59/2007/ND-CP dated 09/04/2007 of Government onthe management of solid waste ♦ Decree 209/2004/ND-CP dated 16/12/2004 of the Government onmanagement of construction quality ♦ Decision No
Trang 1ENVIRONMENTAL MANAGEMENT PLAN
Trang 21 INTRODUCTION
2 ORGANIZATION FOR ENVIRONMENTAL CONTROL
3 THE COMMUNICATION LINE CHART, INTERACTION AND COMMUNICATION
4 ENVIRONMENTAL MANAGEMENT APPROACH
RECORDS/ACTIVITIES
Trang 3This Environmental Management Plan will present the Contractor’s measures
to minimize environmental impact of the construction works on local andpublic residents
This Environmental Management Plan will also be a part of the site qualitymanagement Those objects to be monitored and considered are air, water,noise, vibration level
This Environmental Control and Protection Plan is submitted for approval ofthe Engineer and Employer This Environmental Control and Protection Planwill be reviewed or revised whenever any related law is changed or any need
(a) Timely submission of reports, information and data,
(b) Participating in the meetings conveyed by the Engineer, and
(c) Any other assistance requested by the Engineer
The Contractor will provide monthly reports to the Engineer on theimplementation of the requirements contained in this EMP and the results ofthe environmental performance monitoring
Contractor’s Camps will be located in areas that minimize disturbance tosurrounding land uses; suitable solid and liquid waste disposal systems will beimplemented by Contractor to minimize impacts to the surroundingenvironment
The hierarchy for formulating mitigation measures can be summarized asfollows: 1) avoid the impact; 2) minimize the impact; 3) rectify the impact;and 4) compensate for the impact
Trang 4environment, Total Environment Management Plan, the approvedEnvironmental Management Plan, and Engineer’s instructions Also, theContractor will execute Environmental Monitoring with nominated Sub-Contractors.
The provisions of the standards and existing applications with newpublications will be applied to specific tasks within this plan
a Vietnamese legal documents:
Legal foundation for execute the Environmental impacting report is officialdecision of Government, Ministry of Environment and Resources:
♦ “National Law of Environmental Protection” (NLEP) issued in 2005based on the document issued by the National Assembly onNovember 29th, 2005, amended in July 1st, 2006 replacing theNLEP-1993
♦ “Construction Law” No 16/2003/QH issued by the NationalAssembly in 26/11/2003
♦ “Water resource Law” No 08/1998/QH10 issued by the NationalAssembly in 20/05/1998
♦ Decree No 29/2011/ND-CP dated 18/04/2011 specified list of 146project group must be reported on strategic environmentalassessment, environmental impact assessment, environmentalcommitment of 19 field
♦ “Degree No 21/2008/NDCP: amending and supplementing anumber of articles of the Government’s Decree No 80/2006/ND-CP
of 9 August 2006 detailing and guiding the implementation of anumber of articles of the Law on Environmental Protection
♦ “Decree No 80/2006/ND-CP” providing guidance forimplementation of the NLEP 2005
♦ Decree No 59/2007/ND-CP dated 09/04/2007 of Government onthe management of solid waste
♦ Decree 209/2004/ND-CP dated 16/12/2004 of the Government onmanagement of construction quality
♦ Decision No.16/2008/QD-BTNMT date 31/12/2008 of Ministry ofNatural Resources and Environment on the issuance of nationaltechnical regulations on environmental
♦ Decision No.04/2008/QD-BTNMT date 18/07/2008 of Ministry ofNatural Resources and Environment about issued Nationaltechnical regulations on environmental
♦ Decision No.23/2006/QD-BTNMT date 26/12/2006 of Ministry ofNatural Resources and Environment about issued the list ofhazardous waste
Trang 5♦ Decision 22/2006/QD-BTNMT on 18/12/2006 of the Minister ofNatural Resources and Environment about the mandatory ofVietnam standards on the environment.
♦ Decision of the Ministry of Health 3733/2002/QD-BYT dated10/10/2002 about the application of 21 occupational healthstandards 05 rules and 07 principles of occupational healthinformation
♦ Circular No 43/2010/TT-BTNMT dated 29/12/2010 of the Ministry ofNatural Resources about issued National technical regulations onenvironmental
♦ Circular No 42/2010/TT-BTNMT dated 29/12/2010 of the Ministry ofNatural Resources about issued National technical regulations onenvironmental
♦ Circular No 41/2010/TT-BTNMT dated 28/12/2010 of the Ministry ofNatural Resources about issued National technical regulation onthe environment
♦ Circular No 39/2010/TT-BTNMT dated 16/12/2010 of the Ministry ofNatural Resources about issued National technical regulations onenvironmental
♦ Circular No 16/2009/TT-BTNMT date 10/7/2009 of the Ministry ofNatural Resources about issued Regulation of national technicalregulations on environmental
♦ Circular 08/2009/TT-BTNMT July 15, 2009 of Ministry of NaturalResources and Environment about provide for the managementand protecting the environment in economic zones, high-techzones, industrial zones and industry area group
♦ Circular 02/2009/TT-BTNMT March 19, 2009 of Ministry of NaturalResources and Environment about Regulation assess the capacity
to receive waste water
♦ Circulars No: 05/2008/TT-BTNMT date 08/12/2008 of Ministry of
Natural Resources and Environment about Guidance onenvironmental assessment strategies, assessment ofenvironmental impact and a commitment to protect environment
♦ Circular 04/2008/TT-BTNMT date 18/9/2008 of Ministry of NaturalResources and Environment about guiding of the establishment,approval or certification of environmental protection projects andsupervise the implementation of insurance schemes environment
♦ Circular No 59/2007/ND-CP dated 09/04/2007 of Government onWaste Management
♦ Circular No 12/2006/TT- BTNMT December 26, 2006 of Ministry ofNatural Resources and Environment about guiding the practiceconditions and procedures for making records, registration andlicensing of practice and codes of management hazardous waste
Trang 6b Standards and specifications:
Standards for Water Quality:
♦ TCVN 6773:2000 Water quality for irrigation;
♦ TCVN 6774:2000 Freshwater quality for aquatic life protection;
♦ TCVN 8184-1:2009 Water quality Term Part 1;
♦ TCVN 8184-2:2009 Water quality Term Part 2;
♦ TCVN 8184-5:2009 Water quality Term Part 5;
♦ TCVN 8184-6:2009 Water quality Term Section 6;
♦ TCVN 8184-7:2009 Water quality Term Section 7;
♦ TCVN 8184-8:2009 Water quality Term Section 8;
♦ QCVN 08:2008/BTNMT-National technical regulation for surfacewater quality;
♦ QCVN 09:2008/BTNMT-National technical regulation forgroundwater quality;
♦ QCVN 10:2008/BTNMT-National technical regulation for coastalwater quality;
♦ QCVN 14:2008/BTNMT-National technical regulation for water;
♦ QCVN 24:2009/BTNMT-National technical regulation for industrialwastewater;
♦ QCVN 01:2009/BYT: National technical regulation on drinking waterquality
♦ QCVN 02: 2009/BYT: National technical regulation on water quality
Standards for Air Quality:
♦ TCVN 5508:2009 Workspace Air Requirements of microclimateconditions and methods of measurement;
♦ TCVN 5509:2009 Workspace Air Silica dioxit in dust inhalation.Maximum exposure limit;
♦ QCVN 05:2009 / BTNMT - National technical regulation for ambientair quality;
♦ QCVN 06:2009 / BTNMT - National technical regulation for certainhazardous substances in ambient air
♦ QCVN 19: 2009/BTNMT - National technical regulation for industrialemissions for dust and inorganic substances;
Trang 7♦ QCVN 20: 2009/BTNMT - National technical regulation for industrialemissions of some organic matter;
Standards for pollution limit levels in the soil:
♦ QCVN 03:2008 / BTNMT: National technical regulations on limits ofheavy metals in soil
♦ QCVN 15:2008 / BTNMT: National technical regulations on plantprotection chemical residues in soil
Standards for solid waste management
♦ TCVN 6705:2009 Ordinary solid waste Classification;
Standards for The criteria of hazardous waste
♦ TCVN 6706:2009 Hazardous waste Classification;
♦ TCVN 6707:2009 Hazardous waste Warning signs;
♦ QCVN 07: 2009/BTNMT - QCKT National technical regulation forlimit of hazardous waste;
Standards for Noise and Vibration Quality:
♦ TCVN 7880:2008: Road Transportation Noise emitted fromautomobiles
♦ TCVN 7881:2008: Road Transportation The noise emitted bymotorcycles
♦ TCVN 7882:2008: Road Transportation The noise emitted bymotorbicycles
♦ QCVN 26:2010 / BTNMT: National technical regulation on noise
♦ QCVN 27:2010 / BTNMT: National technical regulation on vibration
Trang 8Standards for labor health:
♦ Decision 3733/2002/QD-BYT dated 10/10/2002 of the Ministry ofHealth about the application of 21 labor health standards
o Standardization of microclimate
o Noise standards
o Standard vibration
o Chemical - The limit in the worked atmosphere
1.4 Environmental Management Plan
The Contractor will be responsible for the remedy or mitigation measure(s)required by the environment-related efects of the works
In case of an environmental problem, the Contractor will immediately notifythe Engineer who will instruct the Contractor as to the next course of action totake Among the situations which may require such steps, are complaints orlegal actions by third parties on matters such as environmental damage toproperty and natural resources, ground subsidence, interruption ofgroundwater flow, and surface and groundwater contamination
This Environmental Control and Protection Plan will be submitted, however, itwill be revised as Vietnamese law changes or for making it suitable for thesituation at site
Although a guide for whole view and some detail measures for environmentalmanagement are mentioned in this Environmental Control and Protection Plan,more concrete measures will be discussed in Method Statement for eachconstruction work
Trang 9Organization Chart of the Contractor
Figure 2.1 shows the organization of Environmental Control and ProtectionPlan and environmental monitoring
Figure 2.1
Trang 10Key personnel of each other position will be decided and submitted as
addendum of this plan separately
Project manager will decide the guide for environmental measures,Environmental expert/ assistant of Environmental expert will make the detailplan
Environmental expert will supervise and implement the environmentalmanagement measures during construction The environment report toengineer was also implement and take responsibility by the Environmentalexpert
Environmental safety assistants are regularly present at site, information andreporting to environmental expert (or Project Manager as needed) to gatherfor periodic reporting
The construction group leader, representing of the subcontractor thatsupervise the construction activities, if find out any environmental problemswill be reported to environmental expert, project manager to be providedreasonable solutions
3 THE COMMUNICATION LINE CHART, INTERACTION AND
COMMUNICATION PROCEDURE:
All the problem happened at site will be informed to Site Engineer andEnvironmental Engineer from workers, stafs or Sub-Contractor, and the reportwill be made to Project Director through Engineer or Sub-Contractors, and thereport will be made to Project Director through Safety/Environmental Manager.Every problem will be reported to the Engineer as well
The Communication Chart for the implementation of Environment Control Planwill be as follows:
Trang 11Related Authorities
The related authorities for the Environment Control and Protection control are as
follows:
The Employer - Ministry of Natural Resource and Environment
The Dong Thap Natural Resource and Environment Office
Highway Maintenance Board: Ministry of transport, Dong Thap Department of
transport
Environmental Management Authority: Ministry of Environment, Dong Thap
Department of Environment
4 ENVIRONMENTAL MANAGEMENT APPROACH
4.1 Method of Promoting Environmental Awareness
In this Project Environmental Control and Protection Plan, the Contractor will
present the measures to minimize environmental impact of the construction
works
Although a guide for whole view and some detail measures for environmental
management are mentioned in this Plan, more detailed measures will be
discussed in Method Statement for each construction work
To promote environmental awareness both amongst on the site Contractor
stafs and to the surrounding community so that an awareness of the
Trang 12measures implemented to minimize impact is promoted, the Contractor willcarry out following procedures:
- Monitoring and reporting the quality of the environment before construction
- Repetitive and continuous education for the site Contractor stafs to havethem to be recognized the significance of environmental protection
- Continuous efort of environmental approach to improve the site condition
to minimize the impact
- To appeal the efort and consequence, the community to be notified theoutcome
- Perform the community consultation and dispute settlement (if any) to raiseawareness about the environment, answer people's questions and get supportfrom people in any environmental problems
4.2 Specific Procedure for Achieving the Environmental Performance Requirements
To comply the requirements in the relevant legislation, the Contractor willcarry out following procedures:
- Conforming to the Socialist Republic of Vietnam’s Laws on Protection ofEnvironment (NLEP) and other relevant legislation,
- Responsible for ensuring that no debris is deposited on public or privateright of way as a result of its operations, including any deposits arising fromthe movement of Construction Plant or vehicles
- The Contractor will ensure that all existing stream courses and drainswithin, and adjacent to, the Site are kept safe and free from any debris andany excavated materials arising from the works The Contractor will ensurethat chemicals and concrete agitator washings are not deposited in thewatercourses
- All water and waste products arising on the Site will be collected, removedfrom the Site via a suitable and properly designed temporary drainagesystem and disposed of at a location and in a manner that will causeneither pollution nor nuisance
- The Contractor will construct, maintain, remove and reinstate as necessarytemporary drainage works and take other precautions necessary for theavoidance of damage by flooding and silt washed down from the Works, Itwill also provide adequate precautions to ensure that no spoil or debris orany kind arc allowed to be pushed, washed down, fallen or be deposited onland adjacent to the Site
Trang 13- In the event of any spoil or debris from construction works being deposited
on adjacent land or any silt washed down to any area, then all such spoil,debris or material and silt will be immediately removed and the afectedland and areas will be restored to their natural
Waste Disposal and Site Drainage Systems: The following conditions shallapply:
Solid Waste Disposal: Proper management of solid waste shall be practiced
on-site Temporary holding area for construction waste materials shall bedesignated Recyclable materials should be recovered and sold to recyclers orhauled out of the site by the Contractor Residual wastes shall be disposed of
in approved landfill or disposal site A permit from the commune or town shall
be secured prior to disposal
Waste Water Disposal: All water and waste products arising on the Site shall
be collected, removed from the Site via a suitable and properly designedtemporary drainage system and disposed of at locations and in manners thatwill cause neither pollution nor nuisance The Site Plan shall indicate thesystem proposed and the locations of related facilities on the Site, includinglatrines, holding areas, etc There shall be no direct discharge of sanitary orwash water to surface water Disposal such as, but not limited to, lubricatingoil and similar materials, onto the ground or into water bodies shall beprohibited Liquid material storage containment areas shall not drain directly
to surface water Liquid material storage containment areas equipped withdrains shall be valved and the valve shall be maintained locked in the closedposition with supervisory control of the key Lubricating and fuel oil spills shall
be cleaned up immediately and spill clean-up materials shall be maintained atthe storage area Spill clean-up materials shall be disposed in approved landfill
or disposal sites
Drainage: The Site Plan shall be devised to ensure that rain run-of from the
construction Sites is not deposited directly into any watercourse, stream, orcanal and shall indicate the system proposed, including the locations ofretention ponds and other facilities There shall be no direct discharge ofsanitary wastewater, wash water, chemicals, spoil, waste oil or solid waste tosurface water bodies Fuel, lubricating oil and chemical spills shall becontained and cleaned-up immediately Spill clean up equipment will bemaintained on Site
Locations Relative to Watercourses: The Site Plans shall be devised to
ensure that, insofar as possible, all temporary construction facilities are locate
at least 50 meters away from a water course, stream, or canal Allconstruction site drainage should be directed into temporary settling basinsbefore release into watercourses
Locations of Fueling Operations: Fueling operations shall occur only within
containment areas
Other Water-Related Facilities: The Contractor is required to construct,
maintain, remove and reinstate as necessary temporary drainage works andtake all other precautions necessary for the avoidance of damage by floodingand silt washed down from the Works Site Plans must indicate adequateprecautions to ensure that no spoil or debris of any kind are allowed to bepushed, washed down, fallen or be deposited on land or water bodies adjacent
to the Site
Trang 14Locations Relative to Settlement and Urban Areas: To avoid potential
conflicts with local communities, construction camps should, insofar aspossible, be located at least two kilometers from urban areas
Location of Batching Plant(s): Dry mix batching shall be carried out in a
totally enclosed area with exhaust to suitable fabric filters The locations ofthese facilities should be clearly illustrated by the Site Plans Batch plantsshould be placed at a distance no less than 500 m from the nearest residence
Location of Wheel Washing Facilities: If determined warranted by the
Engineer or Environment/Safety Officer, the Contractor shall provide a wash pit
or a wheel washing and/or vehicle cleaning facility at the exits from the Sites If
so requested, the Contractor shall ensure that all vehicles are properly cleaned(bodies and tires are free of sand and mud) prior to leaving the Site areas TheContractor shall provide necessary cleaning facilities on Site and ensure that nowater or debris from such cleaning operations is deposited of-site Thelocations of these facilities shall be clearly illustrated by the Site Plans
Location of Sand and Aggregate Storage Provisions: The Contractor shall
implement dust suppression measures that shall include, but not be limited tothe following:
Stockpiles of sand and aggregate greater than 20 cubic meters for use inconcrete manufacture shall be enclosed on three sides, with walls extendingabove the pile and two (2) meters beyond the front of the piles
Cement and other such fine-grained materials delivered in bulk shall be stored
in closed silos fitted with a high-level alarm indicator The high-level alarmindicators shall be interlocked with the filling line such that in the event of thehopper approaching an overfull condition, an audible alarm will operate, andthe pneumatic line to the filling tanker will close
Conveying Systems: Where dusty materials are being discharged to vehicles
from a conveying system at a fixed transfer point, a three-sided roofedenclosure with a flexible curtain across the entry shall be provided Exhaustfans shall be provided for this enclosure and vented to a suitable fabric filtersystem Locations and essential details for these facilities shall be indicated onthe Site Plan as warranted
Other Air Quality Features: Construction walls will be provided in all
locations where strong winds could cause the blowing of dust and debris ThePlan shall indicate where such facilities are proposed All exposed surfacesshall be retained in a damp condition to eliminate dust generation due totrafficking
Locations of Liquid and Toxic Material Storage Areas: The Environmental
Management Plan (EMP) shall specify the locations for the storage of liquidmaterials and toxic materials The following conditions to avoid adverseimpacts due to improper fuel and chemical storage:
All fuel and chemical storage (if any) shall be sited on an impervious basewithin a bund and secured by fencing The storage area shall be located awayfrom any watercourse or wetlands The base and bund walls shall beimpermeable and of sufficient capacity to contain 110 percent of the volume oftanks
Trang 15Filling and refueling shall be strictly controlled and subject to formalprocedures and will take place within a bounded area to contain spills / leaks ofpotentially contaminating liquids.
All valves and trigger guns shall be resistant to unauthorized interference andvandalism and be turned of and securely locked when not in use - Thecontents of any tank or drum shall be clearly marked Measures shall be taken
to ensure that no contaminated discharges enter any drain or watercourses.Disposal of lubricating oil onto the ground or water bodies will be prohibited.Should any accidental spills occur immediate clean up will be undertaken andall cleanup materials stored in a secure area for disposal to a Site authorized todispose of hazardous waste
Trang 16Pre-construction and construction phases mitigation measures
quality; QCVN 09:2008/BTNMT – National technical
regulation on groundwater quality Example
mitigations include:
Implement sediment capture devices, such as traps or basins, to avoid sediment laden runof entering watercourses
Avoid clearing activities during the rainy season
Store chemicals, fuels/oils in covered areas away from watercourses with concrete floors and bunding
Ensure prompt clean-up of any spills
Implement solid and liquid waste management systems at construction camps and at construction sites
Implement wheel washing facilities at construction sites
Develop drainage plan to store solid and liquid wastes from construction site
watercourses
Trang 17IMPACT MITIGATION OBJECTIVES MITIGATION MEASURES
Implement sediment capture devices, such as traps or basins, to avoid sediment laden runof entering Minimise heavy excavation activities plus clearing during dry season
Spray water as needed on dirt roads, cuts, fill material and stockpiled soil to reduce wind-induced erosion;
Slope works and earth moving/excavation shall be conducted in order
to minimize exposure of soil surface both in terms of area and duration Temporary soil erosion control and slope protection works shall be carried out in sequence to the construction;
at least twice a day during dry season
Minimize of size and duration of exposed areas
Cover of trucks carrying dispersible materials
Ensure construction vehicles and equipment are well maintained
Minimise heavy excavation activities plus clearing during dry season
Trang 18IMPACT MITIGATION OBJECTIVES MITIGATION MEASURES
Be responsible for repairing any damage caused as the result of vibrations generated from or by the use of our
equipments, plants, and machineries
Erect temporary noise barriers where schools and other potentially sensitive receptors
Sensitive receptors will be avoided as possible (i.e., aggregate crushers, operators, etc.) Non vibratory rollers (for compaction) will be used near sensitive receptors such as Earthwork
Procure materials from closest quarries whenever possible
Adhere to GOV regulations for sand, rock and soil extraction in the event that contractors themselves exploit sand, rock and soil from rivers, quarries and soil borrow pits respectively
Use on-site materials whenever possible
Prohibit fishing during dredging
Trang 19• Dispose PASS/ASS into contained areas with internal bunds
• Construct drainage ditch around perimeter of bunds to collect leachate, and return it back to main waterway
• Cover contained the PASS/ASS with the PVC membrane
• Ensure safety near the containment area
Ensure construction camps and construction sites have adequate sanitation and waste management systems
Ensure construction workers have access to and are trained in the use of construction safety equipmentWork with local authorities to implement awareness campaigns for local community about issues
associated with presence of construction workers
Ensure prompt clean-up of any spillsImplement solid and liquid waste management systems at construction camps and construction sitesImpacts
Trang 20Socio – Economic Impacts
Undertake training of construction works to minimize conflicts with local communities, particularly in relation
to safety, hygiene and transmission of diseasesWhere possible, avoid housing workers in construction camps Ensure construction camps have adequate sanitation and waste management systems
Changes to
accessibilit
y
Improve local and network wide
Inform local community and drivers of schedule of works and duration of disruptions
Install signage and warnings for drivers in the vicinity
As far as practical, limit construction vehicle movements to main transport routes
Install signage and warning signs in vicinity of worksImplement lighting if night time works undertaken
As far as practical, avoid construction vehicle movements in peak hours
Efects on
public
health
Improve public health
conditions
Avoid pounding of water in construction site by promptly backfilling depressions and maintaining a tidysite
Implement dust suppression measures described previously
Undertake training of construction workers to minimizeconflicts with local communities, particularly in relation
to safety, hygiene and transmission of diseasesImplement warning systems to warn downstream communities of changes to water quality that may afect fisheries or suitability of water for domestic useWhere possible, avoid housing workers in construction camps
Ensure construction camps and construction sites haveadequate sanitation and waste management systemsEnsure construction workers have access to and are trained in the use of construction safety equipmentWorker and
public
safety
Minimize risks
to worker and public safety
Develop an accident contingency plan for the construction works
Trang 214.3 Air Quality control
To avoid air pollution, sufficient air pollution control and quality monitoring will
be made
(a) Related Regulations
Air quality monitoring will be conducted prior to construction The samplingstations will be selected along the project area during construction
The Contractor will not install furnaces, boilers or other similar Plant orequipment using fuel that may produce air pollutants without prior writtenapproval of the Ministry of science, Technology, and Environmental pursuant tothe Vietnam's National Law on Protection of Environmental and other relevantlegislation such as;
- QCVN 05 2009: Air quality - Air quality standards for surroundingenvironment
- QCVN 06 2009: Air quality - The highest allowed concentration of harmfulsubstances in ambient air
Using the equipment for construction that sastify all air standards (see morestandard equipment - submissions of construction machinery)
(b) Mitigation Measures for impacts on air quality
Table 4.1 shows the potential impacts it might occur, and mitigation
measures for each