After reading the material in this chapter, you should be able to: Understand the concept of capacity and how important it is to manage capacity, explain the impact of economies of scale on the capacity of a firm, understand how to use decision trees to analyze alternatives when faced with the problem of adding capacity, describe the differences in planning capacity between manufacturing firms and service firms.
Trang 1Learning Curves
Trang 2Learning Curves
A learning curve is a line that displays the
relationship between unit production and
cumulative number of units produced
One way of learning is “learning by doing”
As plants produce more, they gain experience in the best production methods, which reduces their costs in
a predictable manner
This is observed as a decline in production costs (by a specific percentage) each time cumulative production doubles
Learning rates are unique and depend upon the nature of
Trang 3Learning Curves
Graphed on a logarithmic scale, the learning curve is a straight line
Trang 4Learning Curve Assumptions
Trang 5Learning Curves
Learning curves can be developed from an
arithmetic tabulation, by logarithms, or some other curve-fitting technique
The improved performance can be thought of
in two ways
Time per unit – shows the decrease in time
required for each successive unit
Output per time period – increase in number of
units produced over a fixed time period
Trang 6Learning Curves
A 90% learning curve implies that each
time cumulative production doubles the cost per unit is reduced by 10%
Differences in learning curves can have
dramatic effects over time!
Trang 7Learning Curves
A logarithmic plot allows linear extrapolation
and more accurate interpretation
Excel: Learning Curve Calculations
Trang 8Learning Curves – Logarithmic
Analysis
The relationship between total number of units produced and learning can be expressed
mathematically
Trang 9Learning Curves – Logarithmic
Analysis
Example
For an 80% learning curve, if the first unit
required 100,000 hours, how many hours will the eight unit require?
Trang 10Learning Curve Tables
When the learning percentage is known,
tables can be used to estimate labor hours for
a specific unit
Multiply the initial unit labor hours by the
appropriate value from the table
Example: With an 80% learning rate, the eighth unit should
take 0.512 times the initial unit time If Y1 = 100,000, Y8 =
100,000(0.512) = 51,200
Trang 11Learning Curve Example
From table 4A.5, with an 80%
improvement ratio unit 11 should take between 0.4765 and 0.4493 times the original time Interpolate to obtain a factor of 0.4629
Trang 12Learning Curve Example
Excel: Learning Curve Calculations
Trang 13Managerial Considerations
Trang 14Managerial Considerations