1. Trang chủ
  2. » Luận Văn - Báo Cáo

Lecture Principle of inventory and material management - Lecture 5

37 36 0

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 37
Dung lượng 465,38 KB

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Nội dung

Lecture 5 - Master product scheduling. After production planning, the next step in the manufacturing planning and control process is to prepare a master production schedule. This chapter examines some basic considerations in making and managing an MPS. It is an extremely important planning tool and forms the basis for communication between sales and manufacturing.

Trang 1

Master Product Scheduling

Books

• Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming  College, Emeritus, Stephen N. Chapman, Ph.D., CFPIM, North Carolina State University, Lloyd M.  Clive, P.E., CFPIM, Fleming College

• Operations Management for Competitive Advantage, 11th Edition, by Chase, Jacobs, and Aquilano, 2005,  N.Y.: McGraw­Hill/Irwin.

Trang 2

Master product scheduling

Round cut capacity planning

Planning horizons

Trang 4

• The master production schedule is a vital link between sales and production

– It makes possible valid order promises

– It represents a contract between sales and 

production

Trang 7

• Make a preliminary MPS

• Perform rough­cut capacity planning

• Resolve differences

Trang 8

• Rough­cut capacity planning checks whether critical resources are available to support the preliminary 

master schedule

• A resource bill shows the time required for individual items on a critical resource

• What are some possible critical resources?

Trang 9

• The third step in developing an MPS is to resolve any 

differences between the priority plan and available capacity.  Available capacity must be equal to or greater than required  capacity

Trang 10

• The master production schedule must be judged by three criteria

Resources use. Is the MPS within capacity restraints in 

each period of the plan? Does it make the best use of  resources?

Customer service. Will due dates be met and will 

delivery performances be acceptable?

Cost. Is the plan economical, or will excess cost be 

incurred for overtime, subcontracting, expediting, or  transportation?

Trang 11

• An MPS is not a sales forecast, it is instead a  forecast of production. It may not necessarily 

Trang 12

• As orders are received, they “consume” available  production and inventory

• Any part not consumed is available­to­promise

Customer Orders

Promise Time

Trang 13

• Available­to­Promise is

– the uncommitted portion of a company’s inventory 

and planned production, maintained in the master schedule to support customer order promising. The ATP quantity is the uncommitted inventory balance 

in the first period and is normally calculated for each period in which an MPS receipt is scheduled

    APICS Dictionary, 8th edition

Trang 14

• The ATP calculation assumes that the entire ATP  will be sold before the next scheduled receipt. 

When calculating ATP, consider all orders until  the next scheduled receipt.

ATP for period 1 = on hand ­ customer orders due  before next MPS scheduled receipt

ATP for periods 2, 4, and 6 = MPS scheduled 

receipt ­ customer orders due before next MPS 

scheduled receipt

Trang 19

The planning horizon is defined as

the amount of time the master schedule extends into the 

future. This is normally set to cover a minimum of cumulative lead time plus time for lot sizing low­

level components and for capacity changes of primary work centers or of key suppliers

APICS Dictionary, 8th edition

Trang 20

✦ What is the minimum planning

horizon in this example?

= 16 weeks

Trang 21

Actual and Forecast

(Trade-offs)

Forecast Only (Changes constrained

PlanningTimeFence

Trang 22

Master Production Scheduling (MPS)

Trang 23

• Determine the quantity and timing of completion of end items over a short­range planning horizon

• Schedule end items (finished goods and parts shipped 

as end items) to be completed promptly and when 

promised to the customer

• Avoid overloading or underloading the production facility so that production capacity is efficiently 

utilized and low production costs result. 

Trang 24

2­4 weeks

4­6 weeks

6+  weeks

Time Fences

Trang 25

• The rules for scheduling:

– Do not change orders in the frozen zone

– Do not exceed the agreed on percentage changes when modifying orders in the other zones

– Try to level load as much as possible

– Do not exceed the capacity of the system when 

promising orders

– If an order must be pulled into level load, pull it into the earliest possible week without missing the promise

Trang 26

•  . . more

Trang 27

• Schedulers must:

– estimate the total demand for products from all sources

– assign orders to production slots

– make delivery promises to customers, and

– make the detailed calculations for the MPS

Trang 28

Arizona Instruments produces bar code scanners for consumers and other manufacturers on a produce­to­stock basis.  The production planner is developing an 

MPS for scanners for the next 6 weeks

The minimum lot size is 1,500 scanners, and the safety stock level is 400 scanners.  There are currently 1,120 scanners in inventory.  The estimates of demand for scanners in the next 6 weeks are shown on the next slide

Trang 29

0 50 300 1000

0 0

500 400

200

0 0

0

300 500

0 10

0

700

6 5

1000 200

WEEK

Trang 30

0 50 300 1000

0 0

500 400

200

0 0

0

300 500

0 10

0

700

6 5

1000 200

410 560

1500 410 1350

1160 1500

900 560

700

1250 950

460

460 1160

1500 1500

0

1010 1200

950

Trang 32

• As orders are slotted in the MPS, the effects on the production work centers are checked

• Rough cut capacity planning identifies underloading 

or overloading of capacity

Trang 33

Texprint Company makes a line of computer printers on a produce­to­stock basis for other computer manufacturers.  Each printer requires an average of 24 labor­hours.  The plant uses a backlog of orders to allow 

Trang 34

UNDER or OVER LOAD 2600 200 200 1000 1720 280

Trang 35

• Rough­Cut Capacity Analysis

– The plant is underloaded in the first 3 weeks 

(primarily week 1) and it is overloaded in the last 2 weeks of the schedule

– Some of the production scheduled for week 4 and 5 should be moved to week 1

Trang 36

• Review customer orders and promise shipment of orders as close to request date as possible

• Planning horizon must be as long as the longest lead time item

Trang 37

End of Lecture 5

Ngày đăng: 21/09/2020, 14:04

TỪ KHÓA LIÊN QUAN

TÀI LIỆU CÙNG NGƯỜI DÙNG

TÀI LIỆU LIÊN QUAN

🧩 Sản phẩm bạn có thể quan tâm