Lecture 32 - Revision. The contents of this chapter include all of the following: Material requirement planning, nature of demand, inputs to MRP, bill of material, planned orders, net requirement plan, MRP and JIT, lot sizing techniques, maintenance and reliability, reliability, product failure rate, providing redundancy, maintenance cost, total productive maintenance.
Trang 1Revision:
Material Requirement Planning Maintenance and Reliability
Books
• Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming College, Emeritus, Stephen N. Chapman, Ph.D., CFPIM, North Carolina State University, Lloyd M. Clive, P.E., CFPIM, Fleming College
• Operations Management for Competitive Advantage, 11th Edition, by Chase, Jacobs, and Aquilano, 2005, N.Y.: McGrawHill/Irwin.
• Operations Management, 11/E, Jay Heizer, Texas Lutheran University, Barry Render, Graduate School of Business, Rollins College, Prentice Hall
Trang 3Material Requirement Planning
Trang 6– Independent
• Is not related to the demand for any other product and must be forecast
• Master production schedule (MPS) items are independent demand items
– Dependent
• Is directly related to other items or end items
• Such demand should be calculated and need not and should not be forecast
Trang 7Independent Demand
(Forecast)
Dependent Demand (Calculated)
Table
Legs
(4)
Ends (2)
Sides (2)
Top (1) Hardware Kit (1)
If you have an order for 23 Tables, what components
would you need to produce them?
Trang 8Objectives of MRP
Trang 9• The MRP in turn drives,
or is input to, production control (PC) and purchasing
Trang 10• Four Major Inputs:
– Master Production Schedule
Bill of Material
Inventory
Status
Trang 11• Master Production Schedule (MPS)
– The MPS provides information on planned and scheduled orders for end items (how much is wanted and when)
– Inventory status provides information on what is already available. Inventory records include the status of each item, including amounts on order and on hand and the location
Inputs to the MRP System
Trang 12• Bills of Material
– Bills of material describe components and the quantity of each needed to make one unit
– Planning data include lot size, lead time, scrap factors, yield factors, and safety stock
– Computers are needed because they are fast , accurate, and have the
ability to store and manipulate data and produce information rapidly
Inputs to the MRP System
Trang 13“a listing of all the subassemblies, intermediates, parts, and raw materials that go into making the parent assembly showing the quantities of each required to make an assembly”
Trang 14Sides (2)
Trang 15• The multilevel bill is made up of subassemblies. The
subassemblies reflect the way manufacturing plans to build the product.
Trang 16Bills of Material
Trang 17• LowLevel Coding and Netting A component may reside on more than one level in a bill of material
– The lowlevel code is the lowest level on which a part resides in all bills
of material. Every part has only one lowlevel code.
– Lowlevel are determined by starting at the lowest level of a bill of
material and, working up, recording the level against the part. If a part occurs on a higher level, its existence on the lower level has already been recorded.
– Once the lowlevel codes are obtained, the net requirements for each part can be calculated.
Trang 18Bills of Material
Trang 19þList of components, ingredients, and
materials needed to make product
parents
children
Trang 20Std 12” Speaker booster assembly
0
Trang 21Std 12” Speaker booster assembly
+ 2 x number of Cs = (2)(100) + (2)(150) = 500
Trang 22þModular Bills
components that can be assembled into multiple end items
scheduling
Trang 23the BOM
reduce the number of items planned and scheduled
production
Trang 24temporarily
never go into inventory
Trang 25• Lead time: The time from when an order is placed until the part is ready for use.
• Exploding: Multiplying the parent requirements by the usage
quantity through the product tree
• Offsetting: Placing the requirements in their proper time periods based on lead times
Trang 26• The planned order release of the parent becomes the gross
requirement of the component.
Trang 28planned order releases, but it does not (usually) issue
purchase or manufacturing orders or reschedule open orders. Computer software can create exception
messages and suggest types of action
Trang 29planner can release planned orders, reschedule existing orders in or out, or change quantities. In addition, the planner works with other planners, master production schedulers, production activity control, and purchasing
to solve problems as they arise
Trang 30– Planned orders calculated and controlled by the
software
– Released orders scheduled receipts; releasing is the responsibility of the planner
Trang 31item – 50 units of Item A in week 8
40 are actually required – (net requirement)
= (gross requirement - on- hand inventory)
is 40 units – 40 = 50 - 10
Trang 32planned order release for Item A is now 40 units in week 7
units in week 7
net requirement is 65 units in week 7
generates a planned order release of 65 units in week 5
Trang 33generates a planned order release of 65
units in week 5
updated to reflect the use of the 15 items in inventory and shows no on-hand inventory
in week 8
calculation and is the third basic function of the MRP process
Trang 3510 10
Master schedule for B sold directly Periods
Therefore, these are the gross
requirements for B
Periods
Trang 37allowing effective analysis of changes
Trang 38not do detailed scheduling
might actually vary with batch size
batches of material through the
system
Trang 39capacity during normal planning cycles
recognizes actual capacity limits
schedule is created with feasible capacities which facilitates rapid material movement
Trang 401 MRP “buckets” are reduced to daily or hourly
þ The most common planning period (time bucket)
for MRP systems is weekly
2 Planned receipts are used internally to sequence
production
3 Inventory is moved through the plant on a JIT basis
4 Completed products are moved to finished goods
inventory which reduces required quantities for
subsequent planned orders
5 Back flushing based on the BOM is used to deduct
inventory that was used in production
Trang 41required for production based on net requirements
expensive
and MRP systems often deal with unknown and variable demand
Trang 42future orders to determine most
economic lot size
complex dynamic programming
technique
burdensome
Trang 44No on-hand inventory is carried through the system
Total holding cost = $0
There are seven setups for this item in this plan
Total setup cost = 7 x $100 = $700
Trang 46Total cost = setup cost + holding cost
Total cost = (1,404/73) x $100 + (73/2) x ($1 x 52 weeks) Total cost = $3,798
Cost for 10 weeks = $3,798 x (10 weeks/52 weeks) =
$730
Trang 48Combined requirements) Part Periods Setup Holding Total
Trang 51whenever there is a lot size or order
Trang 52process constraints, and purchase lots
considerable distortion of requirements at lower levels of the BOM
is reasonably smooth, PPB,
Wagner-Whitin, or EOQ should give reasonable
results
Trang 53Maintenance and Reliability
Trang 54þ Profits becoming losses
þ Reduced value of investment in plant and
equipment
Trang 55reliability is to maintain the capability
of the system while controlling costs
keeping a system’s equipment in working order
machine will function properly for a specified time
Trang 57Clean and lubricate
Monitor and adjust
Make minor repair
Keep computerized records
Results Reduced inventory Improved quality Improved capacity Reputation for quality Continuous improvement Reduced variability
Trang 60R3 99
R2 80
Trang 61Number of unit-hours of operating time
Mean time between failures
MTBF = FR(N)1
Trang 6220,000 - 1,200 MTBF = = 9,434 hrs 1
.000106
Trang 64Probability of needing second component
Probability
of second component working
Trang 65713 to .94
Trang 66inspection and servicing to keep facilities in good repair
emergency or priority repairs on failed equipment
Trang 67service or is likely to fail
mortality
follows a normal distribution
the decision on when preventive
maintenance should be performed
Trang 68Output Reports
Inventory and purchasing reports
Equipment parts list
Equipment history reports
Cost analysis (Actual vs standard)
Work orders
– Preventive maintenan ce
– Scheduled downtime
– Emergency maintenan ce
Data entry
– Work requests
– Purchase requests
– Time reporting
– Contract work
Trang 69balance preventive and breakdown maintenance costs
consider the true total cost of
breakdowns
Trang 70Total costs
Breakdown maintenance costs
Optimal point (lowest
cost maintenance policy)
Trang 74month with no preventive maintenance
Expected
breakdown cost = Expected number of breakdowns x Cost per breakdown
= (1.6)($300)
= $480 per month
Trang 75Cost of service contract
= (1 breakdown/month)($300) + $150/month
= $450 per month
Hire the service firm; it is less expensive
Trang 76Increasing Repair Capabilities
Trang 77Operator Maintenance department Manufacturer’s field service (return equipment)Depot service
Preventive
maintenance costs less and
is faster the more we move to the left
Competence is higher as we move to the right
Trang 78þ Designing machines that are reliable, easy to
operate, and easy to maintain
þ Emphasizing total cost of ownership when
purchasing machines, so that service and
maintenance are included in the cost
þ Developing preventive maintenance plans that
utilize the best practices of operators,
maintenance departments, and depot service
þ Training workers to operate and maintain their own
machines
Trang 79situations
they are implemented
problems and select course of action
Trang 80End of Lecture 32