After reading the material in this chapter, you should be able to: Describe what MRP is and where it is best applied, understand the source of the information used by the system, demonstrate how to do an MRP “explosion,” explain how order quantities are calculated in MRP systems.
Trang 1Material Requirements Planning
Trang 2Learning Objectives
1. Describe what MRP is and where it is best
applied
2. Understand the source of the information
used by the system
3. Demonstrate how to do an MRP “explosion.”
4. Explain how order quantities are calculated in
MRP systems
Trang 3Enterprise Resource Planning
(ERP) and Material Requirements Planning (MRP)
Trang 4Material Requirements Planning
(MRP)
The logic that ties production functions
together from a material planning and control view
A logical, easily understood approach to the
problem of managing the parts, components, and materials needed to produce end items
How much of each part to obtain?
When to order or produce the parts?
Dependent demand is drives the MPR system
Trang 5Master Production Scheduling
The master schedule deals with end items and is a
major input to the MRP process
All production systems have limited capacity and
limited resources
The aggregate plan provides the general range of operation, the master scheduler must specify exactly what is to be
produced
To determine an acceptable feasible schedule to be released to the shop, trial master production
schedules are tested using the MRP program
Trang 6Master Production Scheduling
Week
Aggregate plan shows overall quantities to produce – without specifying type
MPS shows quantities
of each type, with
information about the
production time frame
Trang 7MRP System Structure
MRP
system
inputs
Trang 8Product Demand Sources
Customers – specific orders placed by either external or internal customers
Aggregate production plan – the firm’s strategy for meeting demand in the future,
implemented through the master production
schedule (MPS)
Trang 9Bill of Materials (BOM)
Trang 10MRP Explosion Process
Trang 11MRP Explosion Process
(continued)
Trang 12Lot Sizing in MRP Systems
Determination
of lot sizes in
an MRP system
is a
complicated
and difficult
problem
Lot sizes - the
part quantities
issued in the
planned order
receipt and
planned order
release
sections of an
Trang 13Lot-for-Lot
Trang 14Economic Order Quantity
Trang 15Least Total Cost/Least Unit
Cost
Least total cost method (LTC) - a dynamic
lot-sizing technique that calculates the order quantity
by comparing the carrying cost and the setup
costs for various lot sizes and then selects the lot
in which these are most nearly equal
Least unit cost method (LUC) - a dynamic
lot-sizing technique that adds ordering and inventory carrying cost for each trial lot size and divides by the number of units in each lot size, picking the lot