Within 30 days of the award of the Contract, the Contractor shall submit tothe Project Manager for his approval, a complete safety program.. Safety Organization and Responsibility2.1 Saf
Trang 1PROJECT SAFETY PLAN
Trang 3
CONTENT
1 Preface
2 Safety Organization and Responsibility
3 Safety Instruction and Training
4 Implementation of the Daily Work Meeting and Weekly Progress Meeting
5 Recording of safety and reporting of accident
6 Personal Protective Apparel & Other Site Safety Protection Measures
7 Safety Standards and Inspection for Plant and Equipment
14 Access Control on Site
15 Penalties for Safety Violations
Trang 51 Preface
The safety is of paramount importance at all times and consideration ofsuch safety shall take precedence over any and all other consideration Thecontractor shall throughout the execution and completion of the wok,having full regard for safety of all persons entitled to be upon the site andkeep the site and the work in an orderly state appropriate to the avoidance
of danger to such person
The primary objective of the Safety Plan is to avoid human distress andfinancial loss during the performance of all work on field and to ensureeffective control of them It is also expected that every employee does hisbest effort to create a safe environment to work The Safety Programoutlines the procedures essential for the protection of men and materials inwork
Every staff that supervises or directs the work of craftsmen shall pursue hisbest efforts to assure the safety of each employee under his supervision ordirection In addition, he shall be accountable for the protection ofequipment and property within his area of responsibility
Within 30 days of the award of the Contract, the Contractor shall submit tothe Project Manager for his approval, a complete safety program TheProgram shall contain the following as a minimum:
Local requirements, if any, which must be compiled with,i.e., noise control, traffic regulation, etc
The method the Contractor proposes to control and ordinate work of his Subcontractors
co- Safety Plans for layout of temporary construction buildingsand facilities, including how the Contractor plans to controlthose of his Sub-contractors (include sanitary facilities)
Trang 6 Plans for initial and continuing safety education, andtraining for the Contractor's employees.
Plans for traffic control and marking of hazards to cover haulroads, highway intersections, utilities, bridges, restrictedareas, etc
Methods for pedestrian road closures and alternate routes,foot bridges and barricades; directional signs and warningsand pedestrian traffic control This plan shall be co-ordinated with appropriate local People's Committeeofficials
Plans for maintaining continued job clean up and safeaccess
Plans for fire protection and dealing with emergencies(ambulance service, fires, first aid, medical evacuation)
Plans for inspection of the job sites by competent personsincluding reports to be kept, results of the inspection, andcorrective actions taken Particular attention being paid tothe utilization of a "Safety Violation Report Form"
Procedures to be used for accident investigation
Description of safe clearance procedures
Description of office trailer anchoring system
Contingency plans for severe weather
(ii) Activity Hazard Analysis Section
An Activity Hazard Analysis shall be developed for eachcontract activity and operation occurring in each majorphase of work
The Contractor shall develop the plan to identify thesequence of work, the specific hazards anticipated, and thecontrol measures to be implemented to minimise oreliminate each hazard The Activity Hazard Analysis shall bejob specific and shall address the following major points:
Activity being performed (identify major phase), to includebut not be limited to the following :
earth moving (equipment operations, backing signals, etc.)
trenching operation (shoring)
lifting equipment operations (crane certification, rigging,
Trang 7 blasting operations (regulations)
Sequence of work
Hazards to be controlled in each activity, and means ofcontrol, including, but not limited to :
initial and continuing training
personal protective equipment (hard hats, boots, safetyvests, eye/ear protection, etc.)
drugs and alcohol control
The Plan will be reviewed by the Project Manager and ameeting held within two weeks of submittal to discuss andapprove the plan
Trang 82 Safety Organization and Responsibility
2.1 Safety organization chart
2.2 Responsibility
2.1.1 Project Director and Vice Project Directors
Establishing the Safety Control Plan
Trang 9 Taking a measure of accident prevention by coordination throughout the works
Site Patrol
Instruction and Support for Safety Education of Workers
Scheduling and Planning for an Installation of Equipments
Liaison for Authorized Parties
Promote full support of the Safety control Plan
Delegate responsibilities for the various safety functions at all levels ofthe Project
Maintain active involvement in the Project’s safety status and safetymorale
Ensure prompt investigation action on any accident investigations withproper reports completed and follow-up action taken
Be responsible for training and instruction for site engineers and officeengineers about their safety responsibilities
Be equipped to take over the implementation of safety program duringthe time safety manager is absent
Keep main role in Safety team Construction manager will check thetechnical standards and newsletters serving safety method obedient andattaching responsibilities with this safety team
Cooperate with safety manager in evaluating the operation ofsubcontractors and make necessary actions to ensure safety
Support safety manager in relating-to-technique issues
2.2.2 Safety manager
Safety manager is a competent and experienced person who is suitablefor investigation and checking the Safety Plan obedient, and especially indetail but not restrictedly check the Safety Plan Activities in a rolling-upprogram that depending on different time will be submitted toConsultants for approval
The contractor will make no action on site until the Safety manager doesunless Consultants release an official approval document
Trang 10 The contractor must not command the Safety manager to go quit siteunless there is permission in word from Consultants Within 14 days fromthe notice of transfer of that employee, the contractor will choose analter Safety manager and consultants will give final decision.
The contractor authorizes the Safety manager and officers to indicate thecontractor’s or sub-contractor’s employees to end all of their work andcarry out the urgent and reasonable actions to ensure the site safety andprevent unsafe actions or violations to Safety plan or the Law
Evaluate the needs and propose for safety equipments, first-aid and fireprevention Make sure that the safety equipments are in goodmaintenance conditions
Making and maintaining a daily site diary, this recording all relevantmatters concerning site safety, inspections and audits, related incidentsand the like The site diary shall be available at all times for inspection bythe Consultants
Safety manager reports to the project manager and informs the decision
on Safety control plan to workers
Safety manager makes workers list and indicate the leader of workers’groups and implements the workers labour safety training plan
2.2.3 Vice Safety manager
Vice Safety manager is indicated by CEO under the approval fromConsultants and will offer help manage, labour safety monitoring duringconstruction time In case Safety Manager does not present on site, ViceSafety Manager will alter, monitor and decide on matters relating to laborsafety In case serious problem happens, Vice Safety Manager reports toProject manager, Safety Manager can solve the problem
Project manager will indicated a new employee being in charge of sitenurse, carrying out the training of handling health problems forworkers/officers on site
Site nurse must have knowledge of medical, health safety, first-aid andproblems handling
Trang 11Site nurse must has to present on site regularly to monitor activities andmake first-aid and solve medical problem shortly if any
The jobs and actions to do of Vice Safety Manager – Site nurses are asfollows:
Ensure workers health
Monitor the safety training in accordance with site’s requirements
Cooperate in first-aids on site, ensure that employee is basicallyequipped in case the nurse is absent
Investigate all accidents, injuries, fire, and financial loss and otherincidents relating to safety, meanwhile prepare/submit necessary reports
Site nurse has to distinguish between career accidents and time-wastingand injury-causing incidents, monitor to control the situations and fill theform of suitable accidents report
Making and maintaining a daily site diary, this recording all relevantmatters concerning site safety, inspections and audits, related incidentsand the like The site diary shall be available at all times for inspection bythe Consultants
2.2.4 Site Engineer
The Construction manager is directly responsible for the control of siteactivities of this Project They are the key personnel in the implementationand maintenance of an effective job site health and safety program,assisting the Safety Manager
The standards for a good safety programme are established by the SafetyManager and Construction Manager The Site Engineers will be directlyresponsible for the success of Safety Control Plan as they are in directcontact with the Sub-Contractors Their abilities to instill good health andattitudes to the site safety
Sub-Contractors will reflect the success of the Safety Control Plane on site
Site Engineers are responsible for a wide range of activities They mustplan their health and safety activities with care and good effort as theyhave to carry out other portions of their work programme such as cost,
Trang 12manpower allocation and scheduling of the respective work within thisProject.
2.2.5 Safety checker team
Safety checker team is established under the decision of Site engineerwhich was approved by the safety manager Safety checker team is trainedwith labour safety and situations handling
The specific responsibilities of the safety checker team are as follows:
1 Review all work and all new personnel for safety needs Completefamiliarization with safety requirements is an integral part of the totaljob responsibility
2 Continual monitoring of the safety attitudes of Sub-Contractors andtheir responsibilities towards the safety of their trade and participations
in the job safety effort
3 Enforce on compliance with all established health and safetyregulations before and during performance of the work
4 Conduct health and safety inspections and make corrections on a dailybasis
5 Initiate plans prior to the start of work to supply the tools, materials,and equipment necessary to do the job safely
6 Assist with accident investigations to ensure proper reporting anddocumentation with prompt corrections made after accident and toprevent any recurrences
7 Co-ordinate planning and work activities with other supervisorypersonnel performing work within, or adjacent to, their assigned workareas
2.2.6 Sub- contractor’s responsibilities
Trang 131 To ensure that all the respective agents and employees conform withthe contents of this Safety control plan.
2 To supply employees with appropriate safety equipment and applianceswhen working
3 To attend Contractor’s safety meetings, when called upon, and toconduct safety meetings for all his employees
4 To rectify unsafe conditions and hazards when required by contractor’sSafety Manager and/or his staff
5 To maintain good housekeeping
6 Report all accidents to the Contractor’s Safety Manager or his staffimmediately
7 To seek first aid for all injuries, however slight, at the first aid station
8 To be entirely responsible for the implementation of safety measuresand full compliance with regulations of his company in respect of bothhimself and all his employees
9 To ensure that all staff and worker engaged on the project are in soundhealth and capable of carrying out their duties
2.2.7 Operators / Workers
Operators or workers working with tools, plant, equipment, etc areresponsible for their health and safety with others working around them.Therefore, there should be sufficient instructions provided to them Theyshall be responsible for the followings:
1 Use proper, correct and well-maintained tools and equipment for thejobs
2 Wearing of efficient safety helmets and where necessary eye, goggles,ear protection, safety harnesses and other personal protectionequipment for all personnel
3 Maintain and keep tools in good condition at all times
Trang 144 Report defects in plant or equipment or any potential risk to health andsafety to Supervisor
5 Avoid improvising work which entails unnecessary risk
6 Refrain abuse of welfare facilities
7 Suggest ways for eliminating hazards
2.2.8 Sub-contractor management
Contractor will provide sub-contractor with the copied versions of Safety planand bring them into all the clauses of subcontract documents to ensure theplan obedient by all levels in subcontract
Unless there is official approval document from Consultants, contractor willrequire all subcontractors to authorize a representative in charge of safety topresent on site during the implementation time of the contract related tosubcontractors When Consultants approve, Safety manager or safety staff,making to affection to other duties and responsibilities, shall ensure to somepractical extent that all staff provided by subcontractor have knowledgeabout suitable issues of Safety plan and law regulations
3 Safety Instruction and Training
The Safety Education shall be enforced for workers throughout the dailyactivities, while it raises safety consciousness of workers to prevent accident.a)
Orientation for the Newcomers
Newcomer shall have an orientation directed by the Safety Engineer or groupleader to be familiar with working atmosphere
b)
Education for a New Activity/Method
Trang 15A group leader shall give a description of an activity with tips of safetymaters to eliminate any of unsafe factors
3.1 Instruction and Training on the Job
1 Contractor shall hold a Training course on first-safety All workers shallattend this course in the first week of mobilization to site Safetymanager and vice safety manager shall edit the training course book,
be in charge of training and instructing workers in the course
2 Training periods shall ensure the effectiveness, provide workers withinformation about safety regulations, safety equipments use, andsituations handling in incidents At the end of the course there shall be
an comprehension test to check the understanding of workers Thosewho fail the test shall not be allowed to take part in the construction
3 Contractor also hold periodic safety training course every six months.Contractor shall ensure that all subcontractors’ staff attending in thecourse which is appropriate to the job’s features, levels and timeaccording to subcontract This regular course is for all workers on siteand supervisors as well as managers
4 Safety meeting: Safety meetings scheduled on regular basis shall beheld at least once a month with the attendance of safety manager andsafety representatives of subcontractors Safety meetings shall beinformed in advance to Consultants to decide the attendant Themeeting minutes shall be made and sent to Consultants within 7 daysfrom meeting day
5 Everyone required entering confined or enclosed spaces oratmospheres with immediate danger to life, shall be instructed as tothe hazards involved and precautionary measures to be taken Training
by qualified person on the use and care of such emergency andprotective equipment shall be conducted Contractor’s staff shallcomply with all specific regulations in dangerous or potentiallydangerous areas
6 Install the safety signal system on site They shall be in accordancewith regulation and have suitable size to the installation positions
Trang 16Especially, contractor shall pay attention to installing safety signalposts at dangerous areas such as electricity source, poison, flammablematters
7 All employees who have to handle poisons, caustic or other harmfulsubstances, are required to receive instruction regarding the safehandling and use Information and knowledge on the potential hazards,personal hygiene, protective equipment and other personal protectivemeasures involved or required
8 Personnel who may be required to use the rescue or life savingequipment must be familiar with the locations of the equipment andknowledge with training on using them
9 Personnel required to provide or receive signals, must be familiar withthe proper use of the signal system
10 Personnel required handling or using flammable liquids, gases ortoxic materials must be trained in the handling, storage and use ofthem with specific protection requirements
11 Whenever the employees are likely to expose to extremetemperature or exceed atmospheric pressure, instructions onrecognition, potential hazards, avoidance of injury and first aidprocedures to be applied for any incident
12 Contractor shall provide training on the handling of emergencysituations that may arise from the use of equipment in the Project
13 Instruction to use and operate any heavy equipment will be givenand personnel required to use these equipment shall demonstrate theirproficiency in the operation process
14 Any personnel required working with energized power andtransmission lines shall be instructed and trained in the live line bare-hand technique and safety requirements before allowed to use
3.2 Training plan at the first period
Trang 17Training content Attendants
Introduction of labour safety in
construction All contractors’ staff
Situation handling skills training for
workers All contractors’ staff
Health safety instruction – training
for workers All contractors’ staff
Examination on training
comprehension – Course
summation
To-be-trained objectives
Opening new course for new
workers (supplement workers)
Workers who never attend the course
Special training Workers whose job require
high safety Safety checker team – site
engineers training
Safety checker team – site engineers
3.3 Special safety training
1 Object : Specific Safety training for Workers to be in service for specifictasks that are considered as dangerous work
2 Period & Time: Before work start (Required time will be decided bySafety Manager subject to work condition)
3 Instructor: Safety Manager / Specialty Supervisor (e.g Riggingsupervisor / Heavy Lift supervisor)
4 Contents : Work procedure, characteristic of work, potential risk ofhazard, safety requirement and emergency measures
3.4 Emergency communication
1 The emergency communication system shall be established andposted at the convenient access-ways, in all site offices, in all securitytowers / gates, medical center, in order for speedy rescue of theaccident victims, timely communication with local fire brigade office,prompt response from first aid staff, and the soonest possibleevacuation of the workforce if necessary in a serious emergency
Trang 182 First Aid station shall be manned during all working hours This will be
24 hours if necessary First aid center will be equipped with telephoneand 2 way radio
3 Medical Staff will be well informed as to the project layout and betaken on regular site visits as the project changes so that they alwaysknow the access routes and stairs to ensure quickest access to injuredpersons
4 Implementation of the Daily Work Meeting and Weekly Progress Meeting
Daily Work Meeting shall be held once a day with attendance of all staffand work group leaders Agenda shall include:
Exclusion of unsafe action by workers
An instruction sheet shall be issued in accordance with the decision andconfirmation of the responsible persons In addition, Weekly Progress Meetingshall be also held to monitor and update workforces, materials, and safetymatters
5 Recording and reporting of safety and reporting of Accidents
Trang 195.1 Recording and reporting of safety
The contractor shall maintain such records and make such report concerningsafety Such report shall be submitted to Employer representative and theengineer representative on monthly
The Contractor shall submit a summary report as part of the MonthlyProgress Report Prior to submission, the Contractor’s Representative orProject Manager shall endorse the Report Site safety reports shall address allrelevant aspects of site safety and industrial health regulations and, inparticular, report on all site safety audits undertaken during the periodcovered by the report
5.2 Reporting of Accidents
The contractor shall report to the Engineer details of any accident as soon aspossible after its occurrence In the case of any fatality or serious accidentthe contractor shall, in addition, notify the Engineer immediately by thequickest available means
6 Personal Protective Apparel & Other Site Safety Protection Measures
6.1 Personal Protective Apparel
Personal Protective gears like protective footwear such as safety boots,rubber boots, gloves shall be worn by employees engaged in works thatrequire such protection All points of entry for hard hat (safety helmet) must
be identified with the sign Visitors to site must also adhere to the safetyrequirements at the site
1 Protection to eyes and face for work that may cause injury due tophysical, chemical or radiation agents
2 Reflective or high visibility material should be worn for staff exposed tovehicular traffic e.g signalmen, spotters, inspectors, servicemen, etc
Trang 203 Protective nets for overhead protection shall be provided wherever thepublic or workers are subjected to injury due to falling objects.
4 Work near protruded vertical reinforcing steel shall not be permittedunless provision to eliminate possible hazards is carried out
5 Protection to ears with ear plugs or ear muffs are required for soundtransmitted at working area that exceeds 85 dB
6 Insulating personal safety gears such as insulating gloves, insulatingline hose, etc to be provided for electrical staff