the "natural" variation in response to be recognized
and eliminated without distorting the signals from metal-loss defects The end
product is corrected data which looks like that obtained from pipes
manufac-tured from controlled-rolled plate